PHILIS v. GREECE
Doc ref: 12750/87 • ECHR ID: 001-298
Document date: December 7, 1988
- Inbound citations: 0
- •
- Cited paragraphs: 0
- •
- Outbound citations: 8
AS TO THE ADMISSIBILITY OF
Application No. 12750/87
by Nicolas PHILIS
against Greece
The European Commission of Human Rights sitting in private
on 7 December 1988, the following members being present:
MM. C.A. NØRGAARD, President
J.A. FROWEIN
S. TRECHSEL
F. ERMACORA
E. BUSUTTIL
A. S. GÖZÜBÜYÜK
J.-C. SOYER
H.G. SCHERMERS
H. DANELIUS
H. VANDENBERGHE
Sir Basil HALL
MM. F. MARTINEZ
C.L. ROZAKIS
Mrs. J. LIDDY
Mr. H.C. KRÜGER, Secretary to the Commission
Having regard to Article 25 of the Convention for the
Protection of Human Rights and Fundamental Freedoms;
Having regard to the application introduced on 5 January 1987
by Nicholas Philis against Greece and registered on 24 February 1987
under file No. 12750/87;
Having regard to:
- the report provided for in Rule 40 of the Rules of Procedure
of the Commission;
- the written observations of the respondent Government of
31 May 1988 and the applicant's observations in reply contained in
his letters of 4 April 1988, 13 July 1988 and 4 August 1988;
- the parties' oral submissions at the hearing on 7 December
1988;
Having deliberated;
Decides as follows:
THE FACTS
The facts of the case as submitted by the parties may be
summarised as follows:
The applicant is a Greek citizen, born in 1937, and is a
private consultant engineer, having had a technical bureau in Athens
since 1970.
In 1971 a State institution, OEK (Organismos Ergatikis
Katoikias), entrusted with housing labourers' families responsible to
the Greek Ministry of Labour, entered into agreements with the
applicant for him to carry out design projects for and to supervise
work on its electro-mechanical installations for the period 1971-1975
and subsequently entered into further similar agreements for the
period 1976 - 1978.
In March 1978 the OEK terminated its agreements with the
applicant and refused to pay him the remuneration provided for by law.
I.
The applicant instituted proceedings against the OEK before
the Court of Athens (Protodikeio Athinon), claiming the remuneration
for the supervision projects. To this end he lodged 13 actions with
the Court of Athens between 30 October 1978 and 23 December 1982 *.
Actions against the OEK were also brought by the Technical
Chamber of Greece (TEE) which, according to the Royal Decree
(Vassiliko Diatagma) 30/1956 modified by the Royal Decree 188/1966,
is exclusively authorised to claim design projects' remuneration in
substitution for the engineer. The TEE lodged seven actions with the
Court of Athens in the period between 16 December 1977 and 24 December
1982 *. The applicant was a third party in these proceedings.
The main litigious matter in these proceedings was to find out
what sort of contract existed between the applicant and the OEK, a
contract of service or a contract for services. In the first case the
applicant would have elaborated design projects for the OEK as an
employee and should therefore receive no remuneration since he had
been paid a salary. In the second case, his remuneration claims would
have been well-founded.
Five of these actions were brought before the Court of
Cassation (Areios Pagos), after the Court of Athens and the Athens
Court of Appeal (Efeteio Athinon) had given decisions either accepting
or rejecting the claims. At that stage of the proceedings the OEK
requested the cases to be adjourned in view of settlement
negotiations.
----------
* The dates of introduction of each action and the dates on
which decisions were given in these actions by the competent
Greek courts appear on pages 5 to 6 of this decision.
In the meantime a law introduced by the Minister of Labour was
passed by Parliament affecting OEK agreements with engineers, whose
provisions were also to be applied to cases pending before the
courts. According to these provisions (Article 29 para. 5 of the law
(Nomos) 1346/83) the remuneration due to engineers was not the
remuneration provided in the previous law but the agreed one. Article
29 para. 5 reads:
"Contracts for the execution of design, supervision and
control projects ... contracted between the OEK and
private engineers ... or engineers employed by the State
or moral persons of public law, prior to the day of
publication of the present law, are deemed to be in
accordance with the law notwithstanding any other
provisions of law and regardless of whether they are
contracts of service or contracts for services and
whether they are permanent or temporary contracts.
The above mentioned engineers ... are entitled to the
remuneration as agreed in the contract. In this
respect the provisions of the law BD 19/21.2.38 ...
ND 696/1974 and N 716/1977 do not apply.
The provisions of this paragraph apply also to cases
pending before all courts."
After the new law came into force, on 13 April 1983, the OEK
refused to settle the case.
The applicant considered the passing of the law to be an
interference "by the executive authorities - through the legislative
authorities" with his cases pending before the courts and requested
the Court of Cassation not to apply the new law.
The Court of Cassation rejected the applicant's complaints,
considering that the new law applied to all engineers and did not
therefore violate the principle of equality. It also stated that the
legislative authorities are not prevented from re-adjusting civil rights
by voting new civil laws, provided the principle of equality is not
violated. Consequently it rejected the appeals as ill-founded, since
the claims were based on the old law provisions which were no longer
in force.
Following these decisions the applicant and the TEE
discontinued all of the original court actions still pending before
the courts and re-introduced them before the Court of Athens basing
the claims on the new law (second cycle of proceedings). *
These actions, re-introduced in the period between 27 March
1984 and 27 May 1986, are still pending either before the Court of
Athens, the Athens Court of Appeal or the Court of Cassation.
----------
* The dates of introduction of each action and the dates on which
decisions were given on these actions by the competent Greek
courts appear on pages 5 to 6 of this decision.
On 15 November 1985 the Court of Athens gave two decisions
(Apofaseis 384/1985 and 385/1985) by which it accepted that
TEE's actions for declaratory judgments (anagnoristikes agoges) to
which it related were well-founded. However, two other decisions of
another chamber of the same court rejected the TEE's actions
(decisions - apofaseis 326/85 of 16 September 1985 and 274/86 of 27
May 1986). In these decisions the Court of Athens found that the
applicant's claims were prescribed under Greek law "since the period
between the end of the financial year in which the claim was created
and a respective action could be brought before courts and the date of
the introduction of the action exceeded five years".
The TEE had submitted that the claims were not prescribed,
since it had lodged its original actions with the competent court
within the five year time limit. However the Court found that these
original actions should not be taken into consideration since, having
a different legal basis, they were not identical with the actions it
was seized with and might not therefore interrupt the course of the
period of limitation.
Appeals (efeseis) against the above decisions of the Court of
Athens were pursued by the OEK and the applicant. The TEE refused to
pursue any remedies since it thought they did not offer any chance of
success. In its decisions 8671 of 15 October 1986, 9908 of 19
November 1986 and 10040 of 24 November 1986 the Athens Court of Appeal
confirmed that the claims had been prescribed.
The applicant appealed (anaireseis) on 15 April and 17 June
1987 against the decisions of the Athens Court of Appeal. He presented
15 to 18 appeal grounds invoking inter alia the provisions of the
Convention.
The Court of Cassation decided to hold a hearing on the
applicant's appeals on 28 April 1988. The judge-rapporteur presented
his reports on the cases on 13 April 1988. In the hearing of 28 April
1988 the applicant requested the Court of Cassation to adjourn
examination of the cases in order to permit him to reply to the
reports. The Court of Cassation adjourned until 1 November 1988. On
that date the Court held a hearing. No decision has so far been given.
The dates of introduction of each single action and the dates
on which decisions were given by the competent courts in the
proceedings referred to under this part of THE FACTS are indicated
hereafter by the letters i and d respectively. The actions introduced
by the applicant are indicated as a1 to a13, for the first cycle of
proceedings and A1 to A13 for the second cycle. The TEE's actions are
indicated as t1 to t7, for the first cycle, and as T1 to T7 for the
second cycle of proceedings.
First Cycle Second Cycle
Court Athens Court Court Athens Court
of Court of of of Court of of
Athens Appeal Cassation Athens Appeal Cassation
____________________________________________________________________________
a1 i: 30.10.78 18.05.79 3.11.81 A1 i: 26.02.86 / /
d: 31.03.79 29.01.81 3.02.84
____________________________________________________________________________
a2 i: 10.11.79 16.03.81 17.05.82 A2 i: 26.02.86
d: 31.05.80 30.10.81 22.06.84
____________________________________________________________________________
a3 i: 13.02.80 2.07.80 29.10.81 A3 i: 26.02.86
d: 19.05.80 17.06.81 17.01.84
____________________________________________________________________________
a4 i: 05.05.80 A4 i: 17.02.86
d:
____________________________________________________________________________
a5 i: 21.05.80 17.11.81 A5 i: 17.02.86
d: 11.05.81 25.10.82
____________________________________________________________________________
a6 i: 17.09.80 A6 i: 17.02.86
d:
____________________________________________________________________________
a7 i: 28.12.80 A7 i: 17.02.86
d: 31.08.81
____________________________________________________________________________
a8 i: 1.04.81 A8 i: 26.02.86
d:
____________________________________________________________________________
a9 i: 1.04.82 A9 i: 17.02.86
d:
____________________________________________________________________________
a10 i: 26.10.82 A10 i: 17.02.86
d:
____________________________________________________________________________
a11 i: 13.12.82 A11 i: 13.03.86
d:
____________________________________________________________________________
a12 i: 13.12.82 A12 i: 26.02.86
d:
____________________________________________________________________________
a13 i: 23.12.82 A13 i: 26.02.86
d:
First Cycle Second Cycle
Court Athens Court Court Athens Court
of Court of of of Court of of
Athens Appeal Cassation Athens Appeal Cassation
____________________________________________________________________________
t1 i: 23.12.77 2.11.78 3.09.79 T1 i: 26.02.86 7.10.86
d: 30.08.78 9.06.79 8.06.84 d: 27.05.86
____________________________________________________________________________
t2 i: 16.12.78 T2 i: 26.02.86 7.10.86
d: 31.08.81 d: 27.05.86
____________________________________________________________________________
t3 i: 12.01.80 4.07.80 10.02.82 T3 i: 26.02.86 7.10.86
d: 30.05.80 26.06.81 25.05.84 d: 27.05.86
____________________________________________________________________________
t4 i: 23.12.82 T4 i: 26.02.86 7.10.86
d: d: 27.05.86
____________________________________________________________________________
t5 i: 24.12.82 T5 i: 27.03.84 5.02.86 17.06.87
d: d: 15.11.85 19.11.86
____________________________________________________________________________
t6 i: 24.12.82 T6 i: 2.04.84 24.01.86 15.04.87
d: d: 16.09.85 15.10.86
____________________________________________________________________________
t7 i: 24.12.82 T7 i: 27.03.84 5.02.86 17.06.87
d: d: 15.11.85 24.11.86
____________________________________________________________________________
II.
On 13 April 1981 the TEE in substitution for the applicant
introduced an action against the OEK before the Court of Athens
requesting remuneration for design projects he had executed for the
OEK after 1977.
On 30 November 1981 the Court of Athens gave judgment in
favour of TEE and ordered the OEK to pay 898.697 Drachmas in respect
of the money claimed. On 23 January 1982 the OEK appealed against the
above decision. On 26 February 1987 the applicant joined as
respondent. The case was brought before the Athens Court of Appeal on
7 April 1987 (five years and three months after its introduction).
On 23 May 1987 the Court of Appeal gave its decision rejecting
the OEK's appeal. The Court of Appeal found that the applicant's
relations with the OEK after 1977 were not based on any contract for
services or contract of service. It found that the applicant had
executed design projects for the OEK after such projects had been
assigned to him as an independent engineer, within the meaning of
the law No. 716/1977 concerning projects assignment and execution.
Therefore the claims were founded on that law and the provisions of
the new law No. 1346/83 did not apply.
On 7 July 1987 the OEK appealed (anairesi) against the above
decision. The Court of Cassation held a hearing on that case on
11 October 1988. No decision has so far been given.
On 2 July 1987 the applicant requested the TEE to lodge a
subsidiary action with the purpose of capitalising the interest due on
his accepted claim since 8 April 1981 pursuant to Article 296 of the
Greek Civil Code (Astikos Kodix). On 24 September 1987 the TEE
informed the applicant that it did not intend to act in the way the
applicant wished.
III.
The applicant considered that, while the above civil
proceedings were pending, OEK officials had been engaged in
activities aimed at the extinction or limitation of his rights.
On 8 September 1979, 16 January and 18 April 1980 and
15 April and 19 June 1981 he lodged criminal complaints against OEK
officials with the Athens and Volos Prosecutors. The above motions
ended with discharge orders. The applicant's appeals against these
orders have been declared inadmissible by the competent Chamber of the
Court of Appeal (Symvoulio Efeton) for lack of the applicant's locus
standi.
On the applicant's motion of 7 October 1982 the Athens
Prosecutor ordered investigations for the purpose of examining whether
OEK officials should be charged with contempt of court for using
falsified documents in the civil proceedings. A discharge order
issued on 4 June 1984 was delivered to the applicant on 7 May 1985,
11 months after its issue.
The applicant's appeal against the above discharge order was
rejected as inadmissible by the Chamber of the Athens Court of
Appeal. The applicant appealed again before the Chamber of the Court
of Cassation, which on 5 March 1986 found in favour of the applicant
and sent the case back to the Chamber of the Athens Court of Appeal.
On 8 May 1986 the Chamber of the Athens Court of Appeal
rejected once more the applicant's appeal and the latter appealed
again before the Court of Cassation, requesting "legal protection" and
invoking, inter alia, Article 13 of the Convention.
In a decision of 25 July 1986 the Chamber of the Court of
Cassation again allowed the applicant's appeal and revoked the
decisions of the Chamber of the Athens Court of Appeal and the
discharge order of the Athens Prosecutor, deciding however at the same
time that the offence was prescribed under national law.
IV.
While these proceedings were taking place, the Prosecutor of
the Athens Court of Appeal charged the applicant with insulting the
authorities on the ground that a letter, sent by him to the Chamber of
the Athens Court of Appeal on 14 April 1986, stated that the
proceedings followed by the competent authorities in his various legal
actions "leave no doubt as to the existence of bias in favour of OEK
officials", and, that "the clear purpose of the delay in the
proceedings was to ensure that the crimes would be prescribed".
The applicant was summoned to appear before the Investigating
Judge on 15 October 1986 and again on 2 June 1987. On 12 October 1988
the applicant was sentenced to six months' imprisonment by the First
Instance Criminal Court of Athens (Trimeles Plimmeliodikeio
Athinon). The case is now pending before the Athens Court of Appeal.
COMPLAINTS
1. The applicant complains of the passing of the new law. He
alleges that the courts dealing with his cases were not independent or
impartial, since they had to apply a law drafted and passed by his
adversary and invokes Article 6 of the Convention. Moreover,
considering his remuneration claims as possessions within the meaning
of Article 1 of Protocol No. 1, the applicant alleges that the new law
led to a deprivation of his property. Finally, he alleges that he has
been a victim of discrimination, since the new legislative provisions
mainly affected his cases and submits that his name has been expressly
reported in the Parliament's records.
2. The applicant also complains that the length of the
proceedings exceeded the reasonable time required by Article 6 para. 1
of the Convention. He alleges that actions originally introduced
between 13 December 1977 and 24 December 1982 are still pending before
the courts.
3. Moreover, he alleges that he has not been given a right to a
tribunal, since the TEE has been compulsorily substituted for him with
regard to design project remuneration claims and invokes Article 6
para. 1 of the Convention.
4. He also complains of not being given any effective remedy
before a national authority with regard to OEK officials' criminal
activities and invokes Article 13 of the Convention.
5. Finally, the applicant complains of being charged with
insulting judicial authorities for having invoked his right to an
independent and impartial tribunal.
PROCEEDINGS BEFORE THE COMMISSION
The application was introduced on 5 January 1987. On
12 December 1987 the Commission decided to bring the application to
the notice of the respondent Government and invite them to submit
written observations on the admissibility and merits of the
complaints concerning access to court and length of the proceedings
referred to under Part II of THE FACTS.
The Government submitted their observations on 31 May 1988.
The applicant's observations in reply are contained in his letters of
4 April, 13 July and 4 August 1988.
On 11 October 1988 the Commission decided to invite the
parties to appear before it at a hearing on the admissibility and
merits of the complaint concerning the applicant's access to a court.
The hearing was held on 7 December 1988. At the hearing the
parties were represented as follows:
The Government
Mr. C. Economides Head of the Legal Department of the
Ministry of Foreign Affairs, Agent
of the Government
Mr. V. Theofilou Lawyer, Adviser
Mrs. M. Vondicaki Telalian Secretary of the Legal Department of
the Ministry of Foreign Affairs, Adviser
The Applicant appeared in person.
SUMMARY OF THE OBSERVATIONS OF THE PARTIES
1. The Government
The Government observe in limine that proceedings referred
to in the application are still pending before the courts and that
expected decisions can be decisive for the applicant's complaints.
They conclude that the applicant has not complied with the
requirements of Article 26 of the Convention, e.g. that domestic
remedies are not exhausted at this stage of the proceedings.
On the applicant's access to court
The Government admit that according to the provisions of Royal
Decrees 30/1956 and 188/1966 the TEE is exclusively authorised to sue
the debtors of engineers claiming fees for design projects executed by
them. They submit, however, that engineers are not deprived of
guarantees against a possible refusal of the TEE to institute
proceedings in substitution for them.
They first observe that engineers have, pursuant to Article 72
of the Code of Civil Procedure, the possibility of suing directly the
TEE's debtors in case of negligence on the part of TEE by introducing
an "oblique action" (plagiastiki agogi). Article 72 of the Code of
Civil Procedure provides that a creditor may apply for judicial
protection exercising the rights of his debtor, in cases where the
latter does not exercise them, unless these rights are exclusively
personal. As to the effectiveness of such actions, the Government
refer to a decision given on 6 June 1988 by the Athens Court of Appeal
(apofasi 7892/1988). It would then have been possible for the
applicant to introduce such an action against the OEK asking that the
latter pay the fees claimed to the TEE.
The Government also make it clear that, pursuant to Article
914 of the Civil Code the applicant can introduce an action claiming
indemnity for the damages allegedly caused by the TEE's refusal to
institute proceedings.
The Government also submit that according to the provisions of
RD 30/1956 the applicant is entitled to introduce an ancillary
interpleader action (prostheti paremvasi) and join as co-plaintiff
or co-defendant. This interpleader action would furthermore be
"autonomous" (autotelis) pursuant to Article 83 of the Code of Civil
Procedure. In this respect the Government submit that the
interpleader engineer would have the rights of a full party in the
proceedings.
Finally, the Government note that the TEE's substitution for
the engineer system has been functioning successfully since its
institution and that the Court of Cassation has found this system in
accordance with the provisions of the Greek Constitution.
As to the length of the proceedings
referred to under Part II of the FACTS
The Government first observe that the proceedings concerned are
governed by the principle of the conduct of the litigation by the
parties. They moreover note that proceedings concerning engineers'
remuneration claims are dealt with by the courts according to the
provisions of Articles 677-681 of the Code of Civil Procedure.
These provisions institute a particular procedure comparable to that
applied to labour litigations and aim at safeguarding an expeditious
trial:
- Evidence must be submitted until the first hearing of the
case.
- Decisions should be taken, as far as possible, after a single
hearing.
- Witnesses are to be examined in open court during the hearing.
In the applicant's cases, however, the complexity of the
questions put to the courts and in particular the serious contestation
as regards the nature of the contractual relations between the
applicant and the OEK required a deep examination of the elements of
the cases and consequently prolonged the proceedings.
The Government note moreover that unjustified delays on the
part of a court when dealing with a case would expose the judges to
disciplinary penalties. Furthermore, a special action provided by
Article 99 of the Constitution and law 693/77 gives the party injured
due to the fault of the judiciary a right to sue the judge at fault
before a special court and claim reparation of the prejudice (agogi
kadodikias).
Finally, turning to the present case, the Government observe
that the applicant could have expedited the proceedings concerned by
joining as co-defendant before the Court of Appeal pursuant to the
provisions of RD 30/1956 and of the Code of Civil Procedure long
before 26 February 1987. He could then have asked the Court of Appeal
to fix a date for a hearing in the months following his intervention.
Having failed to proceed in that way, the applicant has contributed to
the prolongation of the appeal proceedings.
Conclusion
The Government conclude that the application should be
rejected for lack of compliance with the exhaustion of domestic
remedies requirement set forth in Article 26 of the Convention, or
as manifestly ill-founded.
2. The applicant
The applicant submits that the actions referred to in the
Government's observations as possible steps he could have taken in
order to ensure his right of access to a court or to a fair hearing
within a reasonable time may not be regarded as effective in the
present case. He moreover submits that the Court of Cassation has
declared on several occasions that the substitution system provided by
the Royal Decrees 30/1956 and 188/1966 is in accordance with the
constitution and that, therefore, as regards this complaint, he cannot
be reasonably considered as not having exhausted the domestic remedies
according to the generally recognised principles of international law
within the meaning of Article 26 of the Convention.
On access to a court
The applicant first submits that the substitution system
essentially deprives him of his right to secure the effective drawing
up of the actions, the lodging of the actions in time, and the legal
assistance of his own choosing.
The applicant further submits that the TEE refused on several
occasions to lodge subsidiary actions against the OEK. In particular
the TEE refused to lodge actions for the purpose of capitalising the
interest due on his claims pursuant to Article 296 of the Civil Code.
This refusal concerned the actions referred to as T5, T6 and T7 and
the action referred to under Part II of THE FACTS.
TEE also refused to lodge subsidiary actions for the purpose
of readjustment of his claims in relation to inflation rates pursuant
to Article 12 para. 10 of Royal Decree 13/1938 and Article 105 para. 4
of Presidential Decree 696/1974 in conjunction with the jurisprudence
of the Court of Cassation (decision 443/81). This refusal concerned
actions T5, T6, T7 and the action referred to under Part II of THE
FACTS.
The TEE also converted actions T1, T2, T3, T4, T5 and T7 to
actions for declaratory judgments (anagnoristikes agoges). The
applicant observes in this respect that in case he wins these
proceedings, he will be obliged to re-introduce the same action before
the courts in order to obtain a title for the enforcement of the
courts' decisions.
The applicant contends, moreover, that the interpleader
action he is entitled to introduce before the courts is not
"autonomous" and refers to the case-law of the Court of Cassation
(Decision 407/79). He submits that the "oblique action" is only
theoretically available in his cases and observes that compensation
actions against the TEE would lead to a new cycle of proceedings. The
applicant concludes that the procedural steps or remedies indicated by
the Government cannot be considered as securing for him effective and
sufficient access to a court.
As to the length of the proceedings referred to
under Part II of THE FACTS
The applicant submits that he did not need to become a party in
the appeal proceedings because in his view they concerned a first
instance decision which had been anyway revoked and corrected by the
Court of Athens in a subsequent decision. He found therefore that he
had no interest in joining as a third party.
THE LAW
1. The applicant first complains of the passing of the new law
which entered into force on 13 April 1983. He alleges that he
suffered discrimination by the interference of the legislative
authorities with his cases pending before the competent courts and
that his property was seriously affected by these new law provisions.
He invokes Article 6 para. 1 (Art. 6-1) and Article 14 (Art. 14) of
the Convention and Article 1 of Protocol No. 1 (P1-1).
The Commission observes that according to the declaration by
Greece under Article 25 (Art. 25) of the Convention the competence of the
Commission under that article extends only to applications whereby a
person claims to be a victim of a violation of the Convention in
relation to matters occurring after 19 November 1985. The Commission
notes in this respect that this complaint does not relate to the new
law as such but to the effect it had on the applicant's then existing
remuneration claims on its coming into force on 13 April 1983. That
having taken place before the 19 November 1985, it follows that this
part of the application is outside the competence of the Commission
ratione temporis and must be declared inadmissible in accordance
with Article 27 para. 2 (Art. 27-2) of the Convention.
2. The applicant also complains about the length of the
proceedings and invokes Article 6 para. 1 (Art. 6-1) of the
Convention, which guarantees a fair hearing within a reasonable time
in the determination of civil rights and obligations.
The Commission observes that the applicant's and the TEE's
actions initially introduced on 23 December 1977 (t1), 30 October 1978
(a1), 10 November 1979 (a2), 12 January 1980 (t3) and 13 February 1980
(a3) have been terminated by final judgments of the Court of Cassation
on 8 June 1984, 3 February 1984, 22 June 1984, 25 May 1984 and
17 January 1984 respectively. It also observes that the TEE's actions
introduced on 24 December 1982 (t5, t6, t7) have been terminated by
TEE withdrawals on 27 March and 2 April 1984. These proceedings began
and ended before 19 November 1985 and it follows that the complaint
concerning their length is excluded from the competence of the
Commission ratione temporis for the reasons already stated above.
3. With regard to the other actions of the first cycle of
proceedings which were discontinued by the applicant or the TEE, the
Commission observes that the respective proceedings have been
terminated by the applicant's or the TEE's withdrawals on 17 February
(a4, a5, a6, a7, a9, a10), 26 February (a8, a12, a13, t2, t4) and
13 March 1986 (a11).
The Commission recalls that according to Article 26 (Art. 26)
of the Convention it "may only deal with the matter ... within a
period of six months from the date on which the final decision was
taken".
In the present case the proceedings of which the applicant
complains ended on 17, 26 February and 13 March 1986, which dates fall
to be regarded as the dates of final decisions in the respective
proceedings within the meaning of Article 26 (Art. 26). However, the
application was submitted to the Commission on 5 January 1987, that
is more than six months after the end of the above proceedings.
Furthermore, an examination of the case does not disclose the existence
of any special circumstances which might have interrupted or
suspended the running of that period.
It follows that this part of the application has been
introduced out of time and must be rejected under Article 27 para. 3
(Art. 27-3) of the Convention.
4. With regard to the proceedings instituted by the TEE on
13 April 1981 (cf. Part II of THE FACTS) and with regard to the second
cycle of the proceedings concerning the TEE's actions T5 and T7, which
commenced on 27 March 1984, and T6, which commenced on 2 April 1984,
the Commission observes that these proceedings are now pending before
the Court of Cassation. As far as the length of these proceedings is
concerned, the Commission observes that the period it is competent
ratione temporis to consider begins on 20 November 1985, when
recognition by Greece of the right of individual petition took effect.
However in assessing the reasonableness of the time that elapsed after
20 November 1985 account must be taken of the then state of
proceedings (cf. Eur. Court of H.R., Foti and others judgment of
10 December 1982, Series A no. 56; pp. 18-19, para. 53)
The proceedings concerning the applicant's actions A1 to A13
and the TEE's actions T1 to T4 commenced after 20 November 1985 and
fall therefore entirely within the Commission's competence ratione
temporis.
The Commission observes furthermore that the applicant is now
a third party in the proceedings instituted by the TEE. Moreover, it
appears from the parties' submissions that it is his own right to
remuneration which is to be determined by the competent courts. The
Commission finds, therefore, that the applicant can complain under
Article 6 para. 1 (Art. 6-1) of the Convention of the length of these
proceedings.
The respondent Government have submitted that the actions
concerned by the proceedings the applicant complains of are still
pending before the Greek courts and that therefore the applicant has
not complied with the requirement of exhaustion of domestic remedies
set forth in Article 26 (Art. 26) of the Convention. The Commission
notes, however, that the Government have not shown in what way the
decisions which will be given by the Greek courts can effectively
remedy the situation complained of rather than prolonging the
allegedly already lengthy proceedings.
In order to determine whether the length of these proceedings
may be regarded as "reasonable" within the meaning of Article 6 para.
1 (Art. 6-1) of the Convention, the Commission refers to the
particular circumstances of the case. It has in particular regard to
the criteria put forward by the jurisprudence of the Court (cf. for
example Eur. Court H.R., König judgment of 28 June 1978, Series A no.
27, p. 34, para. 99; Eckle judgment of 15 July 1982, Series A no. 51,
p. 35 para. 80), i.e. the complexity of the case, the conduct of the
applicant and the conduct of the judicial authorities.
The Commission has first examined the proceedings instituted
by the TEE's action of 13 April 1981. It finds that the only point of
concern appears with regard to the proceedings before the Athens Court
of Appeal which have lasted more than five years.
It appears however clearly from the parties' submissions that
the case was adjourned upon request of the parties after notice of
appeal was given. The proceedings were taken up only five years later
at the request of the TEE. Only then did the applicant join as a
third party.
The Commission recalls that the fact that the proceedings
concerned are governed by the principle of the conduct of the
litigation by the parties does not dispense the judicial authorities
from ensuring the trial of the action expeditiously as required by
Article 6 (Art. 6) (Eur. Court H.R. Buchholz judgment of 6 May 1981,
Series A No. 42 p. 16 para. 50). However, the Government have
submitted that the applicant could have joined as a third party
immediately after the introduction of the OEK's appeal and request the
court to fix a hearing in the following months. The applicant does
not contest that he had such a possibility. He submits however that
he had no interest in joining.
The Commission recalls that in civil matters the exercise of
the right to a fair hearing within a reasonable time is dependent on
the diligence of the interested party (No. 7370/76, Dec. 28.2.7, D.R.
9 p. 95). Although the applicant was only involved as a third party
in the proceedings concerned since 26 February 1987, it appears
clearly from his submissions that if he had joined earlier he could
have contributed to an expeditious trial of the action.
In these circumstances the Commission finds that the
applicant's conduct may be regarded as the most important factor of
the delay.
It follows that this part of the application insofar as it
relates to the proceedings instituted on 13 April 1981 is manifestly
ill-founded within the meaning of Article 27 para. 2 (Art. 27-2) of
the Convention.
5. With regard to the length of proceedings concerning the
actions T1 to T7 and A1 to A13 the Commission notes the following:
- On the T1 to T7 actions first instance proceedings barely
exceeded 7 months.
- On the T5, T6 and T7 actions appeal proceedings before the
Court of Appeal did not exceed 9 months. The Court of Cassation was
seized on 15 April and 17 June 1987 and held a hearing on these
actions on 28 April 1988. The case was then adjourned upon the
applicant's request until 1 November 1988. The applicant moreover
submits that he has presented 13 to 15 appeal grounds.
- The T1 to T4 actions have been pending before the Court of
Appeal since 7 October 1986. The A1 to A13 actions have been pending
before the Court of Athens since 17 or 26 February 1986 (A11 since 13
March 1986). According to the applicant's submissions these courts
await the decision of the Court of Cassation before taking up these
cases.
In general, the period to be considered by the Commission in
respect of these proceedings barely exceeds 3 years. Moreover, these
proceedings undoubtedly present a certain degree of complexity.
In these circumstances the Commission finds that no excessive
delays - and in particular no unjustified inactive periods imputable
to the judicial authorities - can be found with regard to these
proceedings.
It follows that this part of the application insofar as it
relates to the actions T1 to T7 and A1 to A13 is also manifestly
ill-founded within the meaning of Article 27 para. 2 (Art. 27-2) of
the Convention.
6. The applicant complains that he has been denied the right of
access to a court in respect of his design project remuneration
claims. He complains in particular that the TEE deprived him of his
right of access to a court by refusing to introduce an action with the
purpose of capitalising the interests of his accepted claim, that it
refused to request adjustment of the amount claimed in relation to
inflation rates and, finally, that in the second cycle of proceedings
it only instituted proceedings for declaratory judgments.
The Commission examined this complaint under Article 6 para.
1 (Art. 6-1) of the Convention, in the light of the jurisprudence of
the European Court of Human Rights. It recalls in particular the
following:
"The right of access constitutes an element which is
inherent in the right stated by Article 6 para. 1 (Art. 6-1).
This is not an extensive interpretation forcing new obligations
on the Contracting States; it is based on the very terms of
the first sentence of Article 6 para. 1 (Art. 6-1) read in its
context and having regard to the object and purpose of the
Convention, a lawmaking treaty and to general principles of
law. (...) Article 6 para. 1 (Art. 6-1) secures to everyone the
right to have any claim relating to his civil rights and
obligations brought before a court or tribunal. In this way
the Article embodies the "right to a court", of which the
right of access, that is the right to institute proceedings
before courts in civil matters, constitutes one aspect only.
To this are added the guarantees laid down by Article 6
para. 1 as regards both the organisation and composition of
the court, and the conduct of the proceedings. In sum, the
whole makes up the right to a fair hearing." (Eur. Court
H.R. Golder judgment of 21 January 1975, Series A, Vol. 18
p. 18 para. 36).
The Government have submitted that since the actions concerned
are still pending before the domestic courts, the applicant cannot be
considered as having exhausted the domestic remedies.
The Commission first observes that the alleged lack of the
applicant's access to a court constitutes a continuing situation
created by the provisions of the Royal Decree 30/1956 instituting the
substitution system. It finds that the respondent Government have not
shown how the decisions which will be given by the Greek courts can
remedy the situation complained of. It moreover considers that the
Government have not shown that a remedy is available to the applicant
under Greek law which would effectively permit him to challenge the
situation complained of before a competent authority.
The Government have submitted that the Greek law secures to
the applicant sufficient access to a court. They submit in particular
that the applicant can bring an autonomous ancillary interpleader
action and that he is entitled to lodge an "oblique action" with the
competent courts in case the TEE refuses to institute proceedings.
Furthermore, he can sue the TEE, claiming compensation for the damage
caused by the TEE's refusal to act in accordance with the law.
The applicant contends that neither the ancillary interpleader
action he is entitled to lodge nor an application for compensation
against the TEE can be considered as guaranteeing him sufficient
access to the court and control of the proceedings. Moreover, he
submits that the "oblique action" is only theoretically available in
his case.
The Commission finds that the question as to whether the
provisions of the Royal Decree 30/1956 reduce the applicant's right of
access to a court in a way or to an extent which would affect the very
essence of the right concerned raises important and complex issues
concerning the interpretation of Article 6 para. 1 (Art. 6-1) of the
Convention and necessitates an examination as to the merits. It
follows that this aspect of the application cannot be considered
manifestly ill-founded within the meaning of Article 27 para. 2 (Art.
27-2) of the Convention. It must, therefore, be declared admissible,
no other grounds of inadmissibility having been established.
7. The applicant complains that he has not been given any
effective remedy with regard to OEK officials' criminal activities.
He invokes Article 13 (Art. 13) of the Convention.
The Commission however observes that Article 13 (Art. 13)
guarantees an effective remedy only to a person who has an arguable
claim that a right contained in the Convention has been violated to
his detriment (cf. for ex. No. 6753/74, Dec. 19.12.74, D.R. 2 p. 118;
No. 7308/75, Dec. 12.10.78, D.R. 16 p. 32). However, no right to
institute criminal proceedings is as such guaranteed by the Convention
(cf. No. 7116/75, Dec. 4.10.176, D.R. 7 p. 91).
It follows that the Commission has no competence ratione
materiae to examine such a complaint, which must be rejected
accordingly pursuant to Article 27 para. 2 (Art. 27-2) of the Convention.
8. Finally the applicant complains of the criminal proceedings
which have been brought against him for allegedly insulting the
judicial authorities by stating that his cases had not been decided by
an independant and impartial tribunal and of his conviction by the
First Instance criminal court of Athens.
Article 10 (Art. 10) of the Convention provides that:
"1. Everyone has the right to freedom of expression.
This right shall include freedom to hold opinions and
to receive and impart information and ideas without
interference by public authority and regardless of
frontiers. This Article shall not prevent States from
requiring the licensing of broadcasting, television or
cinema enterprises.
2. The exercise of these freedoms, since it carries with
it duties and responsibilities, may be subject to such
formalities, conditions, restrictions or penalties as are
prescribed by law and are necessary in a democratic society,
in the interests of national security, territorial integrity
or public safety, for the prevention of disorder or crime,
for the protection of health or morals, for the protection
of the reputation or rights of others, for preventing the
disclosure of information received in confidence, or for
maintaining the authority and impartiality of the judiciary."
However, the Commission is not required to decide whether or
not the facts alleged by the applicant disclose any appearance of a
violation of this provision as, under Article 26 (Art. 26) of the
Convention, it may only deal with a matter after all domestic remedies
have been exhausted according to the generally recognised rules of
international law.
In the present application the applicant's case is still
pending before the Court of Appeal and therefore, the applicant's
conviction by the First Instance Court cannot be regarded as final.
Since the applicant's complaints can be brought before the Court of
Appeal and subsequently before the Court of Cassation, the Commission
finds that he has not exhausted the remedies available to him under
Greek law, within the meaning of Article 26 (Art. 26) of the Convention.
Moreover, an examination of the case as it has been submitted does not
disclose the existence of any special circumstances which might have
absolved the applicant, according to the generally recognised rules of
international law, from exhausting the domestic remedies at his
disposal.
It follows that the applicant has not complied with the
condition as to the exhaustion of domestic remedies. This part of
the application must be rejected under Article 27 para. 3 (Art. 27-3)
of the Convention.
For these reasons, the Commission
DECLARES ADMISSIBLE, without prejudging the merits of the
case, the complaint regarding the access of the applicant to
a court (point 6 of THE LAW part), and
DECLARES THE REMAINDER OF THE APPLICATION INADMISSIBLE.
Secretary to the Commission President of the Commission
(H.C. KRÜGER) (C.A. NØRGAARD)
LEXI - AI Legal Assistant
