PODBIELSKI v. POLAND
Doc ref: 27916/95 • ECHR ID: 001-3605
Document date: April 15, 1997
- Inbound citations: 0
- •
- Cited paragraphs: 0
- •
- Outbound citations: 3
AS TO THE ADMISSIBILITY OF
Application No. 27916/95
by Janusz PODBIELSKI
against Poland
The European Commission of Human Rights (Second Chamber) sitting
in private on 15 April 1997, the following members being present:
Mrs. G.H. THUNE, President
MM. J.-C. GEUS
G. JÖRUNDSSON
A. GÖZÜBÜYÜK
J.-C. SOYER
H. DANELIUS
F. MARTINEZ
M.A. NOWICKI
I. CABRAL BARRETO
J. MUCHA
D. SVÁBY
P. LORENZEN
E. BIELIUNAS
E.A. ALKEMA
A. ARABADJIEV
Ms. M.-T. SCHOEPFER, Secretary to the Chamber
Having regard to Article 25 of the Convention for the Protection
of Human Rights and Fundamental Freedoms;
Having regard to the application introduced on 31 March 1995 by
Janusz PODBIELSKI against Poland and registered on 20 July 1995 under
file No. 27916/95;
Having regard to:
- the reports provided for in Rule 47 of the Rules of Procedure of
the Commission;
- the observations submitted by the respondent Government
on 22 February 1996 and the observations in reply submitted by
the applicant on 9 April 1996;
Having deliberated;
Decides as follows:
THE FACTS
The applicant, a Polish citizen born in 1949, is a businessman
residing in Swidnica.
The facts of the case, as submitted by the parties, may be
summarised as follows:
In May 1992 the applicant filed an action with the Wroclaw
Regional Court (S*d Wojewódzki) against the municipality of Swidnica,
claiming payment due for construction works which the applicant's
company had carried out for the municipality on the basis of a contract
of 18 February 1991.
On 27 May 1992 the Wroclaw Regional Court partly exempted the
applicant from the advance court fees.
On 7 September 1992 the Wroclaw Regional Court pronounced a
partial judgment in which it declared null and void certain clauses of
the contract between the parties as being in breach of civil law.
Upon the applicant's appeal, on 6 November 1992 the Wroclaw Court
of Appeal (S*d Apelacyjny) quashed this judgment and ordered the case
to be reconsidered.
On 1 February 1993 the Wroclaw Regional Court allowed the
applicant's action as regards the claim for payment and declared null
and void another clause of the contract, pertaining to the penalties
for delay in compliance with the contract.
On 27 April 1993 the Wroclaw Court of Appeal dismissed both the
applicant's and the defendant's appeals.
On 25 June 1993 the Ombudsman (Rzecznik Praw Obywatelskich) filed
an extraordinary appeal on the applicant's behalf, claiming that the
judgment was in flagrant breach of the substantive civil law and unduly
restricted the parties' freedom of contract.
On 7 October 1993 the Supreme Court (S*d Najwyzszy) dismissed the
extraordinary appeal considering that, contrary to the legal opinion
which had been established in the past against the background of
planned economy, the Civil Code in fact allowed the parties to include
clauses providing for pecuniary penalties for delay in compliance with
pecuniary contract obligations. However, the Court found that in the
present case the lower Court was justified in declaring the relevant
clauses null and void as these penalties were excessive and
disproportionate to the value of the contract.
The applicant filed a request for the reopening of the
proceedings, claiming that after the Supreme Court's judgment new
circumstances had come to light which he could not have adduced as
evidence in the previous proceedings. His request was granted and on
28 January 1994 the Supreme Court partly altered its earlier judgment
of 7 October 1993, ordering that the remaining claims be reconsidered
by the first instance court. The Court stated, inter alia, that the
previous judgments amounted to a violation of substantive law ("zostaly
wydane z obraz* prawa materialnego").
On 6 June 1994 the Wroclaw Regional Court partly allowed and
partly dismissed the applicant's request to be exempted from the
advance court fees as he had not sufficiently shown that he could not
afford to pay them.
On 20 July 1994 the Wroclaw Court of Appeal quashed the decision
of the Regional Court and terminated the proceedings concerning
exemption from the court fees. The Court considered that the partial
exemption from the court fees granted in 1992 still remained in force.
On 20 February 1995 the Walbrzych Regional Court held that the
defendant was obliged to pay pecuniary penalties to the applicant, but
reduced their sum to 1.844.300.000 zlotys as it considered that the
penalties as fixed in the contract were excessive and disproportionate
to the value of the contract. The Court dismissed the applicant's
claim for compensation for damage caused to his company by the delay
in payment as it considered that the applicant had not shown that his
company had suffered more extensive damages than those which would be
covered by the pecuniary penalties to be paid by the defendant.
The applicant appealed against this judgment, claiming that the
Court had failed to establish certain circumstances significant for the
outcome of the case. In particular the Court had failed to establish
whether the applicant's company had suffered extensive damage as a
result of the defendant's failure to effect the payment on time.
On 12 April 1995 the Walbrzych Regional Court partly exempted the
applicant from the court fee due for his appeal and ordered him to pay
a partial court fee of 40.000 zlotys.
On 1 May 1995 the applicant filed an appeal against this
decision. On 25 May 1995 the Wroclaw Court of Appeal allowed the
appeal, considering that the financial situation of the applicant's
company justified such exemption.
On 31 August 1995 the Wroclaw Court of Appeal quashed the
judgment of 20 February 1995 insofar as it had dismissed the
applicant's claim for payment of 782.175,59 new zlotys and ordered that
that part of the case be reconsidered. The Court stated, inter alia,
that the Regional Court had wrongly formulated the questions to the
accounting expert in that certain questions were too restrictive and
that the Court had requested him to establish the causal link between
the defendant's delay in payment and the damage sustained by the
applicant company which was a matter for the Court to establish. The
Court dismissed the remainder of the appeal.
On 23 October 1996 the Walbrzych Regional Court dismissed the
applicant's claim as to 782.175,59 new zlotys. On 29 November 1996 the
applicant's company filed an appeal against the judgment.
On 3 January 1997 the Walbrzych Regional Court exempted the
applicant's company from the court fee for the appeal as regards the
sum exceeding 20.000 zlotys and dismissed the remainder of the
applicant's request for the exemption. The applicant lodged an appeal.
On 13 February 1997 the Wroclaw Court of Appeal dismissed the appeal,
considering that the applicant's company had in fact at its disposal
sufficient financial means to pay the court fee.
COMPLAINTS
The applicant complains under Article 6 para. 1 of the Convention
about the length of the proceedings.
PROCEEDINGS BEFORE THE COMMISSION
The application was introduced on 31 March 1995 and registered
on 20 July 1995.
On 18 October 1995 the Commission decided to communicate the
application to the respondent Government pursuant to Rule 48 para. 2
(b) of its Rules of Procedure.
The Government's written observations were submitted on
22 February 1996, after an extension of the time-limit fixed for that
purpose. The applicant replied on 9 April 1996.
THE LAW
1. The applicant complains under Article 6 para. 1 (Art. 6-1) of the
length of the civil proceedings.
Article 6 para. 1 (Art. 6-1), insofar as relevant, states:
"In the determination of his civil rights and obligations ...,
everyone is entitled to a ... hearing within a reasonable time
..."
a) The Government submit that the application, insofar as it relates
to events prior to the date of recognition of the right of individual
petition by Poland, is outside the competence ratione temporis of the
Commission.
The Commission recalls that Poland has recognised the competence
of the Commission to receive individual applications "from any person,
non-governmental organisation or group of individuals claiming to be
a victim of a violation of the rights recognised in the Convention
through any act, decision or event occurring after 30 April 1993". It
follows that the Commission is not competent to examine complaints
relating to violations of the Convention by acts, decisions or events
that have occurred prior to this date.
The Commission further recalls that in cases where it can, by
reason of its competence ratione temporis, only examine part of the
proceedings, it can take into account, in order to assess the length,
the stage reached in the proceedings at the beginning of the period
under consideration (see No. 7984/77, Dec. 11.7.79, D.R. 16, p. 92).
In the present case the proceedings started in May 1992 and are
currently pending before the Court of Appeal. They have thus lasted
four years and eleven months, out of which three years and eleven
months after the recognition of the Commission's competence to examine
applications against Poland. It follows that the Commission is
competent ratione temporis to examine the applicant's complaint insofar
as it relates to the proceedings after 30 April 1993, taking into
consideration the stage of the proceedings reached at this date.
b) The Government further submit that the applicant is not a victim
of the alleged violation within the meaning of Article 25 (Art. 25) of
the Convention as it was the applicant's company "Polpure" which had
signed the contract from which originated the subsequent proceedings
and filed the court action. It was also the company which suffered the
alleged financial difficulties arising out of the execution of the
contract.
The applicant submits that he is the sole shareholder of the
company and that therefore he is the victim of the violation of the
Convention. The financial difficulties of the company due to the
excessive length of the proceedings also caused a significant
deterioration of his personal financial situation.
The Commission observes that the applicant's company is a limited
liability partnership with legal personality, owned entirely by the
applicant. The Commission considers that the applicant, given his
shareholding in the company and his position as managing director, can
claim to be a victim of an alleged breach of the Convention, affecting
the rights of his company (No. 10259/83, Dec. 10.12.84, D.R. 40,
p. 170).
c) Under Article 26 (Art. 26) of the Convention, the Commission may
only deal with a matter after all domestic remedies have been
exhausted.
The Government contend that the applicant cannot be regarded as
having exhausted available domestic remedies with regard to the
complaint about the length of the proceedings. The Government submit
that there is no single general remedy available under Polish law to
complain about the length of proceedings. However, they submit that
the usual judicial remedies, i.e. appeals against procedural and
substantive court decisions, could be employed in this respect. The
applicant has not shown that he relied on the length of proceedings in
the appeals which he had filed against various judgments on the merits
of the case. Neither has he complained about the length of the
proceedings in his appeals against the procedural decisions.
The applicant submits that he exhausted all possible domestic
remedies in the civil proceedings as he filed appeals against the
judgments of the merits. Moreover, he complained to the Minister of
Justice and to the Ombudsman about the length of the proceedings.
However, none of those remedies proved to be effective.
The Commission recalls in this respect its finding that there is
no effective remedy under Polish law to complain about the length of
civil proceedings (No. 24559/94, Dec. 6.9.95, D.R. 82-B, p. 76).
Therefore the Commission finds that it has not been established that
the applicant had any effective remedy at his disposal which would have
enabled him to submit his complaints under Article 6 para. 1 (Art. 6-1)
of the Convention to the domestic authorities. Accordingly, the
application cannot be declared inadmissible for non-exhaustion of
domestic remedies.
2. As regards the substance of the complaint, the Government first
contend that the case was highly complex as to its legal contents. In
particular, the contract concluded by the applicant's company and the
defendant was unclear as regards the rights and obligations of the
parties in respect of pecuniary penalties for delay in compliance with
pecuniary contract obligations. The complexity of the case is shown
by the fact that the case has been examined four times by the first
instance court and eight judgments were pronounced in the case,
including two of the Supreme Court and three of the Wroclaw Court of
Appeal. Moreover, several expert opinions had to be taken.
The Government further contend that the applicant's conduct
contributed considerably to the prolongation of the proceedings. They
submit that after the Supreme Court's judgment of 7 October 1993 the
applicant submitted a new claim for compensation of damages caused by
the delay in the defendant's compliance with the terms of the contract.
In the course of the proceedings the applicant several times requested
adjournments of hearings, usually for one month, for the purposes of
negotiations regarding a possible friendly settlement, which finally
was not concluded. The applicant's lawyer practised in Lódz,
approximately three hundred kilometres from Swidnica. Due to his being
ill several times during the proceedings, the service of certain
decisions was delayed. The applicant on numerous occasions appealed
against the decisions concerning the court costs. He further called
into question the soundness of the expert opinions and his objections
had to be communicated to the experts for reply.
The Government further state that the prolongation of the
proceedings cannot be attributed to the conduct of the courts which
were particularly diligent in the handling of the case.
The Government conclude that the case was dealt with within a
reasonable time.
The applicant contests this. He submits that it is the striking
feature of the case that the judgments on the merits of the case were
flawed by flagrant breaches of law, as shown by the judgments of the
appellate courts. It was mostly those legal shortcomings which
contributed to the length of the proceedings as these decisions were
subsequently quashed and the case had to be reconsidered. The case was
not particularly complex as it involved only a determination of the
obligations of the parties to an ordinary civil contract. The clauses
of the contract were in fact clear in this respect and cannot be
regarded as ambiguous.
The applicant further states that, contrary to the Government's
submissions, only one expert opinion was prepared in the case. The
applicant emphasises that the Government's observations contain general
and vague statements as to the conduct of the case and do not provide
concrete details in this regard. In particular, he submits that there
was only one opinion of an accounting specialist prepared in the course
of the proceedings, not several as submitted by the Government, and
that it contained 44 obvious arithmetical errors. Likewise, they had
not substantiated their statement as to the delays in the service of
certain court decisions which should be attributed to the applicant's
representative. He further states that he did not request the
adjournment of certain hearings.
The Commission considers that the applicant's above complaint
raises serious issues of fact and law under the Convention the
determination of which should depend on an examination of the merits.
It follows that this part of the application cannot be dismissed as
manifestly ill-founded within the meaning of Article 27 para. 2
(Art. 27-2) of the Convention. No other ground for declaring it
inadmissible has been established.
For these reasons, the Commission, by a majority,
DECLARES THE APPLICATION ADMISSIBLE, without prejudging the
merits.
M.-T. SCHOEPFER G.H. THUNE
Secretary President
to the Second Chamber of the Second Chamber
LEXI - AI Legal Assistant
