VEIT v. GERMANY
Doc ref: 10474/83 • ECHR ID: 001-45387
Document date: March 12, 1987
- Inbound citations: 0
- •
- Cited paragraphs: 0
- •
- Outbound citations: 1
Application No. 10474/83
Otto VEIT
against
the FEDERAL REPUBLIC OF GERMANY
REPORT OF THE COMMISSION
(adopted on 12 March 1987)
TABLE OF CONTENTS
Page
I. INTRODUCTION
(paras. 1-18) ......................................... 1
A. The application
(paras. 2-7) .................................. 1
B. The proceedings
(paras. 8-13) ................................. 2
C. The present Report
(paras. 14-18) ................................ 3
II. ESTABLISHMENT OF THE FACTS
(paras. 19-68) ........................................ 4
A. Relevant domestic legislation
(paras. 19-21) ................................ 4
B. Particular circumstances of the case
(paras. 22-68) ................................ 6
a) Institution of court proceedings
(paras. 22-25).............................. 6
b) Proceedings before the Stuttgart Court
of Appeal
(paras. 26-60).............................. 6
aa) Evidence proceedings
(paras. 27-53).......................... 6
bb) Conclusion of the appeal proceedings
(paras. 54-60).......................... 10
c) Proceedings before the Federal Court
of Justice and the Federal Constitutional
Court
(paras. 61-66).............................. 11
d) Final conclusion of litigation
(paras. 67-68).............................. 12
III. SUBMISSIONS OF THE PARTIES
(paras. 69-105) ....................................... 13
A. The applicant
(paras. 70-80) ................................ 13
B. The Government
(paras. 81-105) ............................... 15
a) On the admissibility
(paras. 81-89) ............................. 15
b) On the merits
(paras. 90-105) ............................ 17
IV. OPINION OF THE COMMISSION
(paras. 106-142) ...................................... 21
A. Point at issue
(para. 106) ................................... 21
B. Applicability of Article 6 para. 1
(paras. 107-108) .............................. 21
C. Period to be taken into consideration
(paras. 109-113) .............................. 21
D. Relevant criteria
(para. 114) ................................... 22
E. Complexity of the case
(paras. 115-119) .............................. 22
F. Conduct of the parties
(paras. 120-125) .............................. 23
G. Conduct of the authorities
(paras. 126-138) .............................. 25
H. Overall assessment
(paras. 139-141) .............................. 27
I. Conclusion
(para. 142) ................................... 28
APPENDIX I : History of the proceedings before
the Commission ............................. 29
APPENDIX II : Decision on the admissibility of
the application ............................ 31
APPENDIX III : Commission's proposals (separate document)
I. INTRODUCTION
1. The following is an outline of the case as submitted to the
European Commission of Human Rights, and of the procedure before the
Commission.
A. The application
2. The applicant, a German citizen and businessman, resided in
Stuttgart. He died on 7 February 1982. His widow who resides in
Stuttgart is the sole heir.
3. The applicant was represented before the Commission by
Mr. H.-J. Pohl, a lawyer practising in Mannheim, who is now also
representing the applicant's widow before the Commission.
The Government of the Federal Republic of Germany have been
represented by their Agent, Mrs. I. Maier, Ministerialdirigentin in
the Federal Ministry of Justice.
4. The application concerns court proceedings in which the
applicant was involved. The latter was the owner of a warehouse in
Stuttgart which was built by the W. company in 1970. On 17 May 1971
the W. company brought an action before the Stuttgart Regional Court
in which it requested from the applicant the remaining payment for the
construction expenses of the warehouse. The applicant put forward
counter-claims based on alleged deficiencies in the construction work
which the W. company had carried out. By judgment of 10 September
1971 the Stuttgart Regional Court ordered the applicant to pay the W.
company a sum of approximately 660,000.-DM.
5. The applicant appealed against this decision to the Stuttgart
Court of Appeal on 12 November 1971. On 28 July 1972 the Court of
Appeal instructed an expert to prepare an opinion on the construction
expenses and the alleged deficiencies of the warehouse. Following
numerous further submissions by the parties and a number of visits on the
spot, the expert submitted his opinion to the Court on 13 January 1977,
i.e. approximately 4 1/2 years after his instruction. On 31 March 1977
the Court of Appeal rejected the applicant's appeal in its essential parts.
6. The applicant's subsequent appeal on points of law to the
Federal Court of Justice was dismissed though on 11 June 1980 this
decision was quashed by the Federal Constitutional Court on the ground
that it had been insufficiently substantiated. The Federal Court of
Justice then again dismissed the appeal. The applicant's renewed
constitutional complaint was dismissed by the Federal Constitutional
Court on 5 March 1981.
7. When introducing the application, the applicant complained
under Article 6 para. 1 of the Convention of the length of the
proceedings, in particular of the long delay caused by the preparation
of the expert opinion before the Court of Appeal. He also alleged a
violation of his right, under Article 6 para. 1, to a fair hearing.
Following the applicant's death his widow pursued the
proceedings before the Commission.
B. The proceedings
8. The application was introduced on 2 September 1981 and
registered on 4 July 1983. On 7 December 1983 the Commission decided
in accordance with Rule 42 para. 2 (b) of its Rules of Procedure to
give notice of the application to the respondent Government and to
invite them to present before 25 February 1984 their observations in
writing on the admissibility and merits of the application.
9. By letter of 16 February 1984 the Government submitted
information indicating that the applicant had died. They requested
that the application should be struck off the list of the Commission's
cases as the applicant's heirs could not be considered to have a
sufficient legal interest of their own in a continuation of the case.
By letter of 18 April 1984 the applicant's representative
informed the Commission that the applicant had died on
7 February 1982, and that his widow, Mrs. Erna Veit, who had inherited
him wished to continue the case before the Commission.
On 11 July 1984 the Commission decided that there were not
sufficient reasons to strike the application off its list of cases.
It therefore maintained its decision of 7 December 1983 to invite
the Government to submit observations on the admissibility and merits
of the application.
10. Following requests on 30 October and 27 November 1984 for
extension of time-limits, the Government's observations of
14 December 1984 were received on 28 December 1984. Following a
request on 18 March 1985 for extension of the time-limit, the reply of
the applicant's widow of 26 April 1985 was received on 30 April 1985.
11. On 8 July 1985 the Commission decided to invite the parties to
a hearing on the admissibility and merits of the applicant's complaint
under Article 6 para. 1 concerning the length of the proceedings.
The hearing took place on 6 May 1986. The applicant's widow
who was present was assisted by Mr. H.-J. Pohl, as her
representative, and Mr. R. Schuhmann, as adviser. The respondent
Government were represented by Mr. H.A. Stöcker, Agent and
Ministerialrat in the Federal Ministry of Justice, as well as by Mrs.
R. Adlerstein, Regierungsdirektorin in the Federal Ministry of
Justice, and Mr. H. Krukenberg, judge at the Stuttgart Court of
Appeal, as advisers.
12. Following the hearing the Commission declared admissible the
complaint concerning the length of the court proceedings and declared
inadmissible the remainder of the application.
13. After declaring the case in part admissible, the Commission,
acting in accordance with Article 28 (b) of the Convention, placed
itself at the disposal of the parties with a view to securing a
friendly settlement of the case. Consultations with the parties took
place between 6 May and 26 November 1986. In the light of the
parties' reaction, the Commission now finds that there is no basis
upon which such a settlement can be effected.
C. The present Report
14. The present Report has been drawn up by the Commission in
pursuance of Article 31 of the Convention and after deliberation and
votes, the following members being present:
MM. C.A. NØRGAARD, President
G. SPERDUTI
J.A. FROWEIN
G. JÖRUNDSSON
B. KIERNAN
A.S. GÖZÜBÜYÜK
A. WEITZEL
J.C. SOYER
H.G. SCHERMERS
H. DANELIUS
H. VANDENBERGHE
15. The text of this Report was adopted on 12 March 1987 and is
now transmitted to the Committee of Ministers of the Council of Europe
in accordance with Article 31 para. 2 of the Convention.
16. The purpose of the Report, pursuant to Article 31 para. 1 of
the Convention, is:
i) to establish the facts, and
ii) to state an opinion as to whether the facts found
disclose a breach by the State concerned of its
obligations under the Convention.
17. A schedule setting out the history of the proceedings before
the Commission is attached hereto as Appendix I and the Commission's
decision on the admissibility of the application as Appendix II.
18. The full text of the parties' submissions, together with the
documents lodged as exhibits, are held in the archives of the
Commission.
II. ESTABLISHMENT OF THE FACTS
A. Relevant domestic legislation
19. The court proceedings in which the applicant was involved fall
under the German Code of Civil Proceedings (Zivilprozessordnung).
Sections 402-414 of the Code govern, also in respect of appeal
proceedings, the evidence given by experts (Beweis durch
Sachverständige).
20. According to S.404(1), and subject to paras. (2)-(4), the
court will select the experts and determine their number. S. 409
concerns the consequences of failure to appear or of refusal (Folgen
des Ausbleibens oder der Weigerung) and reads:
"(1) Im Falle des Nichterscheinens oder der Weigerung eines
zur Erstattung des Gutachtens verpflichteten
Sachverständigen werden diesem die dadurch verursachten
Kosten auferlegt. Zugleich wird gegen ihn ein Ordnungsgeld
festgesetzt. Im Falle wiederholten Ungehorsams kann das
Ordnungsgeld noch einmal festgesetzt werden.
(2) Gegen den Beschuss findet Beschwerde statt."
(translation)
"(1) If an expert who has been instructed to give an expert
report fails to appear or refuses to do so, the costs
occasioned thereby shall be borne by him. He will also be
ordered to pay a disciplinary fine. In the event of
repeated disobedience, a further disciplinary fine may be
imposed.
(2) The decision is appealable."
S.411 concerns the written expert opinion (schriftliches
Gutachten) and reads:
"(1) Wird schriftliche Begutachtung angeordnet, so hat der
Sachverständige das von ihm unterschriebene Gutachten auf
der Geschäftsstelle niederzulegen. Das Gericht kann ihm
hierzu eine Frist bestimmen.
(2) Versäumt ein zur Erstattung des Gutachtens
verpflichteter Sachverständiger die Frist, so kann gegen ihn
ein Ordnungsgeld festgesetzt werden. Das Ordnungsgeld muss
vorher unter Setzung einer Nachfrist angedroht werden. Im
Falle wiederholter Fristversäumnis kann das Ordnungsgeld in
der gleichen Weise noch einmal festgesetzt werden. § 409
Abs. 2 gilt entsprechend.
(3) Das Gericht kann das Erscheinen des Sachverständigen
anordnen, damit er das schriftliche Gutachten erläutere."
(translation)
"(1) If a written expert opinion is ordered, the expert
shall deposit the opinion bearing his signature at the court
office. The Court can impose a time-limit.
(2) If an expert who has been instructed to give an
expert opinion fails to observe the time-limit, a
disciplinary fine may be imposed on him. He must have
previously been threatened with the imposition of the
disciplinary fine, and an extension granted. In the event
of repeated non-observance of the time-limit, a further
disciplinary fine may be imposed. Section 409 (2) is
applicable.
(3) The Court may order the expert to appear before it in
order to provide explanations concering the written expert
opinion."
21. Alterations of the order to take evidence (Änderung des
Beweisbeschlusses) are governed by S.360 which states:
"Vor der Erledigung des Beweisbeschlusses kann keine Partei
dessen Änderung auf Grund der früheren Verhandlungen
verlangen. Das Gericht kann jedoch auf Antrag einer Partei
oder von Amts wegen den Beweisbeschluss auch ohne erneute
mündliche Verhandlung insoweit ändern, als der Gegner
zustimmt oder es sich nur um die Berichtigung oder Ergänzung
der im Beschluss angegebenen Beweistatsachen oder um die
Vernehmung anderer als der im Beschluss angegebenen Zeugen
oder Sachverständigen handelt. Die gleiche Befugnis hat der
beauftragte oder ersuchte Richter. Die Parteien sind
tunlichst vorher zu hören und in jedem Falle von der
Änderung unverzüglich zu benachrichtigen."
(translation)
"Before the order to take evidence has been executed, each
party can request its alteration on the basis of the
previous hearings. However, the Court can also, upon
application by one party or ex officio, alter the order to
take evidence even without a new oral hearing to the extent
that the opponent agrees or that it concerns merely the
correction or supplementation of facts of evidence mentioned
in the order or the hearing of witnesses or experts other
than mentioned in the order. The same authority falls to
the judge so charged or requested. The parties must be duly
heard beforehand and in each case they must immediately be
informed of the alteration."
According to para. 3 of S. 567, which concerns the
admissibility of an appeal (Zulässigkeit der Beschwerde) in particular
against procedural measures, an appeal is not possible against
decisions of courts of appeal, subject to certain provisions of the
Code not relevant to the present case.
B. Particular circumstances of the case
a) Institution of court proceedings
22. The applicant was the owner of a warehouse in
Stuttgart-Wangen, which was built by the firm Gebrüder Albert und
Ernst Waiss by virtue of a contract concluded on 12 March 1970. The
contract stipulated that the applicant would pay over 2.3 million DM
for the construction, of which he initially paid 1.7 million DM.
23. On 17 May 1971 the Waiss company brought an action before the
Stuttgart Regional Court (Landgericht) in which it requested from the
applicant the remaining payment for the construction expenses
(Werklohn) of the warehouse in the amount of 628,440 DM. The
applicant refused to pay and put forward counter-claims of more than
1 million DM. He based these counter-claims on alleged deficiencies
in the construction work that the company had carried out.
24. By partial judgment (Teilurteil) of 10 September 1971 which
numbered 62 pages the Stuttgart Regional Court ordered the applicant
to pay to the company a sum of 600,000 DM, excluding interest. The
action was rejected to the extent of 3,226.49 DM and judgment was
reserved as to the remainder of the plaintiff's claim and as to costs.
The company was permitted to offer the applicant during the
execution a directly liable bank guarantee as security amounting to
660,000 DM including interest. This bank guarantee would have been the
only asset available to the applicant to satisfy his claims if his
subsequent appeal proved to be successful and the Waiss company had
meanwhile gone bankrupt.
25. The Waiss company, which was then a company under civil law
(Gesellschaft), later became a limited partnership (Kommanditgesell-
schaft). On 16 February 1977 the company and the solely liable
partner filed bankruptcy petitions which were rejected by the
Stuttgart District Court (Amtsgericht) on 1 and 2 March 1977 on the
ground that there were no assets. The company and its partner were,
when the application was filed, without means and in liquidation.
b) Proceedings before the Stuttgart Court of Appeal
26. On 15 November 1971 the applicant appealed against the
judgment of 10 September 1971 to the Stuttgart Court of Appeal
(Oberlandesgericht). The reasons for the appeal were submitted by
letter of 28 January 1972.
aa) Evidence proceedings
27. A first hearing was held on 11 July 1972. On the same day the
applicant requested the Court in writing to visit the warehouse. By
an order of 28 July 1972 concerning the taking of the evidence
(Beweisbeschluss) the Court entrusted an engineer, Dr. A., with the
task of providing the Court with an expert opinion regarding the
deficiencies caused by dampness in the construction work. The Court
also ordered the hearing of witnesses and stated that it would visit
the warehouse together with Dr. A. The Court determined that the
expert opinion should be submitted after the visit to the warehouse.
On 1 August 1972 the documents were sent to Dr. A. to enable
him to assess the probable costs of his opinion. He replied on
1 September 1972 that these would amount to 12,000 DM. Both parties
accepted this.
28. The Court passed a further order concerning evidence on
13 November 1972, whereupon on 11 January 1973 the Court visited the
warehouse together with Dr. A. and thereby also questioned four
witnesses.
On 26 February 1973 the Court supplemented its order to take
evidence by requesting Dr. A. to comment on allegations by the
applicant concerning deficiencies of material and damage caused by
dampness.
29. On 1 March 1973 the file was sent to Dr. A. However, on
14 May and 8 June 1973 the applicant invoked new facts concerning
deficiencies caused by water. The Court therefore requested Dr. A. on
13 June 1973 to return the file.
30. On 22 June 1973 the Court supplemented its order to take
evidence. It ordered in particular a new visit to the warehouse and
the hearing of witnesses in the presence of Dr. A. The Court also
determined that Dr. A. should only prepare his opinion after this
evidence had been taken. However, on 11 July 1973 the Court told
Dr. A. that the planned visit could only take place after the Court
holidays.
31. On 28 June and 11 July 1973 the applicant announced further
deficiencies of the warehouse caused by water. Also on 11 July 1973
the Court informed the expert that a new date for the taking of
evidence would be determined after the summer recess.
On 18 July 1973 Dr. A. told the Court that in view of teaching
obligations he could only be available on a few days in autumn for a
visit to the warehouse.
32. On 24 September 1973 the Court fixed 5 November 1973 as the
new date for the taking of evidence.
33. On 27 September 1973 the applicant submitted two expert
opinions, one prepared by the Stuttgart Public Institute for Research
and Examination of Materials (Amtliche Forschungs- und Materialprüfungs-
anstalt), the other by a private expert, Mr. D. These opinions
commented on certain deficiencies of the warehouse and were
transmitted by the Court to Dr. A. on 4 October 1973.
34. On 5 November 1973 the Court executed the order to take
evidence in its extended form of 22 June 1973 by visiting the
warehouse and hearing five witnesses. The documents were then
transmitted to Dr. A.
35. On 2 and 28 November 1973 the applicant mentioned new
deficiencies, namely new cracks and new damage caused by water. He
also announced that he would furnish proof of these points by means of
a supplementary opinion of the Stuttgart institute. He requested the
opportunity to submit this opinion as well as an extension of the
time-limit to produce further documents.
36. On 4 December 1973 the Court sent the file to Dr. A. and
instructed him to prepare the opinion on the basis of the Court's
orders of 28 July 1972, 26 February 1973 and 22 June 1973, and to take
into consideration the applicant's statements of 28 November 1973.
37. On 7 December 1973 and 8 January 1974 both parties submitted
additional statements alleging new deficiencies. These statements
were transmitted to Dr. A. On 11 January 1974 the latter was
requested by the Court to undertake a supplementary visit to the
warehouse in January. Dr. A. then fixed 28 January 1974 for the visit.
On 21 January and 2 April 1974 the Court received further
contradictory statements by the parties concerning the possibilities
of repairs.
38. On 3 May 1974 the plaintiff company reminded the Court of its
interest in an early preparation of the expert opinion. On
13 May 1974 the presiding judge requested Dr. A. to submit his opinion
early.
The applicant submitted on 27 May 1974 a further opinion of
the Stuttgart institute which the Court transmitted to the expert
Dr. A. on 30 May 1974.
39. Dr. A. informed the Court on 1 June 1974 in reply to its
inquiry of 13 May 1974 that he had waited with the preparation of his
opinion until he had received the supplementary opinion of the
Stuttgart institute. He announced that after returning from his
holidays on 21 June 1974 he planned to prepare the opinion in July
1974. This letter was transmitted by the Court to both parties.
40. On 8 August 1974 the applicant requested the Court to remind
Dr. A. that his opinion should be prepared at an early date. The
Court transmitted this request to Dr. A. on 3 September 1974. On
2 October 1974 the applicant asked the Court whether Dr. A.'s opinion
had been submitted. The letter continues: "Should the opinion not yet
be ready, it is politely requested to remind the expert of its
preparation." On 9 October 1974 the Court again requested the
expert to deliver his opinion promptly. On 11 October 1974 the Court
informed the applicant of this request.
41. On 15 October 1974 the applicant filed photographs allegedly
showing new deficiencies of the warehouse which had only become
apparent in October 1974. He also announced the submission of further
photographs to evidence the development of new cracks in the walls of
the warehouse. Thereupon, on 18 October 1974, the Court instructed
the plaintiff to comment on these new statements before
4 November 1974. The applicant was told to produce the further
photographs as soon as possible.
These photographs were submitted by the applicant on
24 October 1974 together with an opinion of his private expert, Mr. D.
A copy of the opinion had been sent directly to Dr. A.
42. After a further extension of the plaintiff's above time-limit,
the latter submitted on 9 November 1974 a statement containing an
opinion of the company's own private expert, Mr. S., on the opinion of
the applicant's private expert, Mr. D. The plaintiff also requested
an early preparation of Dr. A.'s opinion.
43. From 12 November 1974 onwards, a new lawyer represented the
applicant.
44. In an order of 13 November 1974 the Court supplemented its
decisions of 28 July 1972, 26 February and 22 June 1973. It
instructed Dr. A. also to consider the new deficiencies alleged by the
applicant in his statements of 15 and 24 October 1974 and to comment
on the possibilities and expenses of repairs as well as on a possible
depreciation in value of the warehouse.
On 15 November 1974 the Court again sent the file to Dr. A.
together with the photographs and the new private expert opinions.
45. On 10 December 1974 the Court received a statement by the
applicant in respect of the new deficiencies which had appeared. This
statement was communicated to Dr. A.
On 26 May 1975 the applicant suggested to the Court that it
remind Dr. A. that his opinion was overdue. The letter continues:
"Consideration might be given to setting the expert a formal
time-limit." On 28 May 1975 the Court transmitted this statement to
Dr. A. who at the same time was urgently requested to submit his
opinion speedily.
46. Meanwhile, the Court appointed a new rapporteur who on 16
September 1975 asked Dr. A. when he would submit his opinion. The
latter replied on 2 October 1975 that he would probably do so in
spring 1976. Dr. A. explained in his letter that the recession in the
building industry had resulted in an unpredictable wave of proceedings
for preserving evidence, and that all his normal engagements as court
expert had been disrupted. He was involved as expert in other major
building proceedings which would occupy him until the end of 1975. The
preparation of the opinion could be envisaged for spring 1976.
47. On 3 February 1976 the plaintiff formally requested the Court
to set a time-limit for the submission of Dr. A.'s opinion. The Court
answered that the conditions therefore were, as yet, not met since
Dr. A. himself had announced that the opinion would be ready by spring
1976; this announcement had not been opposed by either of the parties.
Nevertheless, Dr. A. had been instructed to keep within this
time-limit. If this did not happen, the Court would give a ruling on
the application for a time-limit to be set.
48. On 23 March 1976 Dr. A. told the Court that he would make a
"technical" visit to the warehouse which eventually took place on 27
April 1976 with the parties and their private experts, Messrs. D. and
S., but not the judge, being present. On 29 April 1976 Dr. A.
informed the Court that he needed further information concerning the
issue of diminution of value. For these purposes the parties
exchanged further pleadings and submitted contradictory statements on
12 May and 28 June 1976.
On 12 July 1976 Dr. A. explained in a letter to the Court that
the heat wave of the past weeks had delayed the conclusion of his
opinion.
49. On 9 and 18 August 1976 the applicant submitted further
opinions of his private expert, Mr. D., upon which the plaintiff
commented on 30 August and 21 September 1976. The plaintiff also
submitted an opinion of its private expert Mr. S.
50. On 29 September 1976 Dr. A. informed the Court that he was
entering the final stages of preparing the opinion and was including
therein the parties' submissions of the current year. However, until
the end of October 1976 he would be abroad. This information was
passed on to the parties on 30 September.
On 4 October 1976 the applicant requested in a letter to the
Court that the expert be urged to submit his opinion. The applicant
also commented on the plaintiff's statement of 30 August 1976. On 7
October 1976 Dr. A.'s secretariat informed the Court that the opinion
would soon be ready.
51. On 16 November 1976 Dr. A. told the Court's rapporteur on the
telephone that the opinion would be ready before Christmas.
52. On 19 October, 25 November and 15 December 1976 the parties
submitted further statements and evidence. On 15 December the
plaintiff requested the Court to send to Dr. A. an expert opinion
prepared by the expert Mr. P. concerning a different case.
53. On 13 January 1977 Dr. A. personally delivered to the Court
his opinion dated 29 December 1976 of 37 pages. The applicant's
representative received a copy on 19 January 1977.
bb) Conclusion of the appeal proceedings
54. On 4 January 1977 the Court ordered a hearing to be held on
22 March 1977 at which the parties were to be present.
55. On 14 February 1977 the applicant's representative requested
to see the case-file on the ground that certain documents might have
been lost due to the applicant's change of representatives. The file
was then made available to the applicant's representative from 18 to
23 February 1977.
56. On 16 March 1977 the applicant requested a postponement of the
hearing in order sufficiently to prepare the hearing and to enable his
private expert, Professor Dr. Dr. L., to study Dr. A.'s opinion. This
was refused by the Court on 17 March 1977.
57. At the hearing of 22 March 1977 the applicant submitted a
further statement, dated 21 March 1977, with four annexes and
requested them to be taken into account by the Court. The Court
refused the postponement and reserved its decision as to the issue
whether or not the statement and annexes should be utilised. The
Court also refused the applicant's request to appoint L. as court
expert.
10473/83
At the hearing the Court then heard Dr. A., and the parties
put questions to him. The applicant's representative was also able to
include in his submissions Prof. L.'s provisional criticism of Dr.
A.'s opinion. The applicant's private expert D. was also present.
58. On 24 March 1977 the applicant requested the judges of the
Court to visit the warehouse since the Court, in its present
composition, had not yet personally seen the warehouse.
59. On 31 March 1977 the Stuttgart Court of Appeal pronounced its
judgment in which it partly altered the lower court's judgment and
arrived at new conclusions. The judgment, which was made available on
7 April and numbered 110 pages, rejected on the basis of Dr. A.'s
opinion the applicant's appeal in its essential parts.
The amount the applicant had to pay to the company was fixed at
571,924 DM and his counter-claims were not accepted, since the Court
arrived at the conclusion, on the basis of Dr. A.'s opinion, that there
were not, on the whole, any deficiencies in the construction work of
the kind the applicant had alleged. The action was dismissed to the
amount of 31,301 DM.
60. On 23 May 1977 the applicant's expert, Prof. L., prepared an
opinion of 14 pages in which he stated, inter alia, that the decision
of the Court of Appeal diverged strongly from the facts, and that Dr.
A. had insufficiently considered deficiencies and damages which had
been irrefutably evidenced by the applicant's private expert Mr. D.
c) Proceedings before the Federal Court of Justice
and the Federal Constitutional Court
61. The applicant's further appeal on points of law (Revision) to
the Federal Court of Justice (Bundesgerichtshof) was rejected on
19 January 1978.
62. The applicant lodged a constitutional complaint with the
Federal Constitutional Court (Bundesverfassungsgericht) on 20 February
1978. Therein he complained inter alia of a violation of his right to
a hearing in accordance with the law, as guaranteed by Article 103
para. 1 of the Basic Law (Grundgesetz). In respect of the complaint
that he was not granted sufficient time to comment on the opinion of
Dr. A., he stated that "the expert required 4 1/2 years for his
opinion. This shows how difficult the investigation was."
63. Following a decision of 11 June 1980 by the plenary Federal
Constitutional Court, the first chamber (Senat) of the Court decided
on 18 November 1980 to quash the decision of the Federal Court of
Justice of 19 January 1978 and to refer the case back to that Court on
the ground that the latter had not sufficiently motivated its
rejection of the appeal on points of law.
64. On 18 December 1980 the Federal Court of Justice again
rejected the appeal on points of law stating that the case did not
involve any point of principle and did not offer any prospect of
success.
65. The applicant then again filed with the Federal Constitutional
Court a constitutional complaint on 29 January 1981. Therein he
complained of a violation of Article 103 para. 1 and Article 3 para. 1
of the Basic Law. The complaint stated that "the respective members
of the (Court) Senate which were dealing with the case did not have
'the courage' to treat the matter on account of its volume and the
difficulty of the subject-matter."
66. The constitutional complaint was rejected by the Federal
Constitutional Court on 5 March 1981 as not offering sufficient
prospect of success. Insofar as the applicant had invoked Article 6
of the Convention, the Court rejected the appeal as being inadmissible
on the ground that a constitutional complaint could not be based on
provisions of the Convention. The decision was served on the
applicant's representative on 10 March 1981.
d) Final conclusion of litigation
67. On 16 February 1973 the Stuttgart Regional Court delivered
final judgment in the litigation between Waiss Brothers and the
applicant (cf. paras. 22 f above). The applicant was ordered to pay
an additional sum of 17,661 DM, together with the interest thereon, as
remuneration for work expenses. The remainder of the plaintiff's claim
was rejected.
68. Upon appeal the applicant claimed compensation and
depreciation in value to the extent of approximately 1,000,000 DM. As
proof of the deficiencies in the warehouse, the applicant relied on
experts' reports and submitted a report dated 23 May 1977 prepared by
L. In a further pleading, the applicant presented a counter-claim
according to which the Waiss company were to pay him 660,000 DM
together with the interest thereon. On 6 June 1978 the Stuttgart
Court of Appeal dismissed the appeal and the counter-claim as being
unfounded. The applicant's appeal on points of law to the Federal
Court of Justice and his subsequent constitutional complaint were both
unsuccessful.
III. SUBMISSIONS OF THE PARTIES
69. The following is a summary of the parties' main arguments,
submitted at the admissibility stage and during the examination of the
merits, on the merits of the admitted complaint concerning the length
of the proceedings.
A. The applicant
70. The applicant and, after his death, his widow refer to the
proceedings before the Court of Appeal which lasted from the
submission of the appeal statement in January 1972 until the hearing
of 22 March 1977. In this respect, only delays attributable to
domestic authorities and courts would allow a conclusion that the
requirement of a reasonable time has not been observed. However, the
assertion is disputed that the length of the proceedings was caused,
not by the respective court, but solely by Dr. A. and the new factual
submissions of the parties. In fact, the long duration of the taking
of evidence was also caused by the frequent changes of judges of the
Court of Appeal.
71. The Court of Appeal's decision to take evidence is dated 28
July 1972. The first visit to the scene took place together with the
expert on 11 January 1973. The opinion could therefore have been
ready in the months March - May 1973. The decision to take evidence
was supplemented on 22 June 1973 on account of further deficiencies.
This decision might have necessitated a supplementary expert opinion
on Dr.A.'s opinion which at this stage would already have been
prepared. After the scene had again been visited on 5 November 1973
together with the expert, his opinion could have been ready in spring
1974, if the evidence proceedings had been conducted in an orderly
manner, and no damage would then have arisen. Moreover, the order of
28 July 1972 contained six pages with 17 positions, and the order of
22 June 1973 four pages with 9 positions. It would have been possible
for the expert successively to deal with the various positions in
order speedily to conclude his opinion. In any event, the party
filing new submissions before a German court always runs the risk of
coming too late, i.e. that the court will already have given its
judgment.
72. The same considerations apply to the further extension
of 13 November 1974 of the decision to take evidence. The opinion
could now have been ready at the latest in summer 1975. The new
submissions concerning further alleged deficiencies and the statements
concerning the repair costs and the diminution of value could well
have been dealt with in a supplementary expert opinion. The Court of
Appeal could possibly also have passed a partial judgment.
Even if it is assumed that Dr. A. could only have reached his
final opinion after 15 November 1974 when the file was again sent to
Dr. A., the opinion should then have been ready by spring 1975.
However, the Court did not react adequately to the parties'
admonitions of 3 May, 8 August, 2 October and 9 November 1974 and
26 May 1975. It made no use of the possibility of determining a
time-limit or imposing a fine, and also did not appoint a new expert.
73. Such measures of the Court would have been all the more
necessary in view of Dr. A.'s explanation of 2 October 1975 that the
recession in the building trade was delaying the preparation of his
opinion. This recession only started at the end of 1973, not in 1972.
The applicant's widow also cannot accept that the expert was busy with
teaching obligations or with other cases involving high costs; or
that, after 4 years, he explained further delay with the excessive
summer heat. The Court should have rejected these explanations and
simultaneously threatened to apply procedural means. The Court could
at least have indicated to the expert that he had to grant priority to
his old appointment of 1972 as expert in the present case.
74. The new visit to the scene on 27 April 1976 was necessary
due to the new developments. It was also necessary because the
expert was no longer aware of the facts on account of the delay in
time. Even the preparation of the opinion at this stage could have
averted damage from the applicant in view of the fact that the Waiss
company only went bankrupt in 1977 and the Court of Appeal was at this
stage not yet under pressure to decide on account of the imminent
change in the person of the Court rapporteur.
75. There were delays in the proceedings after the case-file was
again transmitted to Dr. A. on 15 November 1974. It was not possible
for the parties to file an appeal under S. 567 (3) of the Code of
Civil Procedure. Both parties unsuccessfully raised with the Court of
Appeal the possibility of fixing a time-limit for the expert. However,
the Court of Appeal was not obliged, according to the Code of Civil
Procedure, to determine such time-limits or to terminate the expert's
appointment since such a measure fell within the Court's discretion.
The parties were legally powerless in respect of the various
announcements of new dates by the expert. They could do no more than
make suggestions or remonstrances (Gegenvorstellungen). The parties
requested the Court on altogether seven occasions to remind the expert
of his opinion. Moreover, before the Court of Appeal polite language
is used; one does not "thump on the table". To request more rigid
measures would have meant alienating the expert and, if a new expert
had been nominated, to prolong the proceedings.
76. The Court of Appeal did not exercise its discretion without
fault. The development of the delays since 1972 demonstrated that it
was insufficient for the Court merely to make urgent requests to the
expert. Moreover, after the new visit to the scene on 27 April 1976,
the Court should have determined a final time-limit for the delivery
of the opinion. The Government confirm that the Court of Appeal had
to expedite proceedings. Finally, if it is true that the expert would
not have accepted time-limits being fixed for him, this should have
prompted the Court very early on to think of a replacement.
77. It can also not be said that the applicant had, until November
1974, himself caused the delay in the preparation of the expert
opinion by requesting extensions of the taking of evidence and by
alleging new deficiencies. Long before that point the expert should
have prepared his opinion on the basis of the original procedural
situation. Subsequent complaints concerning new deficiencies could
possibly have led to a supplementary expert opinion. The Court of
Appeal would at that stage have had a sufficient basis for
deliberating on, and adjudicating, the original deficiencies.
78. The obligation of the German courts to expedite proceedings
has been seriously violated by the Court of Appeal. Already in the
Buchholz case the Commission regarded time-limits of five to six
months as constituting an extraordinary delay (Comm. Report 14.5.80).
The Court did not employ the effective measures at its disposal, and
it was insufficient only to ask the expert about the state of the
proceedings and at the same time to transmit the parties' admonitions.
In the present case, especially strict standards had to be applied as
the object of litigation was of extraordinary importance to the
applicant (see Eur. Court H.R., König judgment of 23 April 1977,
Series A no. 27 para. 111).
79. The applicant's widow submits that the possible damages
amounted at least to 660,000 DM. These damages occurred because,
after failing in the appeal proceedings, the applicant could not be
repaid the amount expended after the first instance decision, i.e.
more than 600,000 DM as well as interests and costs. The bank
guarantee amounting to 660,000 DM had to be given back. Such damages
would normally not have arisen if evidence had been taken speedily.
There would either have been a different result, or the applicant's
objections would have been heard. Had the proceedings been conducted
in an orderly manner, the pressure to pass judgment which lay on the
Court of Appeal in March 1977 due to an imminent change of a judge
would not have occurred.
80. The applicant's widow concludes that the Federal Republic of
Germany has violated Article 6 para. 1 of the Convention and the
rights of the applicant and his heir by means of the decision of the
Federal Constitutional Court of 5 March 1981 and the judgment of the
Court of Appeal of 31 March 1977, and that they have suffered damages
of 660,000 DM.
B. The Government
a) On the admissibility
81. In their further observations on the merits of the application
the Government have included the following submissions on the
admissibility of the application so that failure to do so may not be
held against them, should the application subsequently be examined by
the Court (see Eur. Court H.R., Corigliano judgment of 10 December
1982, Series A No. 57, p. 11 para. 26).
82. In the Government's view it is insufficient under Article 26
of the Convention for the applicant to have raised the complaint of
the undue length of proceedings by means of a constitutional complaint
only after final completion of the proceedings.
83. The Government do not share the Commission's view expressed in
application No. 8961 (Dec. 8.12.81, D.R. 26, p. 202) that the question
whether the applicant could and should have taken steps to speed up
the proceedings is not one of exhaustion of remedies, but simply one
aspect of the merits of the application. The notion of "exhaustion of
domestic remedies" can in the Government's view only be interpreted
according to domestic procedural law. Even in cases such as the
present one, the applicant must have availed himself of the
possibility of submitting a constitutional complaint before being able
to make an application under Article 26 (see No. 8961/80, ibid).
84. The only issue in the present case is whether the Stuttgart
Court of Appeal failed in its duty by not setting the expert Dr. A. a
time-limit in which to complete the expert opinion, if necessary by
imposing a fine or eventually by replacing him by another expert. The
applicant assumed that there were no legal means available to him to
oppose the Court's dilatory conduct of the proceedings. He only
suggested from time to time to the Court that it should consider
setting the expert a time-limit.
This argument is in the Government's view incorrect. Thus,
the applicant could under the second sentence of S. 360 of the Code of
Civil Proceedure, have made a formal application for the
replacement of Dr. A. Only then would the Court have had grounds to
take a formal decision. Indisputably, the applicant neither applied
for a replacement nor for the imposition of a fine since he wished
Dr. A. to remain "well disposed" towards him.
85. According to S. 567 (3) of the Code of Civil Procedure, an
appeal (Beschwerde) is not possible against decisions of courts of
appeal. Moreover, in accordance with S. 567 (3), a procedural
decision of an appeal court must be challenged directly by means of a
constitutional complaint. In the present case, however, there has not
been a formal decision on the matter by the Court of Appeal, since the
applicant failed to make a formal application.
86. It follows that the applicant did not avail himself of the
possible remedies. It cannot be argued that according to the practice
of the Federal Constitutional Court a constitutional complaint would
not have been admissible until after a decision had been reached on
the appeal on points of law against the judgment of the Court of
Appeal. This argument is not borne out by the law, and the Government
refer to and cite extensively two decisions of the Federal
Constitutional Court (BVerfGE 5, 10 and 33, 247).
In the light thereof, a person wishing to lodge a
constitutional complaint must have claimed a violation of the relevant
basic right in the "most closely relevant proceedings" (sachnächstes
Verfahren) and have availed himself of the remedy specifically
provided for against the violation. The person concerned cannot be
content in such cases to lodge a constitutional complaint after final
completion of the proceedings (cf. the indication by the Federal
Constitutional Court in BVerfGE 5, 10). Moreover, it happens in
practice that constitutional complaints on grounds of undue length of
proceedings, directed against specific procedural decisions of
ordinary courts, may be filed before the final judgment has acquired
the force of res judicata; an example of such a constitutional
complaint is mentioned in the König judgment (Eur. Court H.R.,
28 June 1978, Series A No. 27 p. 23 para. 64).
87. The applicant failed to compel the Stuttgart Court of Appeal
by means of a formal application to take a formal decision, which
could have been challenged by means of a constitutional complaint.
The applicant has admitted that he did not take this obvious step to
speed up the proceedings, because he did not wish to incur the
expert's displeasure. This argument does not excuse the applicant.
The fact that the applicant constantly alleged further deficiencies
was such as to give the Court of Appeal the impression that he was in
fact not interested in substantially speeding up the proceedings. This
impression is clearly conveyed by the fact that not even in his
constitutional complaint of 20 February 1978 did the applicant claim
that he considered a right under Article 6 para. 1 of the Convention
to have been violated by the length of proceedings.
88. Furthermore, the Federal Constitutional Court's decision of
5 March 1981 must be understood to mean that in respect of Article 6
para. 1 the constitutional complaint was not properly substantiated.
However, a constitutional complaint which is disallowed for lack of
proper substantiation does not meet the requirement of exhaustion of
domestic remedies.
89. Finally, the applicant's widow can no longer have a
financially based legal interest after the application was declared
inadmissible insofar as it concerned the right to a fair hearing. The
complaint still at issue merely states that the proceedings lasted too
long, not that they would have had a different outcome.
b) On the merits
90. By way of a general introduction the Government point out
that according to the Commission's case-law the guarantees in Article
6 para. 1 need not be examined in respect of the proceedings before
the Federal Constitutional Court. Moreover, the applicant has also not
complained of the proceedings before the Regional Court or the Federal
Court of Justice. The Government therefore concentrate on the appeal
proceedings before the Court of Appeal lasting from 15 November 1971,
when the applicant filed his appeal, until 31 March 1977 when the
Court pronounced its judgment. Again, during these proceedings the
dispute is over the time taken by the expert for the preparation of
his opinion, in particular the extent to which the Court of Appeal
could at all be made responsible therefor.
91. According to the principle of party disposition governing
civil proceedings the parties have the means to determine the
commencement and termination of proceedings, e.g. by filing an action
or by withdrawing it, or by not filing any remedies. The parties may
indeed have different interests as regards the issue of expediting
civil proceedings. In this light, a violation of the requirement in
Article 6 para. 1 of the Convention that proceedings must be conducted
expeditiously can only arise in civil cases where the affected party
himself has let it be known during the proceedings that he is
interested in the speedy conduct of proceedings and therefore expects
the court to take certain measures, or reproaches the court for the
length of proceedings. On the other hand it lies in the court's
discretion whether it employs the means mentioned in S. 411 of the
Code of Civil Procedure.
92. The expert appointed by the Court of Appeal, Dr. A., was a
well-known and very busy expert in the Stuttgart District where there
was a dearth of qualified building experts. Dr. A., who was born in
1910, was nominated after 20 years' experience in the free building
market by the Regional Administration (Regierungspräsidium) of North
Württemberg as expert for the building industry. Per year he dealt
with approximately 100-130 opinions of varying nature and length.
93. As regards the relevant stages of the proceedings at
issue, the Stuttgart Court of Appeal stated, in its order to take
evidence of 28 July 1972, that the expert's opinion should be
delivered only after the visit to the warehouse. After both parties
had agreed on the costs of the opinion, the visit to the warehouse
took place on 11 January 1973. After this inspection the original
order to take evidence had to be supplemented on 26 February 1973 on
account of the applicant's new submissions. Therefore, the case files
could not be forwarded to the expert until 1 March 1973. The Court
again supplemented its order to take evidence on 22 June 1973 due to
further alleged defects. The Court again ordered a new visit to the
warehouse on 5 November 1973 and decided that the report would only
have to be delivered thereafter. This instruction and the documents
of the proceedings were transmitted to the expert on 4 December 1973.
94. After the expert had visited the warehouse on 28 January 1974,
both parties submitted further documents and private expert opinions
to be considered by Dr. A. On 13 November 1974 the Court again had to
supplement its order to take evidence requesting further views from
the expert on the newly reported defects, on the repair costs and on
the depreciation in value. These new documents were transmitted to
Dr. A. on 15 November 1974.
95. Upon inquiry by both parties and by the Court, the expert
stated on 2 October 1975 that the report would be ready in spring 1976
and that his work on the report had been delayed as a result of the
recession in the building trade. On 27 April 1976 the expert carried
out another visit to the warehouse together with both parties and
their private experts. He included in his opinion the subsequent
submissions and private expert opinions of the parties. Information
received from the expert after each inquiry by the Court as to the
state of the opinion was passed on to both parties without delay. They
did not object to the expert's announcements concerning the date for
submission of his opinion; nor did they object to references to delays
caused by the recession in the building trade, to his appointment
abroad, and to impairment of his health resulting from the excessive
summer heat.
96. As regards the responsibility of the German authorities,
it is pointed out that the documents of the proceedings together with
the instruction to deliver an opinion in accordance with the orders to
take evidence made on 28 July 1972, 26 February and 22 June 1973 were
not conveyed to the expert again until 4 December 1973. The order to
take evidence had to be supplemented yet again on 13 November 1974 on
account of new party submissions of fact. During this period the
expert did not even have the documents at his disposal. In view
thereof, no criticism can be made with regard to the period ending on
15 November 1974 when the case-file was again sent to the expert.
97. Delays in the expert's work did, however, occur during the
period from 15 November 1974 to 27 April 1976 (when he again visited
the warehouse) and also from June 1976 (receipt of the parties'
submissions on questions put by the expert) until delivery of the
report on 29 December 1976. During these periods the applicant drew
the Court's attention to the possibility of setting the expert a time-
limit, and the plaintiff actually applied for this.
98. However, as indicated above, the Court was not obliged to
proceed in this manner. Setting a time-limit for delivery of a report
is a matter within the Court's discretion. The Court exercised its
discretion correctly. The Court could not anticipate the applicant's
many subsequent submissions or that the expert Dr. A. would be
involved in very important parallel cases. The taking of evidence, as
described above, shows that the Court conveyed to the expert without
delay the various, partly urgent requests of the parties, adding its
own urgent requests. After the expert had requested forbearance for
the delays until spring 1976 and neither of the parties objected
thereto, the Court was able to refrain from setting a time-limit.
99. In the present case both parties requested on altogether seven
occasions that the expert be reminded to submit his opinion. On the
other hand, they themselves caused delays until November 1974, and
subsequently they did not object to the dates given by the expert and,
in particular, did not call for the appointment of a new expert.
While the German courts are also under a duty to expedite proceedings,
they are not responsible for the object and substantiation of the
action and for procuring evidence.
100. For this reason it is not to the point if it is maintained
that the Court of Appeal did not take any steps to expedite the
preparation of the opinion, or to appoint a new expert. At regular
intervals the Court asked the expert for information on the current
position. It also forwarded to him every reminder submitted by the
parties. In view of both parties' conduct, the Court was able to
dispense with further measures against the expert, such as setting a
time-limit and threatening with the imposition of a fine. The Court
was also not obliged to commission a new expert of its own accord.
101. In this respect the following arguments are expounded: First,
in view of the importance of his oath as expert, Dr. A. regularly
reserved his right himself to set priorities when dealing with his
various opinions. The judges at the Court of Appeal who knew this
position respected it and had confidence therein. It thus becomes
patent that Dr. A. could not have been given a time-limit for
preparing an opinion. Second, on account of the many private opinions
submitted by the applicant, it was necessary to call upon a
particularly prominent, sworn expert who could guarantee an objective
assessment of the alleged deficiencies. Indeed, the parties
themselves disclosed confidence in Dr. A. and paid a lump sum of
12,000 DM for the preparation of his opinion. Third, Dr. A. could
hardly have been fined, as it would have been necessary to prove that
he culpably violated his obligations. In any event, Dr. A. had never
been fined on these grounds in 30 years. Fourth, had another expert
been nominated, this would have further prolonged the proceedings as
he would have had to commence afresh. Such a course of proceeding
would have been particularly counter-productive as from September 1976
when Dr. A. announced that he was in the final stages of preparing his
opinion. Fifth, the applicant did not formulate his various requests
in respect of Dr. A. too firmly although the plaintiff formally
applied to the Court that Dr. A. should be given a time-limit.
Finally, envisaging the preparation of only a partial expert opinion
would not have been practicable and would have had little
justification insofar as discussion of the alleged deficiencies at
issue had already been postponed by the Regional Court in first
instance.
102. The applicant should have made it clear while evidence was
being taken that he had an interest in swifter delivery of the opinion
by objecting to the expert's explanations or by applying for a new
expert. The applicant never objected to the explanations given by the
expert for his delays. He should also have tried to accelerate the
proceedings by lodging a constitutional complaint.
103. There is a contradiction between the present complaint and
those made before the domestic courts. Thus, in both constitutional
complaints the applicant had argued that the time reqired by the
expert to prepare his report showed "how difficult the investigations
were and what extensive considerations had to be taken into account".
Only in his constitutional complaint of 29 January 1981 did he refer
to the length of the proceedings. However, he only referred to the
total length of the litigation, without specifying more closely delays
allegedly caused by the courts or by the expert.
104. The Government conclude that the actual course of proceedings
for the taking of evidence indicates that the time taken was not
caused by the Court of Appeal but predominantly fell within the
applicant's or the plaintiff's responsibility.
105. As regards the issue of damages, the Government emphasise
that the claim to compensation asserted by the applicant and his widow
also does not arise on the merits. These claims to compensation have
been adjudicated by the courts, and the final judgment has acquired
the force of res judicata. The courts recognised these claims to a
minimal extent and to that extent only dismissed the Waiss company's
action for remuneration for their work. The applicant has suffered no
disadvantage through the length of the proceedings (see Preikhzas v.
the Federal Republic of Germany, Comm. Report 13.12.78, D.R. 16 p. 5).
V. OPINION OF THE COMMISSION
A. Point at issue
106. The issue to be determined in the present case is whether the
court proceedings in which the applicant was involved were concluded
within a "reasonable time" as required by Article 6 para. 1 of the
Convention.
B. Applicability of Article 6 para. 1
107. Article 6 para. 1 insofar as it is relevant, reads as follows:
"In the determination of his civil rights and obligations...,
everyone is entitled to a ... hearing within a reasonable
time ..."
108. The Commission notes that the applicability of Article 6
para. 1 is not in dispute between the parties. Indeed, the
proceedings at issue resulted from claims and counter-claims in
respect of construction costs for a warehouse and thus clearly
concerned the determination of the applicant's civil rights and
obligations within the meaning of Article 6 para. 1 of the Convention.
Accordingly, the guarantees of this provision are applicable in the
present case.
C. Period to be taken into consideration
109. The starting point of the period to be considered is 17 May
1971, the date on which the Waiss company initiated proceedings before
the Stuttgart Regional Court.
110. As regards the end of the period, the time to be considered
under Article 6 para. 1 covers in principle the entirety of the
litigation, including the appeal proceedings. However, the question
arises whether it also includes the proceedings before the Federal
Constitutional Court. In this respect the European Court of Human
Rights has held in one case that proceedings before the Federal
Constitutional Court are to be taken into account when considering the
issue of the length of civil court proceedings under Article 6
para. 1, the reason being that, although the Federal Constitutional
Court has no jurisdiction to rule on the merits, its decision is
capable of affecting the outcome of the claim (see Eur. Court H.R.,
Deumeland judgment of 29 May 1986, Series A No. 100, p. 26 para. 77).
Consequently, the proceedings in the present case were
terminated on 10 March 1981 when the decision of the Federal
Constitutional Court of 5 March 1981 was served on the applicant's
representative.
111. Therefore, the period to be considered under Article 6 para. 1
is nine years, nine months and three weeks (17 May 1971 - 10 March 1981).
112. While it is the entire span of the proceedings which the
Commission has to examine, it observes that the main question of the
present case concerns the time taken, during the proceedings before
the Stuttgart Court of Appeal, for the preparation of the expert
opinion. There is no dispute between the parties as to the
reasonableness of the time required for the remainder of the
proceedings.
Thus, the Court of Appeal entrusted Dr. A., by order of 28
July 1972, with the task of providing it with an expert opinion. The
opinion which was finally submitted was dated 29 December 1976 and was
delivered personally by Dr. A. to the Court on 13 January 1977.
113. The time taken for the preparation of the expert opinion
was, therefore, four years, five months and sixteen days
(28 July 1972 - 13 January 1977).
D. Relevant criteria
114. The reasonableness of the length of proceedings has to be
assessed in each case according to the particular circumstances and
having regard, in particular, to the complexity of the case, the
conduct of the parties and the competent authorities and to what is
at stake for the former. The present case which concerns civil
proceedings must also take into account whether the applicant has
shown due diligence by taking the necessary steps to expedite the
proceedings and whether delays occurred for which the applicant cannot
be held responsible. Only delays attributable to the State may
justify a finding of a failure to comply with the "reasonable time"
requirement (see Eur. Court H.R., Deumeland judgment of 29 May 1986,
Series A No. 100 p. 26 para. 78; Poiss v. Austria, Erkner and Hofauer
v. Austria, Comm. Reports 24.1.86, paras. 94 and 95, respectively).
E. Complexity of the case
115. Neither the applicant nor subsequently his widow made
submissions before the Commission on the complexity of the case as
such. However, in respect of the applicant's other complaint under
Article 6 para. 1 concerning a fair hearing, which was declared
inadmissible by the Commission, he indicated the complexity of the
case by pointing out that the period of nine weeks at his disposal
after the expert had delivered the opinion was insufficient for him
adequately to prepare the hearing fixed for 22 March 1977.
The Government have drawn attention to the applicant's two
constitutional complaints. Therein, he argued that the time required
by Dr. A. to prepare his opinion showed how difficult the
investigations had been and what extensive considerations had to be
taken into account.
116. The Commission has first examined the object of the domestic
court proceedings. It notes that they resulted from an action brought
by the Waiss company which requested from the applicant the remaining
payment of 618 440 DM for the construction costs for a warehouse. The
applicant put forward counter-claims of more than one million DM. The
Commission also notes the extensive judgments given by the German
courts. Thus, the partial decision of the Stuttgart Regional Court of
10 September 1971 numbered 62 pages, the decision of the Court of
Appeal of 31 March 1977 110 pages.
117. The Commission recalls its case-law according to which large
claims and counter-claims put forward by the parties to the
proceedings do not in themselves justify longer proceedings (see
Andorfer Tonwerke v. Austria, Comm. Report 8.3.82, D.R. 32, p. 110
para. 81). Nevertheless, the Commission is satisfied that the present
case as a whole raised a number of difficult technical questions of
fact which account, to a certain extent, for the long duration of the
proceedings.
118. The questions to be answered in the expert opinion itself
concerned the alleged deficiencies in the warehouse caused by dampness
in the construction work. In this respect, however, a number of
reasons demonstrate that the questions were not of such complexity as
to justify the very long time it took to prepare the expert opinion.
First, Dr. A., the person appointed, was an expert of
considerable and specialised knowledge in the field. Second, in his
various statements to the Court of Appeal, Dr. A. explained the delays
mainly by referring to elements which had little to do with the
complexity of the matter, namely his other obligations, his journey
abroad, and on one occasion the summer heat. Third, the expert
opinion was a document of 37 pages and was not, therefore,
particularly lengthy. Fourth, the applicant's private expert,
Professor L., was able, despite an illness, to prepare his own opinion
of 14 pages, which strongly criticised Dr. A.'s opinion, within
approximately 4 months after the applicant had received a copy of
Dr. A.'s opinion on 19 January 1977.
119. It follows that the period of approximately 4 1/2 years which
elapsed before Dr. A. presented his opinion was not justified by the
complexity of the matter.
F. Conduct of the parties
120. The applicant and subsequently his widow have submitted that
the applicant cannot be made responsible for the delays in preparing
the expert opinion. In fact, the new deficiencies alleged by him
should not have delayed the expert's work but could have been dealt
with in a separate expert opinion. Moreover, when the expert failed
to produce his expert opinion, the parties could do no more than make
suggestions or remonstrances to the Stuttgart Court of Appeal. To
request more rigid measures would have meant alienating the expert.
The Government have submitted that the parties to the
proceedings, in particular the applicant, are responsible for the
delays until 15 November 1974 by frequently filing new submissions.
As to the period thereafter, the Government submit, with reference to
the principle of party disposition governing civil proceedings, that
the applicant did not object to the explanations given by the expert
as to the progress of his work. He did not formally request the
fixing of a time-limit or call for the appointment of a new expert.
He thus failed to show that he had an interest in a swifter delivery
of the opinion, and he did not sufficiently accelerate the
proceedings.
121. The Commission observes, on the one hand, that the parties and
in particular the applicant frequently filed submissions on the facts
or their private expert opinions. In a number of instances, the
applicant thereby alleged new deficiencies in the warehouse. As a
result, the Court of Appeal was obliged on four occasions (13 November
1972, 26 February and 22 June 1973, 13 November 1974) to supplement
its order of evidence of 28 July 1972 and subsequently again to
transmit the case-file to the expert.
On the other hand, the submissions in which the applicant
alleged new deficiencies were filed no later than 10 December 1974.
In 1975, he filed no submissions. In 1976 the parties filed further
submissions between 9 August and 15 December 1976.
122. Thus, it can be assumed that the parties and in particular the
applicant himself, through their conduct, caused some delays in the
proceedings during the period up to December 1974 and again in the
second half of 1976.
123. The applicant was standing to lose a substantial sum of money
in the proceedings before the Court of Appeal which centred on the
alleged deficiencies of the construction of the warehouse. He must
therefore have regarded it as essential to his case to be able to
invoke as many deficiencies as possible and to have them examined by
the expert. Accordingly, the Commission finds no reason to believe
that by filing new submissions on several occasions the applicant
failed to show due diligence during the proceedings.
124. In this context the Government have also submitted that the
applicant did not take adequate measures to expedite the proceedings
before the Court of Appeal and did not, therefore, disclose his
interest in their speedy conclusion.
These submissions have already been addressed by the
Commission at the admissibility stage. Insofar as they now concern
the merits of the application, the Commission has had regard to the
measures mentioned in S. 360 and 411 (2) of the Code of Civil
Procedure. As the Government themselves have pointed out, the
possibility under these provisions of fixing a time-limit for the
expert, or of terminating his appointment, lay solely within the
Court's discretion. Indeed, when on 3 February 1976 the plaintiff
formally requested the Court of Appeal to determine a time-limit, the
latter replied that the conditions were not yet at hand.
Nevertheless, on at least four occasions (8 August and 2 October 1974,
26 May 1975 and 4 October 1976) the applicant reminded the Court of,
or inquired about, the preparation of the opinion, or suggested
setting a time-limit.
The Commission has considered the argument of the Government
according to which the applicant could have formally applied for the
appointment of a new expert under the second sentence of S. 360 of the
Code of Civil Procedure. However the Commission is of the opinion that
the applicant could not be required to take a step which would have
been likely to create a conflict with Dr. A., who was the generally
recognised expert in the field, and which might therefore have been
prejudicial to the applicant's own interests. A party to civil
litigation cannot be expected to act against its interests concerning
the outcome of the litigation.
The Commission is therefore satisfied that, from 8 August 1974
onwards, the applicant sufficiently disclosed to the Court of Appeal
his interest in a speedy conclusion of the proceedings.
125. Consequently, although the applicant's conduct up to December
1974 and again in the second half of 1976 caused certain delays in the
proceedings, it can in no way account for the period of nearly 4 1/2
years which it took to prepare the expert opinion.
G. Conduct of the authorities
126. The Commission considers, and it has not been disputed by the
parties, that in the proceedings before the Stuttgart Regional Court,
the Federal Court of Justice, and the Federal Constitutional Court,
the authorities dealt with the case efficiently and speedily.
127. As regards the proceedings before the Court of Appeal, the
applicant and subsequently his widow have submitted that the expert
Dr. A. caused the delays by not preparing his opinion. The Court did
not react adequately to his explanations as to the progress of his
work and to the parties' admonitions. In particular, it made no use
of the possibility of fixing a time-limit, or of appointing a new
expert.
The Government have submitted that, while some delays in the
expert's work occurred during the period from 15 November 1974 until
27 April 1976, and also from 28 June until 29 December 1976, the Court
at regular intervals asked the expert for information on the current
position. More was not required since the parties had not objected to
the explanations given by Dr. A. The Court had respected Dr. A.'s
right himself to set his priorities; a fine would have presupposed
proof of a culpable violation of his obligations. Nomination of
another expert would have further prolonged the proceedings, and
preparation of a partial opinion would not have been practicable.
128. The first issue to be clarified by the Commission is the
position of the expert in civil proceedings. The Commission notes
that the Court of Appeal ordered the expert opinion on 28 July 1972,
but that the opinion was not submitted until 13 January 1977.
However, the expert's conduct cannot as such fall to be examined under
Article 6 para. 1 of the Convention since he was not acting in the
name of the public authorities. Nevertheless, the expert remains
subject to the control of the judicial authorities which have a duty
to ensure that the task is discharged properly (see Capuano v. Italy,
Comm. Report 15.10.85, para. 69).
129. It is true that in the Federal Republic of Germany civil
proceedings are governed by the principle of party disposition, which
means that the main responsibility for the conduct of a case rests
with the parties. Nevertheless, this principle cannot relieve the
courts of the duty to ensure that the case is heard within a
reasonable time. The respondent Government themselves have
pointed out that the German courts are under a duty to expedite
proceedings. This demonstrates that in German law, as indeed under
the Convention, the principle of party disposition must be reconciled
with the right to a proper administration of justice, which will be
impaired by the existence of excessively long proceedings (see
Capuano, ibid. para. 70).
The principle of party disposition is subject to certain
limitations, when the court itself has appointed an expert. Where the
court deems it necessary to have expert advice it must be its
responsibility to supervise the expert as far as compliance with the
time-limits is concerned. The court must, if necessary, appoint a new
expert. The Commission is of the opinion that, although S. 360 of the
German Code of Civil Procedure gives a party the possibility formally
to apply for the appointment of a new expert, the court cannot, for
the reasons explained in paragraph 124, expect the parties to take
steps which may be disadvantageous for them.
130. The Commission thus turns to the means at the disposal of the
Court of Appeal to ensure the proper discharge of the expert's task.
It considers, inter alia, that the Court could at an early stage have
requested the expert to respect the time-limits. It could also have
requested the expert to set, or to explain, the priorities among his
different obligations. According to S. 411 of the Code of Civil
Procedure, the Court could thereafter have fixed a time-limit for the
expert, or even threatened him with a fine. Further possibilities for
the Court would have been the appointment of a new expert, or a
request for a partial opinion followed by the rendering of a partial
judgment.
131. In this context the Commission sees a number of reasons which
should have prompted the Court of Appeal, by resorting to these or
other means, actively to pursue and to expedite the proceedings, in
particular at the stage when one or both of the parties had shown
impatience with the slow progress in the expert's work.
132. The Commission has already pointed out that, particularly from
August 1974 onwards, the applicant clearly disclosed his interest in
the speedy conclusion of the proceedings. A similar indication had
been given already in May 1974 by the other party. Moreover, the
proceedings were already at an advanced stage in that the case was
being dealt with in second instance and the Court ought to have been
aware of a possible further lapse of time in subsequent proceedings
before higher judicial bodies. Indeed, in the present case nearly
four years were still to pass, after the Court of Appeal handed down
its judgment on 31 March 1977, until the Federal Constitutional Court
finally rejected the applicant's constitutional complaint on 5 March
1981.
133. In particular, however, the reasons given by the expert for
the delay were not satisfactory. The extraordinarily long time
required to prepare the opinion - almost 4 1/2 years - could only have
been justified in very exceptional circumstances. In fact, however,
the expert explained the delays with his commitments in other proceedings,
teaching obligations, travels abroad, and the summer heat. These
explanations were clearly insufficient. Insofar as the expert invoked
as an excuse the fact that the applicant had frequently invoked new
deficiencies in the warehouse, the Commission has already found (para.
125) that some delays were caused thereby, but this can only account
for a part of the long time the expert took to prepare his opinion.
134. The Commission has thus listed some means which the Court of
Appeal had at its disposal to control the expert's discharge of his
task as well as a number of reasons which should have prompted the
Court actively to pursue and speedily to conclude the proceedings. It
must now turn its attention to the manner in which the Court of Appeal
in fact conducted the proceedings in question at their various stages.
135. The Commission notes that, as a rule, the Court of Appeal
reacted promptly to the parties' submissions insofar as it transmitted
them to the expert. The Court also transmitted the expert's
explanations for the delays to the parties. During the initial period
from July 1972 to the end of 1973 the Court took a number of other
measures. After instructing the expert on 28 July 1972 it took
further decisions on the taking of evidence on 13 November 1972 and on
26 February and 22 June 1973. The Court also visited the warehouse on
11 January and 5 November 1973. Moreover, during this initial period
there were frequent new submissions or allegations by the applicant
which affected the work to be done by the expert, and it is
understandable that at that stage the Court did not take further
measures to expedite the preparation of the expert opinion.
136. In the period 1974-1976 the situation gradually changed. It
is true that during parts of this period new submissions and
allegations were again made by the applicant and counter-submissions
by the plaintiff, but this was not the case, for instance, in 1975
and the first half of 1976. Moreover, the parties had now indicated
to the Court that they were anxious to expedite the proceedings. The
plaintiff made a statement to this effect on 3 May 1974 and the
applicant made several requests to the Court - from 8 August 1974
onwards - in order to accelerate the preparation of the expert
opinion.
137. Consequently, and in view also of the fact that a considerable
time had elapsed since the expert was instructed by the Court's
decision of 28 July 1972, there were good reasons for the Court at
this stage to take effective steps to expedite the proceedings. The
reasons for the delay indicated by the expert could not be accepted,
and in these circumstances the means employed by the Court - reminding
the expert of his work, requesting him to prepare his opinion,
exchanging communications, etc. - were inadequate to advance the
proceedings and to bring them to a speedy conclusion.
138. The Commission therefore considers that the conduct of the
Court of Appeal in the years 1974-1976 was not conducive to a speedy
conclusion of the proceedings in the applicant's case.
H. Overall assessment
139. The Commission will finally consider whether, in view of the
various elements indicated above, there has been a violation of the
applicant's right under Article 6 para. 1 of the Convention to a
hearing within a reasonable time.
140. In all, the proceedings lasted for nearly ten years. However,
there is no appearance of any unreasonable delay except in the
proceedings before the Court of Appeal. During these proceedings it
took almost 4 1/2 years to prepare an expert opinion on the alleged
deficiencies in a warehouse. The complexity of the subject-matter was
not such as to justify such a long delay. Although the applicant's
own conduct in the proceedings made the work of the expert more
difficult, it can in no way explain a delay of this kind. On the
other hand, it is clear that the Court of Appeal did not take
sufficiently strong and effective measures to expedite the
proceedings, and the Court must therefore be held to have contributed
to the delay.
141. Consequently, the Commission finds that the applicant did not
get a hearing within a reasonable time in the meaning of Article 6
para. 1 of the Convention.
I. Conclusion
142. The Commission concludes by a unanimous vote that there has
been a violation of Article 6 para. 1 of the Convention in that the
applicant's case was not heard within a reasonable time.
Secretary to the Commission President of the Commission
H.C. KRÜGER C.A. NØRGAARD
&-APPENDIX I&S
HISTORY OF PROCEEDINGS
Date Item
----------------------------------------------------------------------
2 September 1981 Introduction of the application
4 July 1983 Registration of the application
Examination of admissibility
7 December 1983 Commission's deliberations and decision to
invite the Government to submit observations
on the admissibility and merits of the
application
16 February 1984 Government's request that the Commission
strike the application off its list of cases
in view of the applicant's decease
18 April 1984 Statement of the applicant's representative
that the applicant's widow wished to continue
the application
11 July 1984 Commission's decision to maintain its decision
of 7 December 1983
14 December 1984 Government's observations
20 April 1985 Applicant's observations in reply
8 July 1985 Commission's decision to invite the parties to
a hearing on the admissibility and merits of
the application
6 May 1986 Hearing and Commission's decision on
admissibility. At the hearing the parties were
represented as follows:
Government
Mr. H.A. Stöcker
Mrs. R. Adlerstein
Mr. H. Krukenberg
Applicant
Mr. H.-J. Pohl
Mr. R. Schuhmann
The applicant's widow was also present
Examination of the merits
8 December 1986 Commission's consideration of the state
of proceedings
3 March 1987 Commission's deliberations on the merits and
final vote
12 March 1987 Adoption of the Report
LEXI - AI Legal Assistant
