B. v. GERMANY
Doc ref: 15720/89 • ECHR ID: 001-45533
Document date: September 8, 1992
- Inbound citations: 0
- •
- Cited paragraphs: 0
- •
- Outbound citations: 2
EUROPEAN COMMISSION OF HUMAN RIGHTS
FIRST CHAMBER
APPLICATION No. 15720/89
B.
against
the
FEDERAL REPUBLIC OF GERMANY
REPORT OF THE COMMISSION
(adopted on 8 September 1992)
TABLE OF CONTENTS
Page
I. INTRODUCTION
(paras. 1 - 5). . . . . . . . . . . . . . . . . . . . . . . . 1
II. ESTABLISHMENT OF THE FACTS
(paras. 6 - 36) . . . . . . . . . . . . . . . . . . . . . . . 2
III. OPINION OF THE COMMISSION
(paras. 37 - 54). . . . . . . . . . . . . . . . . . . . . . . 6
A. Complaint declared admissible
(para. 37) . . . . . . . . . . . . . . . . . . . . . . . 6
B. Point at issue
(para. 38) . . . . . . . . . . . . . . . . . . . . . . . 6
C. Compliance with Article 6 para. 1 of the Convention
(paras. 39 - 53) . . . . . . . . . . . . . . . . . . . . 6
CONCLUSION
(para. 54). . . . . . . . . . . . . . . . . . . . . . . . . . 8
APPENDIX : Decision on the admissibility of the application . . . . 9
I. INTRODUCTION
1 The present Report concerns Application No. 15720/89 by B.
against the Federal Republic of Germany, introduced on 19 July and
registered on 30 October 1989.
The applicant, born in 1936, is a German national and resident
in Munich.
The Federal Republic of Germany are represented by their
Agent, Mr. J. Meyer-Ladewig, Ministerialdirigent, of the Federal
Ministry of Justice.
2 The application concerns the length of court proceedings
instituted by the applicant against his employer. The application
was communicated to the Government on 7 January 1991. On
27 May 1991 the application was referred to a Chamber. Following an
exchange of memorials, the complaint relating to the length of
proceedings (Article 6 para. 1 of the Convention) was declared
admissible on 9 December 1991. The decision on admissibility is
appended to this Report. Application No. 20580/92 deals with the
applicant's further complaint about the alleged lack of impartiality
of Judges involved in the above proceedings.
In the present case, the applicant submitted further
observations on 22 and 23 January, 31 March, 2 May and 2 June 1992.
3 Having noted that there is no basis upon which a friendly
settlement within the meaning of Article 28 para. 1 (b) of the
Convention can be secured, the Commission (First Chamber), after
deliberating, adopted this Report in accordance with Article 31
para. 1 of the Convention, the following members being present:
MM. F. ERMACORA, Acting President of the First Chamber
J.A. FROWEIN
E. BUSUTTIL
A.S. GÖZÜBÜYÜK
Sir Basil HALL
Mr. C.L. ROZAKIS
Mrs. J. LIDDY
MM. M. PELLONPÄÄ
B. MARXER
4 In this Report the Commission states its opinion as to whether
the facts found disclose a violation of the Convention by the
Federal Republic of Germany.
5 The text of the Report is now transmitted to the Committee of
Ministers of the Council of Europe, in accordance with Article 31
para. 1 of the Convention.
II. ESTABLISHMENT OF THE FACTS
6 In 1979 a dispute arose between the applicant and his
employer, a company producing motors and turbines, concerning the
compensation due for the invention of a steering mechanism patented
in the Federal Republic of Germany, Italy and the United Kingdom.
7 On 18 May 1979 the applicant instituted proceedings before the
Arbitration Committee (Schiedsstelle) of the German Patent Office
(Patentamt) under the Employees' Invention Act (Arbeitnehmererfin-
dungsgesetz). The arbitration proceedings, including a proposal for
settlement made by the Arbitration Committee on 26 March 1980, which
was served upon the applicant in April 1980, were to no avail.
8 On 23 December 1980 the applicant, represented by counsel,
filed an action for compensation with the Munich I Regional Court
(Landgericht). He requested the Court to fix the appropriate amount
of compensation which he considered should be DM 1.8 million minimum
and DM 3 million maximum.
9 In January 1982 the Regional Court decided to take extensive
expert evidence, and appointed the experts Prof. G. and Prof. W. in
agreement with both parties in April 1982.
10 The expert G. delivered his opinion on 8 December 1982. On
21 January 1983 the applicant requested the Regional Court to
expedite the proceedings. The expert W. delivered his opinion on
30 June 1983. Following further submissions by the parties, the
expert opinions were amended in November and December 1983.
11 On 13 December 1983 the Regional Court heard the parties and
the two experts.
12 On 13 March 1984 the Regional Court ordered the defendant
company to pay the applicant DM 1,381,403 with interest. It also
declared that the defendant was obliged to pay compensation for the
future use of the applicant's invention. The remainder of the
applicant's action, which had been amended several times and in
particular increased to a compensation claim of some DM 18 million
with interest, was dismissed. The Regional Court, in its judgment
comprising 63 pages, found in particular that the applicant was
entitled to compensation for his invention under S. 9 of the
Employees' Invention Act. The amount of compensation was fixed with
regard to the value of the applicant's invention in relation to the
defendant's sales in this respect.
13 In April 1984 both parties lodged appeals (Berufungen) with
the Munich Court of Appeal (Oberlandesgericht).
14 On 22 May 1984 the 6th Chamber of the Court of Appeal fixed a
hearing for 7 March 1985. In May and June 1984 the parties filed
the reasons for their respective appeals, and they made further
submissions in the period between November 1984 and February 1985.
15 On 12 February 1985 the Deputy of the Presiding Judge declared
himself biased. On 27 February 1985 the Court of Appeal accepted
his declaration.
16 The Court of Appeal held a hearing on 7 March 1985. On
25 March 1985 it inquired with the parties whether or not, having
regard to the increasing procedural costs and the constitutional
complaint (Verfassungsbeschwerde) envisaged by the defendant, the
proceedings should be continued. The parties subsequently informed
the Court that they wished to continue the proceedings.
17 At a hearing on 23 May 1985 the Court of Appeal ordered that
expert evidence be taken as regards the parties' submissions upon
appeal. Prof. W. and Prof. G. were again appointed.
18 On 30 May 1985 the applicant requested the Presiding Judge at
the Court of Appeal to further the proceedings.
19 On 19 June 1985 the files were sent to the expert W.
Following inquiries about his fees, the Court of Appeal requested W.
to start preparing his expert opinion on 18 September 1985, and sent
a reminder on 12 December 1985. On 12 March 1986 the expert W.
informed the Court that he was seriously ill. On 20 March 1986 the
Court of Appeal informed the parties that it intended to instruct
the expert G. to deliver his opinion first. Thereupon, in
April 1986 the applicant proposed to stop the taking of evidence and
to fix a hearing; and the defendant opposed an expertise by G. and
proposed another expert.
20 On 15 September 1986 the applicant again requested the Court
to expedite the proceedings. On 17 October 1986 he was informed
that due to illness of one judge no date for a hearing could be
fixed.
21 On 21 January 1987 the Court of Appeal proposed a settlement
of the case on the basis of DM 1.5 million. If the parties should
not agree, further extensive evidence would have to be taken.
22 At the next hearing on 14 May 1987 the Court's proposal for a
settlement was not accepted by the parties.
23 On 19 May 1987 the Court of Appeal asked the expert W. whether
he would again deliver an opinion. W. refused for health reasons on
28 May 1987.
24 On 1 June 1987 the applicant again urged the Court of Appeal
to render a judgment soon.
25 On 25 June 1987 the Court of Appeal ordered that further
expert evidence be taken and appointed the expert F. On 3 July 1987
the applicant objected to the appointment of the expert F. in view
of alleged contacts between F. and the defendant. On 28 August 1987
the files were transmitted to the expert F. He delivered his
opinion on 12 November 1987.
26 Between 24 November 1987 and 1 July 1988 the applicant three
times unsuccessfully challenged the expert F. for bias. On
22 September 1988 the Court of Appeal ordered another expert opinion
and invited the parties to propose an expert to be appointed. The
parties apparently agreed on two possible experts.
27 On 29 November 1988 the Court of Appeal proposed a settlement
of the case on the basis of the payments made by the defendant so
far, i.e. about DM 1.5 million.
28 On 6 February 1989 the Court of Appeal informed the parties
that another expert, namely Dr. S., had been asked to deliver the
expert opinion. The applicant objected to the appointment of Dr. S.
and challenged the judges of the 6th Chamber for bias. His motion
was dismissed by the 29th Chamber at the Court of Appeal on
22 March 1989.
29 On 6 April 1989 the applicant challenged the judges of the 6th
and 29th Chamber for bias. His motions were dismissed in May 1989.
30 On 7 June 1989 the Court of Appeal appointed Prof. M., one of
the two experts agreed by the parties. Prof. M. refused to deliver
an opinion.
31 On 11 July 1989 the Federal Constitutional Court (Bundes-
verfassungsgericht) refused to admit the applicant's constitutional
complaint dated 28 December 1988 concerning the length of the
proceedings. The Constitutional Court found that for the time being
the conduct of the proceedings by the Court of Appeal could not be
objected to, although it had not yet rendered a judgment.
32 The Constitutional Court recalled its jurisprudence according
to which there was a right to have court proceedings terminated
within a reasonable time. However, in examining the reasonableness
of the length in the particular circumstances of the case, the
Constitutional Court could not examine each procedural step, as
every court had to deal with numerous cases, and this necessarily
resulted in delays of the separate proceedings.
33 In the applicant's case the Constitutional Court considered
that it was not required to examine the delay before the hearing in
March 1985, which had been due to the Appellate Court's workload,
because the applicant had not expressly raised this issue. In any
case, the Chamber concerned had in the meantime been unburdened.
Furthermore, the late statement of the Presiding Judge's Deputy
about his being biased had not resulted in any delays. The length of
the proceedings was essentially due to the fact that the Court of
Appeal considered extensive taking of evidence necessary, which did
not appear arbitrary. The taking of evidence in successive steps
could not be objected to on the ground that the necessity of further
evidence in some respects depended upon the outcome of an earlier
taking of evidence. Moreover, the renewed recourse to expert
evidence could not be objected to. The delays in taking the expert
evidence could not be avoided, or were partly caused by the conduct
of the parties.
34 Finally, the Constitutional Court held that, though a
violation of constitutional law could not be found for the time
being, the proceedings before the Court of Appeal, which had already
lasted five years, had attained an unusual and, as a rule,
unacceptable length. In view of the length of the proceedings at
first instance, namely more than three years, this was even less
acceptable. The Court of Appeal would have to ensure that these
proceedings be terminated soon and, if necessary, give them
precedence.
35 On 18 August 1989 the Munich Court of Appeal again appointed
Dr. S. as expert. Thereupon, the applicant again challenged the
judges of the 6th Chamber for bias, objected to the appointment of
Dr. S. and challenged him for bias. His motions were dismissed in
October and November 1989, respectively.
36 At a hearing on 4 May 1990 the applicant and the defendant
entered into a settlement of the dispute, which provided in
particular for a payment of DM 1.8 million in view of the
applicant's compensation claim and the termination of his
employment.
III. OPINION OF THE COMMISSION
A. Complaint declared admissible
37 The Commission has declared admissible the applicant's
complaint that his case was not heard within a reasonable time.
B. Point at issue
38 The only point at issue is whether the length of the
proceedings complained of exceeded the "reasonable time" referred to
in Article 6 para. 1 (Art. 6-1) of the Convention.
C. Compliance with Article 6 para. 1 (Art. 6-1) of the Convention
39 Article 6 para. 1 (Art. 6-1) of the Convention includes the
following provision:
"In the determination of his civil rights and obligations ...,
everyone is entitled to a ... hearing within a reasonable time
by (a) ... tribunal ..."
40 The proceedings in question concerned the applicant's
compensation claims under the Employees Invention Act. The purpose
of the proceedings was to obtain a decision in a dispute over "civil
rights and obligations", and they accordingly fell within the scope
of Article 6 para. 1 (Art. 6-1) of the Convention.
a. Relevant period to be considered
41 The Government submit that the applicant brought his civil
action before the Munich I Regional Court on 23 December 1980. His
proceedings before the Arbitration Committee of the German Patent
Office could only be taken into account to the extent of six months,
as under the Employees Invention Act a civil suit could be brought
six months after having instituted proceedings before the
Arbitration Committee.
42 The Commission recalls that in civil matters the relevant time
may begin to run even before the issue of the writ commencing court
proceedings, if the plaintiff could not seize the competent court
before having preliminary proceedings terminated (Eur. Court H.R.,
König judgment of 28 June 1978, Series A no. 27, p. 33, para. 98).
43 The Commission notes that in the present case the applicant
had to submit the dispute concerning his invention first to an
Arbitration Committee under the Employees Invention Act. These
proceedings lasted from 18 May 1979 until 26 March 1980, i.e. about
ten months.
44 The Commission considers that the applicant could reasonably
await the termination of the arbitration proceedings with a detailed
proposal by the Arbitration Committee in order to possibly avoid
court proceedings. The relevant period under Article 6 para. 1
(Art. 6-1) therefore covers the arbitration proceedings in question.
45 The period to be considered thus started on 18 May 1979 and
lasted until the date of the settlement achieved in the course of
the appeal proceedings on 4 May 1990, i.e. almost eleven years
later.
b. The reasonableness of the length of the proceedings
46 The Government consider in particular that the proceedings
were extremely complicated, and involved the taking of special
expert evidence on very difficult technical matters. Moreover, the
applicant himself contributed to the prolongation of the proceedings
by submitting a large number of written pleadings and making use of
various remedies. The domestic courts were faced with a difficult
task. They did not remain inactive over any significant period of
time. The Government refer also to the findings of the Federal
Constitutional Court in its decision of 11 July 1989.
47 The applicant criticises mainly the conduct of the proceedings
by the Munich Court of Appeal. He submits that the Court of Appeal
had planned a total length of the appeal proceedings of eighteen to
twenty years and, moreover, decided to repeat the taking of
evidence.
48 The Commission recalls that the reasonableness to the length
of proceedings must be assessed in the light of the particular
circumstances of the case. In the present case, which was
terminated by settlement after almost eleven years, those
circumstances call for a global assessment (cf. Eur. Court H.R.,
Obermeier judgment of 28 June 1990, Series A no. 179, p. 23,
para. 72; Brigandi judgment of 19 February 1991, Series A no. 194-B,
p. 31, para. 30).
49 The Commission considers that the applicant's case was of
great complexity, as his compensation claim raised difficult factual
issues related to the technical aspects of his invention, the
patents concerned as well as the value of its use by his employer.
50 The Commission further considers that the parties' conduct is
not in itself sufficient to explain the length of the proceedings.
In this respect, the Commission notes in particular that the
applicant contributed to the overall length of the proceedings in
that he did not institute his action before the Munich I Regional
Court more than seven months after termination of the arbitration
proceedings. It does not appear that the parties, in other
respects, unduly delayed the proceedings. Moreover, the applicant
repeatedly asked for an expeditious handling of his case.
51 As regards the conduct of the German judicial authorities, the
Commission notes that the initial arbitration proceedings were
terminated within ten months. The proceedings before the
Munich I Regional Court lasted from 23 December 1980 until
13 March 1984, i.e. three years and two and a half months. The
appeal proceedings before the Munich Court of Appeal lasted more
than six years, namely from 9 April 1984 until 4 May 1990. The
Commission considers that major delays occurred at first and second
instance in fixing hearings and in taking expert evidence.
52 The Commission, bearing in mind that when the proceedings
terminated with a settlement, the Court of Appeal had again entered
into an extensive taking of evidence and no decision on the merits
was in sight, finds that no convincing explanation of the delays has
been advanced by the respondent Government.
53 In these circumstances, the Commission finds that the length
of the proceedings complained of exceeded the "reasonable time"
referred to in Article 6 para. 1 (Art. 6-1) of the Convention.
CONCLUSION
54 The Commission concludes, unanimously, that there has been a
violation of Article 6 para. 1 (Art. 6-1) of the Convention.
Secretary Acting President
to the First Chamber of the First Chamber
(M. de SALVIA) (F. ERMACORA)
LEXI - AI Legal Assistant
