KOCENIAK v. POLAND
Doc ref: 1733/06 • ECHR ID: 001-145668
Document date: June 17, 2014
- 4 Inbound citations:
- •
- 5 Cited paragraphs:
- •
- 14 Outbound citations:
FOURTH SECTION
DECISION
Application no . 1733/06 Zbigniew KOCENIAK against Poland
The European Court of Human Rights (Fourth Section), sitting on 17 June 2014 as a Chamber composed of:
Ineta Ziemele , President, George Nicolaou , Ledi Bianku , Nona Tsotsoria , Zdravka Kalaydjieva , Paul Mahoney , Krzysztof Wojtyczek , judges, and Françoise Elens-Passos , Section Registrar ,
Having regard to the above application lodged on 12 December 2005,
Having regard to the observations submitted by the respondent Government and the observations in re ply submitted by the applicant,
Having deliberated, decides as follows:
THE FACTS
1. The applicant, Mr Zbigniew Koceniak, is a Polish national, who was born in 1963 and lives in Mielec. He is rep resented before the Court by Ms A. Ż uraniewska, a lawyer practising in Kraków.
2. The Polish Government (“the Government”) are represented by their Agent, Mrs J. Chrzanowska of the Ministry of Foreign Affairs.
A. The circumstances of the case
3. The facts of the case, as submitted by the parties, may be summarised as follows.
4 . On 16 February 1994 the Mielec Municipal Office ( Urząd Gminy ) issued a building permit allowing the applicant ’ s neighbour, H.K., to construct a storehouse ( budnek inwentarsko-składowy ) and a midden ( gnojownia ) on her land adjacent to the applicant ’ s plot. It was specified that the building should be situated along the boundary between the plots, half a metre from the applicant ’ s land. It was further required that the walls facing the applicant ’ s property should be without windows or doors and that rainwater should run off onto H.K. ’ s land. It appears that on an unspecified date in 1993 another of the applicant ’ s neighbours, K.Ś., obtained a similar construction permit concerning her land.
B. The applicant ’ s administrative complaints against his neighbours
1. First complaint to the Mielec District Office
5 . On 11 October 1996 the applicant wrote to the Mielec District Office (UrzÄ…d Rejonowy) to complain that H.K. and K.Åš. had constructed on their land large buildings serving as slaughterhouses (ubojnia) and meat ‑ processing plants (masarnia) . The applicant submitted, inter alia , that H.K. ’ s building was too close to his property and that rainwater from her roof ran off directly onto his land. He maintained that the neighbours ’ activities were a nuisance to him and his family.
6 . On 17 October 1996 the Mielec District Office sc heduled an inspection of the properties concerned , which was carried out on 28 October 1996. It was established that H.K. ’ s building on the land adjacent to the applicant ’ s was being constructed in accordance with the building permit issued on 16 February 1994 by the Mayor of the Mielec Municipality . It was further established that despite the fact that the building had not yet been completed, H.K. was already using it as a meat ‑ processing plant. H.K. was fined in the amount of 50 . 00 zlotys ( PLN ) . [1]
7 . As regards the property of K.Åš., the applicant submitted that he had not been informed of the result of the relevant inspection or the course of the administrative proceedings which had followed. This was so because the authorities considered that he had no legal interest in the outcome of th o se proceedings since her land did not directly adjoin his .
8 . On 15 November 1996 the Mielec District Office ordered that the construction work on H.K. ’ s land be stopped. The order was to remain valid for two months and a new decision as to the continuation of the work was to be issued before its expiry. Subsequently, on 18 December 1996 the Mielec District Office ordered H.K. to submit, by 30 June 1997, certain technical documents concerning the construction . The authority informed her that if she wanted to use the building as a meat-processing plant , she would have to apply for so - called “ initial planning permission ” (decyzja w sprawie warunków zabudowy i zagospodarowania terenu). It was further established that the dimensions of the building were smaller than those stipulated by the original building permit of 16 February 1994; windows and doors had been placed in different places ; the rainwater draining system was inadequate, mainly because the building was situated very close to the boundary between the plots ; and the build ing was already being used as a slaughterhouse and a meat ‑ processing plant.
9 . On 21 December 1996 the Mielec District Office issued a similar decision in respect of K.Ś . ’ s land. The decision was subsequently quashed by the Rzeszów Governor. On 18 May 1998 the National Building Inspector upheld the Governor ’ s decision .
10 . On 12 June 1997 the Mielec Dis trict Sanitary Inspector gave a positive opinion with regard to the sanitation of the building on H.K. ’ s property. The i nspector considered that the modification of the use of that building as a slaughterhouse and meat-processing plant was legally permitted, on condition that a maximum of 50 porkers were slaughtered per month. On 8 July 1998 the Rzeszów Regional Sanitary Inspector ate quashed that decision .
11 . Following a request by the applicant, on 8 June 1998 the Mielec District Office summoned the applicant and H.K. to another inspection of H.K. ’ s property to be carried out on 29 June 1998. It was established during that inspection that H.K. had failed to comply with the terms of the original building permit. On 16 July 1998 the Mielec District Office asked the Minor Offences Adjudicative Board to impose a fine on her.
2. Second complaint to the Mielec District Office
12 . On 26 June 1997 the applicant complained to the Mielec District Office that his neighbours had not ceased their business activities. He submitted that H.K. ’ s company was slaughtering approximately ten animals per day and continuing the meat - processing activities. He asked for an expert in environmental matters to be appointed to inspect the property. In reply, on 15 July 1997 the Mielec District Office informed the applicant that the deadline which had been set for H.K. to submit the relevant technical documents (see paragraph 8 above) would expire on 30 November 1997 and that the proceedings had therefore been stayed until that date.
13 . By way of a decision given on 29 August 1997 , the Rzeszów Governor ordered H.K. to submit, within four months, an environmental impact assessment of the slaughterhouse and meat-processing plant, referring to an o rdinance of 13 May 1995 issued by the Minister for Environmental Protection, Natural Resources and Forestry.
14 . On 5 November 1997 the Mielec District Office warned H.K. that non ‑ compliance with the deadline for submission of the documents which she was obliged to submit could lead to criminal sanctions under the Construction Act 1994 (Prawo budowlane) (“the 1994 Act”).
15 . On 12 November 1997 H.K. submitted the environmental impact assessment in respect of her slaughterhouse and meat-processing plant to the r egional o ffice of the Department of Environment al Protection.
3. Complaints to the Rzeszów Governor
16 . In his letter of 18 September 1997 the applicant asked the Rzeszów Governor to carry out an environmental impact assessment of H.K. ’ s business. He complained that H.K. and K.Ś. were running two slaughterhouses and meat-processing plants , which were causing pollution and posed a real risk to the health of the neighbourhood. He stressed that his complaints to the Mielec Municipal Office and District Office, the Rzeszów Regional Sanitary Inspectorate (Państwowy Wojewódzki Inspektorat Sanitarny ) and the Rzeszów Veterinary Hygiene Inspectorate ( Wojewódzki Weterynaryjny Inspektorat Sanitarny) had been to no avail. On 3 October 1997 the Governor ’ s Office forwarded the letter to the Regional Environmental Protection Inspectorate and on 8 October 1997 asked the Regional Veterinary Hygiene Inspector ate to inform the Governor ’ s Office and the applicant about the measures taken as a result of his complaint .
17 . On 16 October 1997 the Regional Veterinary Hygiene Inspector ate informed the applicant that on 29 April 1997 the Mielec District Veterinary Surgeon ( Powiatowy Lekarz Weterynarii ) and the State Sanitary Inspectorate had conducted an on-site inspection of the company and established that the applicant ’ s allegations were unfounded. The inspectors had no objections to the sanitation of the sites. T he liquid sewage was drained to concrete containers with covers and removed by a waste-disposal company at least once per week. The owners had been keeping records of the water used and sewage removed from the premises.
18 . On 29 October 1997 the Regional Environment al Protection Inspectorate informed the r egional o ffice of the Department of Environmental Protection that four inspections had been carried out on the sites of both companies between October 1996 and May 1997. As a result, certain obligations had been imposed on the owners in order to rectify any irregularities identified during the inspections. Otherwise, the inspectors had found that the companies had been complying with the applicable environmental requirements. In particular, the bacteriological soil tests confirmed that the land had not been contaminated and that no danger to health or the environment could originate from it.
4. Application for demolition of buildings built by K.Åš. and H.K.
19 . On 9 February 1998 the applicant applied to the Mielec District Office for an order to demolish the buildings constructed by K.Åš. and H.K. on their plots. He argued that the buildings did not comply with the original building permits issued in 1993 and 1994. On 12 March 1998 the Rzeszów Governor informed the applicant that he had enquired into why the first ‑ instance authority had not yet enforced decisions concerning the illegal construction on H.K. ’ s land.
20 . On 28 April 2000 the Mielec District Office informed the applicant that section 48 of the 1994 Act, which provided for the demolition of buildings constructed in breach of building permits , was not applicable to the buildings on K.Ś. ’ s and H.K. ’ s property. This was so essentially because the local land development plan allowed for the type of business activity conducted in th o se buildings. A demolition order could not therefore be issued in respect of th o se buildings.
C. Proceedings instituted by H.K. with a view to legalising her meat ‑ processing business
21 . On 25 November 1997 H.K. lodged an application for retrospective permission to use the building on her property as a slaughterhouse and meat-processing plant (postÄ™powanie w sprawie zalegalizowania poprzez wydanie pozwolenia na użytkowanie budynku gospodarczego za zmianÄ… sposobu uzytkowania jego części na rzeźniÄ™ ‑ masarniÄ™ wybudowanego niezgodnie z pozwoleniem) . She submitted the documentation requested on 18 December 1996 by the Mielec District Office (see paragraph 8 above). On 16 January 1998 the Rzeszów Governor ’ s Office ( UrzÄ…d Wojewódzki ) informed her that under the Environment al Protection Act of 29 August 1997 ( Ustawa z dn. 29.08.1997 o zmianie ustawy o ochronie i ksztaÅ‚towaniu Å›rodowiska ) (“the 1997 Act”) she was obliged to lodge her application for a retrospective permit with the Mielec District Office. It was pointed out that the new application should contain a report on the environmental impact of her business activities.
22 . On 10 February 1998 the Mielec District Office informed H.K. that her application could not be examined as it did not meet the formal requirements. On 17 February 1998 H.K. renewed her application. On 11 March 1998 the Mielec District Office, having noted that the building on her land did not comply with th e original building permit, requested an expert opinion from the Rzeszow Regional Office as to the compatibility of the meat-processing plant with the provisions of the 1997 Act .
23 . On 7 April 1998 the Director of the Environment al Protection Department of the Rzeszow Governor ’ s Office ( Wydział Ochrony Środowiska Urzędu Wojewódzkiego) refused H.K. ’ s application for a retrospective conversion permit on the grounds that her business plan was flawed. It was further noted that appropriate tests should be performed to assess the environmental impact of her business activities on the neighbourhood. On 8 June 1998 the Mielec District Office requested another expert opinion from the Rzeszow Regional Office as to the compatibility of that business with the requirements of the environmental legislation .
24 . On 29 June 1998 the Rzeszów Regional Office ordered H.K. to submit, by 15 July 1998, supplementary documents concerning her company (concerning, inter alia , the results of soil contamination tests, noise levels caused by the operation of the plant and the waste disposal survey). On 15 July 1998 she complied with that order. On 23 July 1998 she informed the Rzeszów Regional Office that the r egional a gronomy l aboratory had been commissioned to carry out the soil contamination test. However, the test could not be carried out because the applicant had not allowed soil samples to be taken from his property. Subsequently, samples were taken from H.K. ’ s property close to the boundary with the applicant ’ s property.
25 . On 29 July 1998 the d irector of the e nvironment al p rotection d epartment of the Rzeszów Governor ’ s Office issued an administrative decision declaring that H.K. ’ s business activity was compatible with the requirements of the environmental legislation . It was held that it had not caused any environmental degradation and its continuation was un likely to pose any environmental risks in the future. The meat-processing plant fulfilled the requirements laid down by environmental protection regulations. In particular, its operation did not exceed permissible levels of pollution and noise , and the waste and sewage - disposal system worked properly. On 10 August 1998 the applicant appealed against that decision to the Minister for Environmental Protection, Natural Resources and Forestry.
26 . On 17 March 1999 the Minister quashed the contested decision , stating that under new environmental legislation that had entered into force on 1 August 1998 ( when the proceedings were ongoing) it was no longer necessary to determine whether the plant complied with environmental requirements, essentially because the plant could not be qualified as being particularly harmful to the environment and/or human health. The proceedings were therefore discontinued.
27 . On 8 June 1998 the Mielec District Office scheduled an inspection of H.K. ’ s property. On 23 June 1998 the applicant informed the Office that H.K. had continued the construction work. On 28 June 1998 the inspection was carried out. There were no signs of ongoing construction work at that time. It was established that H.K. had continued to run her meat-processing business in the unfinished building. On 21 July 1998 the Mielec District Office ordered H.K. to refrain from us ing her slaughterhouse and meat ‑ processing plant , since the building was considered an illicit construction ( samowola budowlana ). H.K. appealed. On 7 September 1998 the Rzeszów Governor quashed the contested decision and remitted the case to the first ‑ instance authority.
28 . On 23 November 1998 the Mielec District Office stayed the proceedings ex officio because H.K. had, in the meantime, applied to have her case decided under the legal provisions applicable at the time when the construction work had stopped . On 3 December 1998 the applicant lodged an interlocutory appeal against that decision. On 14 January 1999 the Rzeszów Governor quashed the contested decision and remitted the case to the first-instance authority. On 18 April 2000 the District Building Inspector ate ( Rejonowy Inspektor Nadzoru Budowlanego) informed the Mielec District Office that H.K. had complied with the requirements imposed on her by the decision of 18 December 1996 (see paragraph 8 above).
29 . On 2 May 2000 the Mielec District Office issued a decision authorising H.K. to run her business on her property (decision No. AB 7353/16/00). The applicant appealed. On 23 August 2000 the Podkarpacki Governor quashed the first-instance decision and refused to issue the permit sought (no. AB V 7114/12/1/00). On 23 October 2002 the Supreme Administrative Court quashed both the first and second-instance decisions. It referred to the number of proceedings conducted in H.K. ’ s case and found that all of them, including the proceedings concerning the request for retrospective permission to use the building as a meat - processing plant should have been dealt with by the District Building Inspector ate .
30 . On 21 June 2004 the Mielec District Office gave a positive opinion with regard to the partial use of the building on H.K. ’ s property as a slaughterhouse and meat-processing plant. It had regard to a report concerning that business ’ s environmen tal impact. By a decision of 29 November 2004 the Podkarpacki Regional Building Inspector ate ( Wojewódzki Inspektor Nadzoru Budowlanego ) authorised H.K. to use part of the building for meat-processing activities (decision No. 79/2004). On an unspecified date the applicant appealed against that decision. On 20 April 2009 the Regional Building Inspector ate quashed the contested decision and remitted the case to the first-instance authority. The applicant and H.K . appealed. On 29 July 2009 the Rzeszów Regional Administrative Court rejected the applicant ’ s appeal. On 12 October 2009 the c ourt rejected H.K. ’ s appeal.
31. A number of decisions given in subsequent proceedings were quashed upon appeal and the case was remitted to the first ‑ instance authority. On 15 February 2011 the local Building Inspector ate again authorised H.K. to use part of the building for meat-processing activities. This decision was quashed upon appeal. The owner was ordered to submit an expert opinion on the technical state of the building. In the proceedings conducted afterwards H.K . acknowledged, in December 2013, that she had been conducting meat processing business in a building which had never been certified as suitable for these purposes within the meaning of construction laws. On 17 January 2013 the local Building Inspectorate ordered the owner to cease operation of her business. This decision was subsequently quashed and the proceedings were discontinued. The applicant ’ s efforts to have them reopened remain unsuccessful. In the relevant correspondence the authorities stated repeatedly that in his complaints the applicant had failed to make it clear what procedural steps should be taken by the authorities in respect of the decision to discontinue the proceedings.
D. Proceedings concerning the application to pursue the construction on H.K. ’ s land
32 . By a decision of 18 December 1996 (see paragraph 8 above) the h ead of the Mielec District Office ordered H.K. to apply for a permit to continue construction of the storehouse. On 21 July 1999 the District Building Inspector ate discontinued the proceedings, finding that they had become devoid of purpose given that the construction had been finalised. On 14 October 1999 the Podkarpacki Regional Building Inspector ate quashed that decision as premature and remitted the case to the first ‑ instance authority.
33 . On 2 December 2002, in accordance with the Supreme Administrative Court ’ s judgment o f 23 October 2002 (see paragraph 29 above), the Mielec District Office transmitted the case file to the District Building Inspector ate. On 4 February 2003 the i nspector summoned H.K. and the applicant to participate in an administrative hearing and inspection of H.K. ’ s property. By a decision of 6 May 2003 the District Inspector ate ordered H.K. to stop using the storehouse for meat-production purposes, having noted that she had not obtained the relevant retrospective permission (decision No. NB 7355/38/99-03). On 29 July 2003 the Podkarpacki Regional Building Inspector ate upheld that order (decision No. OA 7144/12/14/03).
34 . On 7 October 2003 the authority inspected H.K. ’ s property. It was established that she had continued to use the building for meat-processing purposes in breach of the decision of 6 May 2003 . As a result, H.K. was fined on the basis of a judgment given on 5 April 2004 by the Mielec District Court.
35 . On an unspecified date H.K. appealed against the decision of 29 July 2003 (see paragraph 34 above) to the Rzeszów Regional Administrative Court. On 28 April 2005 that court stayed the appellate proceedings because the applicant ’ s sister , who was a party to the proceedings , had died. On 4 September 2006 the proceedings were resumed. On 23 January 2007 the Rzeszów Regional Administrative Court quashed the decision of 6 May 2003 and the subsequent decision given on 29 July 2003. On 4 June 2008 the Supreme Administrative Court quashed that judgment and remitted the case to the Rzeszów Regional Court. The proceedings are apparently pending.
E. Proceedings conducted before the County Veterinary Surgeon
36 . On 4 January 1995 H.K. ’ s company began to operate under its business licence of 2 January 1995 issued by the Mielec Municipal Office. The District Veterinary Surgeon ( Rejonowy Lekarz Weterynarii ) was charged with administrative supervision of the company. Subsequently, after the local administration reform of 1999 , the County Veterinary Surgeon ( Powiatowy Lekarz Weterynarii ) took over.
37 . On 3 March 2000 the company obtained a favourable opinion from the District Sanitary Inspector ate with regard to the waste ‑ disposal system on her land . On 27 March 2000 the County Veterinary Surgeon issued a decision obliging H.K. to eliminate some irregularities found in the functioning of the company during a previous inspection.
38 . On 24 July 2000 the applicant complained to the County Veterinary Surgeon about the company ’ s operation and requested that it be closed down. On 31 July 2000 the County Veterinary Surgeon inspected the company ’ s premises. The inspection established certain shortcomings as to the compatibility of the company ’ s operation with animal husbandry regulations. The company wa s ordered to rectify them by 15 August 2000. On 1 August 2000 the County Veterinary Surgeon informed the applicant about the results of the inspection and the obligations imposed on the owner. On 22 August 2000 the County Veterinary Surgeon conducted a further inspection and found that the orders had been complied with.
39 . On 11 January 2001 the applicant again complained to the County Veterinary Surgeon . On 17 January 2001 that authority conducted an inspection of the company with a view to checking whether the previous orders had been complied with. It was established that the orders concerning the meat-processing plant had been fulfilled for the most part, but those concerning the slaughterhouse had not been followed.
40 . Certain obligations imposed on H.K. were subsequently modified by a decision of 17 January 2001. On 25 January 2001 the County Veterinary Surgeon ordered H.K. to cease operation of the slaughterhouse until the orders had been complied with. On 26 January 2001 the applicant was informed accordingly. On 27 February 2001 the County Veterinary Surgeon conducted another inspection of the company. It was established that all obligations imposed previously o n the owner had been met. On 1 March 2001 the County Veterinary Surgeon revoked his decision of 25 January 2001 accordingly .
41 . On 7 March 2001 the applicant again complained of the alleged nuisance caused by the company. A new inspection of the site was carried out on 14 March 2001. No infringements of the applicable regulation s were found. In his letters of 7 and 14 March 2001 the County Veterinary Surgeon informed the applicant accordingly.
42 . Subsequent inspections were carried out on 23 May and 5 July 2001. No breach of the applicable regulations was established. The company remained under regular supervision by the County Veterinary Surgeon, who inspected its site in order to take samples for analysis on the following dates: 10 August, 22 August, 18 September, 5 November 2001, 28 January, 30 January, 1 March, 13 March, 13 May, 5 June, 16 July, 12 September, 22 October, 12 December 2002, 12 March, 21 May, 25 June, 30 June, 16 September, 9 October, 2 December 2003, 6 January, 23 February, 15 March, 17 June, 21 July, 16 September, 5 November 2004, 17 Jan uary, 14 April, 30 August, 20 October 2005, 15 February, 5 April, 1 June 2006, 29 March, 24 April 7, 3 July, 3 October 2007, 25 April, 10 September, 23 October 2008, 26 Marc h, 2 July, 17 November 2009, 13 January, 22 February and 4 June 2010. The results of the tests were in accordance with the applicable norms.
43. With regard to the outcome of th o se inspections the County Veterinary Surgeon issued decisions of 27 October 2003, 5 September 2005, 7 April 2006 and 25 February 2010 ordering H.K. to bring certain aspects of the company ’ s operation in to conformity with the law. O n 29 March 2007 H.K. was fined for certain irregularit ies . S ubsequent inspections showed that all irregularities had been removed and the requirements of the sanitation laws had been fulfilled.
44 . As a result of a serious flood which occurred in June 2010 , the company ceased to operate . On 7 July 2010 the County Veterinary Surgeon inspected the site and ordered its cleaning and disinfection. Tests carried out a fter cleaning of the site showed that there was no contamination, and the administrative authority renewed authorisation for production .
COMPLAINT
45. The applicant complained that the authorities had failed to take effective measures to stop the nuisances originating from the land adjacent to his property . He relied on Article 8 of the Convention .
THE LAW
46 . The applicant complained that the authorities had failed to take effective measures to stop the nuisances originating from the plot of land adjacent to his. He relied on Article 8 of the Convention which in so far as relevant reads:
“1. Everyone has the right to respect for his private and family life, his home ....
2. There shall be no interference by a public authority with the exercise of this right except such as is in accordance with the law and is necessary in a democratic society in the interests of national security, public safety or the economic well-being of the country, for the prevention of disorder or crime, for the protection of health or morals, or for the protection of the rights and freedoms of others.”
47 . The Government submitted that the applicant had failed to exhaust all the available domestic remedies. The administrative authorities had taken all necessary and adequate measures to protect him and his family against the alleged interferences with their rights. However, if the applicant was of the view that that protection had been insufficient, the civil law provided him with effective remedies to stop the alleged infringements and claim compensation. He should have brought a civil action against his neighbour before the courts. He could have relied on Article 144 in conjunction with Article 222 § 2 of the Civil Code and claim ed that his neighbour had infringe d his ownership rights. Alternatively, he could have had recourse to a compensation claim, relying on Article 144 in conjunction with Article 448, and Articles 23 and 24 of the Civil Code. He had also had at his disposal a compensatory claim in tort under Article 415 of the Civil Code.
48 . The applicant submitted that by instituting administrative proceedings , he had done everything possible in order to avert the negative impact which the business operation on the land adjacent to his had had on his home and property, but to no avail.
49. The Court does not find it necessary to examine the Government ’ s preliminary objection because this complaint is in any event inadmissible for the following reasons .
50 . The applicant complained of the State ’ s failure to protect his private life and home from environmental nuisance arising from the activities of the slaughterhouse and meat ‑ processing plant illegally constructed by his neighbour. The smell, noise and pollution produced by the plant had created a risk to his health and that of his family. The administrative authorities had failed to enforce the decision of 15 November 1996, allowed his neighbour to use her illicitly constructed buildings to his detriment and had been unable to successfully resolve the matter for more than thirteen years because ineffective proceedings had been conducted before various administrative authorities and had been delayed without good reason.
51 . The Government submitted that the case did not concern an interference by the public authorities with the applicant ’ s rights protected under Article 8 of the Convention , but the authorities ’ alleged failure to take action to put a stop to third-party breaches of the rights relied on by the applicant. T he public authorities had had to strike a fair balance between the competing interests of the parties involved in the dispute.
52 . The Government emphasised that the particularity of the case consisted in the fact that the applicant was closely related to H.K. and K.Åš., the owners of the businesses concern ed. They had been involved in a serious dispute in 1998 , when H.K. had instituted civil proceedings against the applicant challenging his right of passage through her property. It was essentially the animosity in the family that had resulted in the numerous proceedings in the present case, rather than the actual nuisance caused by the operation of the meat-processing plant built by H.K.
53 . The Government submitted that the buildings contested by the applicant were situated in an area designated under the local land development plan for small businesses and services. That plan authorised the construction of establishments such as the meat - processing plant contested by the applicant. The Government further relied on the decision of the Minister for Environmental Protection, Natural Resources and Forestry issued on 17 March 1999 emphasis ing that the business in question did not fall into the category of businesses with a potentially nefari ous impact on the environment.
54 . The Government submitted that the applicant had not been affected by pollution and noise allegedly emitted by the slaughterhouse and meat ‑ processing plant. The company had been under regular and meticulous supervision by the District Veterinary Surgeon, who had not found any grounds on which to order that the operation of the company should cease. Whenever that authority had found that the company had failed to respect certain regulations, the owner had been ordered to rectify th o se shortcomings. The District Veterinary Surgeon subsequently supervised whether the company had respected his orders. On numerous occasions the authorities found that the company ’ s operation was compatible with the requirements of the environmental legislation . It had not been established that it had caused any environmental degradation. Both the slaughterhouse and the meat-processing plant had fulfilled the environmental protection requirements. They had not exceeded permissible levels of pollution , and the waste and sewage - disposal system had been found to be in compliance . Hence, there were no grounds on which to allege that the authorities had failed to comply with their positive obligations under Articl e 8 of the Convention.
55 . The Court reiterates that Article 8 of the Convention protects the individual ’ s right to respect for his private and family life, his home and his correspondence. A home will usually be the place, the physically defined area, where private and family life develops. The individual has a right to respect for his home, meaning not just the right to the actual physical area, but also to the quiet enjoyment of that area within reasonable limits. Breaches of the right to respect of the home are not confined to concrete breaches such as unauthorised entry into a person ’ s home, but may also include those that are diffuse, such as noise, emissions, smells or other similar forms of interference. A person ’ s right to respect for his home may have been seriously breached if he has been prevent ed from enjoying the amenities of his home (see Moreno Gómez v. Spain , no. 4143/02 , § 53, ECHR 2004-X; Deés v. Hungary , no. 2345/06 , § 21, 9 November 2010; and Ivan Atanasov v. Bulgaria , no. 12853/03 , § 66, 2 December 2010 ).
56 . The present case does not concern interference by public authorities with the right to respect for the home, but their alleged failure to take action to put a stop to third-party breaches of the right relied on by the applicant.
57 . Although there is no explicit right in the Convention to a clean and quiet environment, where an individual is directly and seriously affected by noise or other pollution an issue may arise under Article 8 of the Convention (see Hatton and Others v. the United Kingdom [GC], no. 36022/97 , § 96, ECHR 2003 ‑ VIII; López Ostra v. Spain , 9 December 1994, Series A no. 303-C; Powell and Rayner v. the United Kingdom , 21 February 1990, Series A no. 172, § 40; Furlepa v. Poland (dec.), no. 62101/00 , 18 March 2008; and Oluić v. Croatia , no. 61260/08 , § 45, 20 May 2010). Specifically, Article 8 of the Convention applies to severe environmental pollution, which may affect individuals ’ well-being and prevent them from enjoying their homes in such a way as to affect their private and family life adversely, even without seriously endangering their health (see, among others, TaÅŸkın and Others v. Turkey , no. 46117/99 , § 113, ECHR 2004-X, and Zammit Maempel v. Malta , no. 24202/10 , § 36, 22 November 2011 ).
58 . However, under Article 8 the alleged nuisance must have attained the minimum level of severity required for it to amount to an interference with applicants ’ rights to respect for their private lives and their homes. The assessment of that minimum is relative and depends on all the circumstances: the intensity and duration of the nuisance, its physical or mental effects, the general context, and whether the detriment complained of was negligible in comparison to the environmental hazards symptomatic of life in every modern city (see, among other authorities, Fadeyeva v. Russia , no. 55723/00 , §§ 66-70, ECHR 2005-IV, and Galev and Others v. Bulgaria , (dec.), no. 18324/04 , 29 September 2009).
59. In a case such as the present one the Court may also scrutinise the decision-making process to ensure that due weight has been accorded to the interests of the individual (see TaÅŸkın and Others v. Turkey , no. 46117/99 , § 115, ECHR 2004 ‑ X). The Court has held on a number of occasions that in cases involving environmental issues the State must be allowed a wide margin of appreciation (see Hatton and Others , cited above, § 100; Buckley v. the United Kingdom , judgment of 25 September 1996, Reports 1996 ‑ IV, pp. 1291-93, §§ 74-77; and TaÅŸkın and Others , cited above, § 116). The national authorities are in principle better placed than an international court to assess the requirements relating to the treatment of industrial waste in a particular local context and to determine the most appropriate environmental policies and individual measures while taking into account the needs of the local community. However , the Court must ensure that in the decision-making process the interests of the community are balanced against the individual ’ s right to respect for his or her home and private life. It has consistently held that although Article 8 contains no explicit procedural requirements, that process must be fair and must afford due respect to the interests of the individual safeguarded by Article 8 (see, mutatis mutandis , McMichael v. the United Kingdom , judgment of 24 February 1995, Series A no. 307-B, p. 55, § 87). In particular, the individuals concerned must also be able to appeal to the courts against any decision, act or omission where they consider that their interests or their comments have not been given sufficient weight in the decision ‑ making process (see, mutatis mutandis , Hatton and Others , cited above, § 128, and TaÅŸkın and Others , cited above, §§ 118-19; see also WaÅ‚kuska v. Poland (dec.), no. 6817/04, 29 April 2008).
60 . Turning to the circumstances of the present case , the Court observes , in connection with the substantive aspect of the case, that it is not in dispute that the building which the applicant ’ s neighbour constructed on the land adjacent to the applicant ’ s property did not comply with the conditions laid down in the building permit. It is a matter of regret that the proceedings by which the owner sought to obtain retrospective authorisation to use the building as a meat-processing plant lasted for a long time . However, t he mere fact that the buildings did not comply with the applicable provisions of the construction law is not sufficient grounds for asserting that the applicants ’ rights under Article 8 were interfered with (see Furlepa v. Poland (dec.), cited above ). The Court must examine, on the basis of all the material in the file, whether the alleged environmental nuisances were sufficiently serious to affect adversely the applicant ’ s enjoyment of the amenities of his home and the quality of his private and family life (see Galev and Others , cited above; and Darkowska and Darkowski v. Poland , (dec.), no. 31339/04, 15 November 2011).
61 . In this connection, the Court accepts that the applicant could have been affected by the smell and pollution emitted by the meat - processing plant. However, the Court must determine whether the nuisance attained the minimum level required for it to constitute a violation of Article 8. The Court observes that the applicant did not substantiate his complaint about the alleged environmental nuisance before the national authorities. It is true that he repeatedly complained about the noise and smell emitted by the plant. However, he provided no medical or environmental expert opinions or other evidence of the damage or nuisance allegedly caused to him by the operation of the plant in the close vicinity of his property, either in the domestic proceedings or in the proceedings before the Court. Hence, it has not been reliably established , prima facie , that the operation of the plant caused an environmental hazard, or that the pollution it caused exceeded safe levels set by the applicable regulations. Nor has the applicant furnished the Court or the national authorities with any evidence to substantiate his allegation that his health was or could have been adversely affected by the noise or pollution. It has not therefore been shown that the pollution complained of was of such a degree or character as to cause any noxious effect on the applicant ’ s health or that of his family.
62 . The Court will also consider the findings made by the authorities in the context of administrative proceedings. It notes that the inspection carried out on 29 April 1997 by the Mielec District Veterinary Surgeon and the State Sanitary Inspectorate demonstrated that the applicant ’ s allegations as to the sanitation on the premises concerned were unfounded . F our further inspections were carried out from October 1996 to May 1997. As a result, certain obligations were imposed on the owners in order to rectify the irregularities identified during the inspections. Otherwise, the inspectors found that the companies were complying with the applicable environmental requirements. T he bacteriological soil tests confirmed that the land was not contaminated and that no danger to health or the environment could originate from it . In a decision of 29 July 1998 , the administrative authority declared that H.K. ’ s business activity was compatible with the requirements of the environmental legislation . The meat-processing plant fulfilled the requirements laid down by the provisions of the environmental protection regulations. In particular, its operation did not exceed permissible levels of pollution and noise , and the waste and sewage - disposal system worked properly. The Court is aware that that decision was later quashed on formal grounds . However, no arguments have been adduced to show that the findings of that decision were erroneous.
63 . The Court further observes that in the course of the proceedings , the environmental impact of the meat-processing plant was assessed . The applicant has not submitted, either in the domestic proceedings or in the proceedings before the Court, the results of any alternative tests which would have led to the conclusion that the pollution levels exceeded the norms set either by domestic law or by applicable international environmental standards, or exceeded the environmental hazards symptomatic of life in every modern town (see, in this connection, Fadeyeva , cited above, § 69).
64 . Lastly, it should not be overlooked that the domestic authorities found that the operation of the meat - processing plant in the area was compatible with the local land development plan (compare and contrast with Apanasewicz v. Poland , no. 6854/07 , § 98, 3 May 2011 ; Mileva and Others v. Bulgaria , nos. 43449/02 and 21475/04 , § 61 , 25 November 2010 , mutatis mutandis ).
65 . In conclusion, having particular regard to the findings made in the administrative proceedings referred to above, the Court finds that there is no evidence that the alleged disturbances resulting from the operation of the meat-processing plant in the vicinity of the applicant ’ s land were sufficient to amount to an interference with the effective enjoyment of the applicant ’ s right to respect for his home and private life (compare and contrast with Apanasewicz , cited above, §§ 97-98).
66 . As to the procedural aspects of the case, the Court notes that the authorities did not limit themselves to examining documents concerning the business operation of the applicant ’ s neighbour. Throughout the various sets of proceedings the authorities conducted on-site inspections of the property with a view to establishing whether the applicant ’ s complaints were well ‑ founded, whether the buildings complied with the building permit s , and whether the operation of the company was compatible with environmental and sanitation regulations. In particular, H.K. ’ s business was under the regular supervision of the District Veterinary Surgeon. Post ‑ inspection orders were formulated with a view to bringing the plant ’ s operation in to conformity with the law , and compliance with th o se orders was subsequently checked.
67 . The Court further notes that the applicant had the right to appeal against the first-instance administrative decisions and he availed himself of that right. His objections were therefore examined by the second ‑ instance administrative bodies.
68 . It was open to the applicant to appeal to the Supreme Administrative Court against the second-instance decisions in order to have their lawfulness examined in a procedure guaranteeing fairness and judicial impartiality and independence. The Court further notes that the reasons provided by the domestic authorities, both administrative and judicial, were plausible and based on a careful examination of the case. The Court is of the view that there is no indication of any arbitrariness in their reasoning.
69 . Therefore, it cannot be established that the State failed to take reasonable measures to secure the applicant ’ s rights under Article 8 of the Convention, especially having regard to the fact that the domestic authorities balanced the applicant ’ s interests against the interests of his neighbour. Therefore, it cannot be established that the State failed to take reasonable measures to secure the applicant ’ s rights under Article 8 of the Convention.
70 . It follows that this complaint is manifestly ill-founded and must be rejected in accordance with Article 35 §§ 3 (a) and 4 of the Convention.
71 . The applicant further complained, under Article 13 of the Convention , that his administrative appeals had not been successful. The Government contested that argument.
72. The Court has reiterated on numerous occasions that Article 13 of the Convention guarantees the availability at national level of a remedy to enforce the substance of the Convention rights and freedoms in whatever form they are secured in the domestic legal order. The effect of this Article is thus to require the provision of a domestic remedy allowing the competent national authority both to deal with an “arguable complaint” under the Convention and to grant appropriate relief (see Jabari v. Turkey , no. 40035/98 , § 48, ECHR 2000 ‑ VIII). The effectiveness of a remedy within the meaning of Article 13 does n ot depend on the certainty of a favourable outcome for the applicant. Nor does the “authority” referred to in that provision necessarily have to be a judicial authority. Nevertheless, its powers and the procedural guarantees which it affords are relevant in determining whether the remedy before it is effective (see Klass and Others v. Germany , 6 September 1978, § 67, Series A no. 28). The expression “effective remedy” used in Article 13 cannot be interpreted as a remedy that is bound to succeed ; it simply means an accessible remedy before an authority competent to examine the merits of a complaint (see, for example, Å idlová v. Slovakia , no. 50224/99 , § 77, 26 September 2006).
73 . The Court has already found that the applicant had at his disposal numerous administrative remedies by which he could bring his complaint about the alleged breach of his rights guaranteed by the Convention to the attention of the authorities. He availed himself of th o se remedies and the authorities examined the essence of his complaints. In this context, the Court notes the Government ’ s argument that the administrative authorities took all necessary and adequate measures to protect the applicant against the alleged interference with his right to respect for his home and family life by private parties . In the light of the foregoing, the Court considers that in the circumstances of the present case it cannot be said that the applicant ’ s right to an effective remedy under Article 13 of the Convention has not been respected.
74 . It follows that this complaint is manifestly ill-founded and must be rejected in accordance with Article 35 §§ 3 and 4 of the Convention.
For these reasons, the Court , unanimously ,
Declares the application inadmissible.
Françoise Elens-Passos Ineta Ziemele Registrar President
[1] . Approximately EUR 12