Lexploria - Legal research enhanced by smart algorithms
Lexploria beta Legal research enhanced by smart algorithms
Menu
Browsing history:

L. v. Finland

Doc ref: 18595/91 • ECHR ID: 001-45716

Document date: April 5, 1995

  • Inbound citations: 0
  • Cited paragraphs: 0
  • Outbound citations: 20

L. v. Finland

Doc ref: 18595/91 • ECHR ID: 001-45716

Document date: April 5, 1995

Cited paragraphs only



                  EUROPEAN COMMISSION OF HUMAN RIGHTS

                             FIRST CHAMBER

                       Application No. 18595/91

                                   L.

                                against

                                Finland

                       REPORT OF THE COMMISSION

                       (adopted on 5 April 1995)

                           TABLE OF CONTENTS

                                                                 Page

I.    INTRODUCTION

      (paras. 1-20) . . . . . . . . . . . . . . . . . . . . . . . . 1

      A.   The application

           (paras. 2-4) . . . . . . . . . . . . . . . . . . . . . . 1

      B.   The proceedings

           (paras. 5-15). . . . . . . . . . . . . . . . . . . . . . 1

      C.   The present Report

           (paras. 16-20) . . . . . . . . . . . . . . . . . . . . . 2

II.   ESTABLISHMENT OF THE FACTS

      (paras. 21-91). . . . . . . . . . . . . . . . . . . . . . . . 4

      A.   The particular circumstances of the case

           (paras. 21-53) . . . . . . . . . . . . . . . . . . . . . 4

      B.   Relevant domestic law and practice

           (paras. 54-91) . . . . . . . . . . . . . . . . . . . . . 8

           1.    General provisions on the construction

                 and the maintenance of a private road

                 (paras. 54-64) . . . . . . . . . . . . . . . . . . 8

           2.    The proceedings before the Forestry Board

                 (paras. 65-66) . . . . . . . . . . . . . . . . . . 9

           3.    The proceedings before the Expert and Trustees

                 (paras. 67-79) . . . . . . . . . . . . . . . . . . 9

           4.    The proceedings before the Land Court

                 (paras. 80-89) . . . . . . . . . . . . . . . . . .13

           5.    Supreme Court practice

                 (paras. 90-91) . . . . . . . . . . . . . . . . . .14

III.  OPINION OF THE COMMISSION

      (paras. 92-160) . . . . . . . . . . . . . . . . . . . . . . .16

      A.   Complaints declared admissible

           (para. 92) . . . . . . . . . . . . . . . . . . . . . . .16

      B.   Points at issue

           (para. 93) . . . . . . . . . . . . . . . . . . . . . . .16

      C.   As regards Article 6 para. 1 of the Convention

           (paras. 94-115). . . . . . . . . . . . . . . . . . . . .16

           CONCLUSION

           (para. 115). . . . . . . . . . . . . . . . . . . . . . .20

                           TABLE OF CONTENTS

                                                                 Page

      D.   As regards Article 1 of Protocol No. 1

           to the Convention

           (paras. 116-153) . . . . . . . . . . . . . . . . . . . .20

           1.    The deprivation of the applicant's property

                 (paras. 126-137) . . . . . . . . . . . . . . . . .22

                 CONCLUSION

                 (para. 137). . . . . . . . . . . . . . . . . . . .24

           2.    The applicant's obligation to participate

                 in the road costs

                 (paras. 138-153) . . . . . . . . . . . . . . . . .24

                 CONCLUSION

                 (para. 153). . . . . . . . . . . . . . . . . . . .27

      E.   As regards Article 13 of the Convention

           (paras. 154-156) . . . . . . . . . . . . . . . . . . . .27

           CONCLUSION

           (para. 156). . . . . . . . . . . . . . . . . . . . . . .27

      F.   Recapitulation

           (paras. 157-160) . . . . . . . . . . . . . . . . . . . .27

PARTIALLY DISSENTING OPINION OF MRS. J. LIDDY . . . . . . . . . . .28

APPENDIX:  DECISION OF THE COMMISSION AS TO THE ADMISSIBILITY

OF THE APPLICATION. . . . . . . . . . . . . . . . . . . . . . . . .31

I.    INTRODUCTION

1.    The following is an outline of the case as submitted to the

European Commission of Human Rights, and of the procedure before the

Commission.

A.    The application

2.    The applicant is a Swedish citizen, born in 1942 and resident at

Västerås, Sweden. He was represented before the Commission by

Mr. Peter Westdahl, a lawyer practising in Gothenburg, Sweden.

3.    The application is directed against Finland. The respondent

Government were represented by their agent, Ambassador Tom Grönberg,

then Director-General for Legal Affairs, Ministry for Foreign Affairs,

and by their co-agent, Mr. Arto Kosonen, legal adviser of the said

Ministry.

4.    The case concerns administrative and court proceedings with a

view to establishing a private road crossing over the applicant's

property. It raises issues mainly in regard to the composition of a

tribunal and the justification of the interference with the applicant's

property rights. The applicant invokes Article 6 para. 1, Article 13

of the Convention as well as Article 1 of Protocol No. 1 to the

Convention.

B.    The proceedings

5.    The application was introduced on 22 April 1991 and registered

on 15 July 1991.

6.    On 1 July 1992 the Commission (First Chamber) decided, pursuant

to Rule 48 para. 2 (b) of its Rules of Procedure, to give notice of the

application to the respondent Government and to invite the parties to

submit written observations on the admissibility and merits thereof

with the exception of the complaint under Article 1 of Protocol No. 1.

7.    The Government's observations were submitted on 22 October 1992

and the applicant's observations in reply on 4 January 1993.

8.    On 11 January 1994 the Commission decided to invite the parties

to a hearing on the admissibility and merits of the applicant's

complaints under Article 6 para. 1 of the Convention. It further

decided to invite the respondent Government to submit written

observations on the admissibility and merits of the complaints under

Article 1 of Protocol No. 1.

9.    The Government's observations on the complaints under Article 1

of Protocol No. 1 were submitted on 22 February 1994 and the

applicant's observations on 6 and 16 March 1994.

10.   On 8 March 1994 the Commission granted the applicant legal aid

for the representation of his case as from and including counsel's

preparations for the hearing.

11.   On 13 April 1994 the Commission decided to extend the scope of

its hearing to include the question of the admissibility and merits of

the applicant's complaints under Article 1 of Protocol No. 1.

12.   At the hearing which was held on 12 May 1994 the Government were

represented by their agent, Mr. Grönberg, their co-agent, Mr. Kosonen,

as well as their expert, Mrs. Leea Vikman, land surveyor of the

District Surveying Office of Southern Savo. The applicant himself was

present, assisted by his counsel, Mr. Westdahl.

13.   On 12 May 1994 the Commission declared admissible the applicant's

complaint concerning the composition of a court dealing with his case,

his access to that court as well as the fairness of the proceedings as

a whole. The Commission further declared admissible one of his

complaints relating to the interference with his property rights caused

by the construction of the road and to the lack of an effective remedy

in this respect. The Commission declared inadmissible the remainder of

the application.

14.   The text of the Commission's decision on admissibility was sent

to the parties on 25 May 1994 and they were invited to submit further

observation on the merits. Such observations were submitted by the

Government on 2 July and 26 August 1994 and by the applicant on

1 July and 8 September 1994.

15.   After declaring the case admissible, the Commission, acting in

accordance with Article 28 para. 1 (b) of the Convention, also placed

itself at the disposal of the parties with a view to securing a

friendly settlement. In the light of the parties' reaction, the

Commission now finds that there is no basis on which such a settlement

can be effected.

C.    The present Report

16.   The present Report has been drawn up by the Commission (First

Chamber) in pursuance of Article 31 of the Convention and after

deliberations and votes, the following members being present:

           Mr.   C.L. ROZAKIS, President

           Mrs.  J. LIDDY

           MM.   A.S. GÖZÜBÜYÜK

                 A. WEITZEL

                 M.P. PELLONPÄÄ

                 B. CONFORTI

                 N. BRATZA

                 I. BÉKÉS

                 E. KONSTANTINOV

17.   The text of this Report was adopted on 5 April 1995 by the

Commission and is now transmitted to the Committee of Ministers of the

Council of Europe, in accordance with Article 31 para. 2 of the

Convention.

18.   The purpose of the Report, pursuant to Article 31 of the

Convention, is:

      (i)  to establish the facts, and

      (ii) to state an opinion as to whether the facts found disclose

           a breach by the State concerned of its obligations under

           the Convention.

19.   The Commission's decision on the admissibility of the application

is appended to the Report.

20.   The full text of the parties' submissions, together with the

documents lodged as exhibits, are held in the archives of the

Commission.

II.   ESTABLISHMENT OF THE FACTS

A.    The particular circumstances of the case

21.   The applicant is the owner of the real property Bjurträsk 1:214

at Iskmo in the municipality of Korsholm (Mustasaari) in Finland.

22.   In 1979 certain property owners requested the Forestry Board

(metsälautakunta, skogsnämnden) of Ostrobotnia to draw up a plan for

the construction of a private forestry road in the area of Iskmo.

23.   At a meeting organised by the Forestry Board on 3 June 1988 and

attended by certain property owners and others a road construction plan

drawn up by the Board was adopted. According to the plan, the road was

to cross over the applicant's property.

24.   On the same day the Executor of the road construction project

(toimitusmies, syssloman), who had been elected at the meeting,

requested the District Surveying Office (maanmittauskonttori,

lantmäteribyrån) of Vaasa to institute proceedings (tietoimitus,

vägförrättning) with a view to approving and implementing the Forestry

Board's plan in accordance with the 1962 Act on Private Roads (laki

358/62 yksityisistä teistä, lag 358/62 om enskilda vägar, hereinafter

"the 1962 Act").

25.   A further meeting with certain property owners was organised by

the Forestry Board presumably in the summer of 1988. At this meeting

the planned road was apparently extended.

26.   The applicant was not summoned to the above meetings and did not

attend any of them. According to him, only some 10 to 15 persons were

heard by the Forestry Board, whereas the total of number of property

owners to be affected by the road amounted to approximately 120.

27.   After its plan had been adopted the Forestry Board, in the summer

of 1988, had certain logging carried out on the applicant's property

in order to stake out the intended location of the road.

28.   According to the applicant, he received information about the

location of the proposed road on his property before the logging took

place but subsequent to the meeting on 3 June 1988. In a letter of

18 November 1991 to the Forestry Board the applicant referred to his

and his wife's conversation with a representative of the Board soon

after the meeting on 3 June 1988. The representative had given them a

copy of the map indicating the planned location of the road, but had

allegedly stated that they "had no say" in the matter.

29.   Having been informed about the logging, the applicant also

reported it to the National Forestry Board (metsähallitus, forst-

styrelsen), alleging that it had been carried out illegally. In a

letter of 29 November 1988 to the applicant the National Forestry Board

found no reason to take measures, having heard the Forestry Board. The

National Forestry Board recommended the applicant to present his claims

in the forthcoming administrative proceedings.

30.   On 18 October 1988 the Head of the District Surveying Office

appointed M.P. Expert (toimitusinsinööri, förrättningsingenjör) to

conduct the proceedings under the 1962 Act.

31.   On 15 November 1989 the Environmental Office (ympäristötoimisto,

miljövårdsbyrån) of the County Administrative Board (lääninhallitus,

länsstyrelsen) of Vaasa favoured the Forestry Board's plan.

32.   On 16 May 1990 T.K., Head of the District Surveying Office, took

over the Expert's duties.

33.   According to a list drawn up by the Forestry Board on

19 June 1990, the total area of the properties to be affected by the

road amounted to 1.312,50 hectares. The size of the applicant's

property was 8 hectares, corresponding to 0,61 per cent of the total

area. The total cost of the road construction was estimated at

1.695.000 FIM. The applicant's share was proposed to amount to

19.154 FIM, corresponding to 1,13 per cent of the total cost. The

applicant's address was indicated in the list.

34.   On 27 June 1990 a hearing was held before the Expert, assisted

by two Trustees (uskottu mies, gode man). The applicant had not been

summoned to the hearing, but attended it nevertheless, having received

information about it from relatives. At the hearing it was decided to

approve the plan drawn up by the Forestry Board. This entailed, inter

alia, the approval of the proposed location of the road except for

certain points not relevant for the present case, the approval of the

cost estimation, the establishing of road rights pertaining to the

encumbered properties, the approval of the so-called road units

(tieosuus, vägenhet) indicating the relative distribution of the road

costs between its owners and the founding of an association of road

owners (tiekunta, väglag). It was further decided that no property

owner should receive compensation, as the benefit of the road was

considered to compensate the interference.

35.   According to the applicant, the property owners attending the

hearing were not provided with detailed plans of the location of the

road and the related easements. The property owners were simply

informed that the Forestry Board's plan "had to be approved". No

information was allegedly given in regard to their respective shares

of the road costs. The parties could only submit their remarks

concerning their respective properties in private to the Expert and

Trustees.

36.   According to the applicant, he unsuccessfully objected to the

proposed location of the road. His wife, moreover, requested

compensation on his behalf for the interference to be caused thereby.

This request was immediately rejected. The applicant allegedly attended

the whole hearing, but not the subsequent meeting of property owners

at which the association of road owners was founded. He further claims

that no notice of appeal was either read out or served on him.

37.   According to the Government, the applicant was present when the

notice of appeal was read out and handed over to one of the Executors.

He did not request to receive an individual notice of appeal.

38.   According to the minutes from the hearing, a notice of appeal was

given to one of the Executors at the end of the hearing. In addition,

the minutes and the notice were read out and a copy of the notice was

enclosed to the file. No remarks were made against the minutes.

39.   From the minutes it also appears that a proposal by the Forestry

Board for the relative distribution of road costs was read out at the

hearing. The proposal was based on a number of factors such as the

annual average production of timber in respect of each property and the

calculated advantage of a shorter distance for transporting the timber

from a property to a public road. Certain property owners, excluding

the applicant, objected to the proposal.

40.   The applicant subsequently lodged an appeal with the Land Court

(maaoikeus, jorddomstolen) of Vaasa claiming, inter alia, that the

road, if it were to be constructed in accordance with the plan approved

by the Expert and Trustees, would considerably decrease the value of

his property. He also joined another appeal lodged on 23 July 1990. In

that appeal it was requested that only part of the adopted plan be

confirmed by the Land Court and that its remaining part be replaced by

already existing roads. This alternative solution would allegedly have

lowered the cost of the road from approximately 1,7 million FIM to

0,8 million FIM and required significantly less interference with the

natural habitat.

41.   By a letter of 10 September 1990 the Land Court summoned the

applicant to a hearing on 16 October 1990. Notification of the hearing

was, moreover, given by an announcement placed on the notice board of

the Municipal Hall of Korsholm (Mustasaari) on 18 September 1990. It

was also announced in Swedish in the local newspaper "Vasabladet" on

29 September 1990.

42.   In so far as the applicant had lodged a separate appeal he was

represented at the hearing by one of the signatories of the appeal of

23 July 1990. In so far as he had also signed that appeal he was

represented by another of its signatories. These were both heard by the

Land Court which decided to hold a further hearing on 24 October 1990

in connection with which it would carry out an inspection of the area

(katselmus, syn).

43.   At it second hearing the Land Court again heard the applicant's

respective representatives. It also heard other appellants as well as

fourteen property owners none of whom were appellants but who had

intervened in the proceedings in accordance with section 322,

subsection 1 of the 1951 Partition Act (jakolaki 604/51, lag 604/51 om

skifte, hereinafter "the 1951 Act"). It further heard the now three

Executors as well as the Expert and two representatives of the Forestry

Board.

44.   In its judgment the Land Court without examining the merits

thereof dismissed the applicant's separate appeal in so far as it

concerned the refusal of his alleged compensation claim. The applicant

was considered estopped from making such a claim to the Land Court,

since he had not made such a claim before the Expert and Trustees. The

Land Court rejected the remainder of his separate appeal, considering

it established that he had been present at the hearing on 27 June 1990,

when a notice of appeal had been read out and given to the property

owners.

45.   The Land Court furthermore rejected the appeal of 23 July 1990

as lodged by, among others, the applicant. It found that the proposed

road would not create any significant inconvenience for the property

owners and that there were no weighty reasons for changing the proposed

location. Regard was had to the opinion by the Environmental Office of

the County Administrative Board. The Land Court further noted that none

of the appellants had questioned the need for a road to the area.

46.   The Land Court was presided by a judge and further consisted of

four members, namely the Head of the County Surveying Office (läänin-

maanmittausinsinööri, länslantmäteriingenjören), a Land Court Surveyor

(maaoikeusinsinööri, jordrättsingenjör) and two lay judges.

47.   On 25 March 1991 the Supreme Court (korkein oikeus, högsta

domstolen) refused the applicant leave to appeal.

48.   On 26 September 1991 the Supreme Court rejected the applicant's

request for an annulment of the Land Court's judgment.

49.   In letters of 18 and 26 November 1991 addressed to the Forestry

Board the applicant requested, among other things, pursuant to section

28, subsection 2 of the 1962 Act, to be excluded from the association

of road owners and exempted from his obligation to participate in the

road maintenance costs.

50.   In letters of 25 November 1991 and 7 January 1992 the Forestry

Board informed the applicant that a road agreement (tiesopimus,

vägavtal) had been signed by all affected by it except for the

applicant and one further property owner (the applicant in Application

No. 18507/91). The Board recalled that the proceedings before the

Expert and Trustees had determined the location and width of the road

as well as the relative financial responsibility of each party. As all

relevant decisions had acquired legal force, the plan including its

financial implications could no longer be amended. Accordingly, the

Board had no competence to amend the applicant's share of the road

costs.

51.   On 12 January 1992 the applicant authorised one of the Executors

to sign the road agreement on his behalf, although reserving his

position as stated in his application to the Commission. The acceptance

of the agreement qualified the applicant for a State subsidy and low-

interest loan related to his share of the road costs.

52.   The road construction works commenced in the summer of 1991.

53.   On 1 October 1991 the Forestry Board adopted a forestry

improvement plan pertaining to the road. On 21 January 1992 it decided

to grant the applicant a State forestry improvement subsidy (metsän-

parannusvarat, skogsförbättringsunderstöd) in the amount of 3.830 FIM

and a low-interest forestry improvement loan by the State (metsän-

parannuslaina, skogsförbättringslån) in the amount of 15.324 FIM. It

further disregarded the applicant's reservations to his authority of

12 January 1992.

B.    Relevant domestic law and practice

      1.   General provisions on the construction and the

           maintenance of a private road

54.   A road shall be constructed so as to achieve the purpose of the

road in an optimal manner while at the same time not causing more than

necessary damage or harm to anyone. A road shall not be constructed,

if it cannot be regarded as necessary, having regard to the use of

existing private and public roads and other important general

considerations. The above considerations shall also apply to other

measures taken in connection with a road construction (section 7,

subsections 1 to 3 of the 1962 Act, as amended by Act no. 521/75).

55.   If the proper use of a property requires that a road be

established over a property owned by someone else and provided this

does not cause significant harm to the last-mentioned property, an area

of that property shall be given up for road purposes. The area is to

be determined in proceedings before an Expert and Trustees. Such a

permanent right of usufruct relating to an area forming part of another

property is called a right of way (section 8, subsection 1).

56.   If the proper use of a property requires it to be served by an

already existing road in respect of which a right of way has not yet

been granted to the property, such a right shall be granted provided

this does not cause significant harm to the property on which the road

is located or to other holders of a right of way. Such a right of way

shall be granted in proceedings before an Expert and Trustees or by

decision of the municipal Road Board (tielautakunta, vägnämnd) or the

association of joint road owners (section 9).

57.   Anyone who has been given permission to use a road or whose

property is located either partly or completely within the area which

the road must be considered to serve shall participate in the

construction and maintenance costs for the road (section 22,

subsection 1).

58.   If a significant number of those who would be obliged to

participate in the costs for the maintenance of the road oppose its

construction and provided the road would clearly serve only a minor

purpose for several properties, it may be decided to construct the road

only at the expense of those who wish to have it constructed

(section 22, subsection 2).

59.   If the road to be constructed would only serve a property to a

limited extent, due to, for instance, another already existing road

serving the property, the owner shall be exempted from participating

in the costs for the new road provided he states that he will abstain

from using it (section 22, subsection 3).

60.   The financial responsibility for the road shall be distributed

between the participants in the road construction according to their

individual benefit from the road. In this assessment regard should be

had to, among other things, the size of the properties and to what

extent the road will be used by each participant (section 23,

subsection 1).

61.   The proposed location of the road shall, as far as necessary,

also be marked in the terrain pursuant to the 1962 Decree on Private

Roads (asetus 690/62 yksityisistä teistä, förordning 690/62 om enskilda

vägar) (section 48, subsection 2 of the 1962 Act, as amended by Act

no. 521/75).

62.   A road owner may request to be excluded from the association of

road owners and exempted from his obligation to participate in the road

maintenance costs if the road is no longer needed by the property at

issue (section 28, subsection 2 of the 1962 Act).

63.   If the circumstances affecting his obligation to participate in

the maintenance of the road or his share of the maintenance costs have

considerably changed, the relative distribution of those costs between

the road owners shall be revised on request. Regardless of such

circumstances he may request a revision of the cost responsibility if

it has remained unchanged during at least five years (section 29).

64.   The above requests shall be examined at the general meeting of

the association of road owners (section 64, subsection 2, para. 2). The

decision of the meeting can be appealed to the Road Board (section 70,

subsection 1). The decision of the Road Board may be appealed to the

Land Court (section 55, as amended by Act no. 521/75). Leave to appeal

to the Supreme Court may subsequently be requested (section 333,

subsection 2 of the 1951 Act, as amended by Act no. 509/84).

      2.   The proceedings before the Forestry Board

65.   The Forestry Board is a public body governed by the 1987 Act on

the Central Forestry Boards and Forestry Boards (laki 139/87 keskus-

metsälautakunnista ja metsälautakunnista, lag 139/87 om centralskogs-

nämnder och skogsnämnder) and, as from 1 March 1991, by the 1991 Act

on Forestry Centres and Forestry Boards (laki 265/91 metsäkeskuksista

ja metsälautakunnista, lag 265/91 om skogscentraler och skogsnämnder).

66.   Under both Acts the members of the Forestry Boards shall be

appointed by the Ministry of Agriculture and Forestry. The meetings

held at the initial stage of the proceedings with a view to outlining

a road construction plan are governed by the 1987 Forest Improvement

Act (metsänparannuslaki 140/87, skogsförbättringslag 140/87).

      3.   The proceedings before the Expert and Trustees

67.   Proceedings for the execution of a road construction plan may be

instituted by the property owner or municipality concerned or by the

relevant association of road owners (section 39, subsection 1 of the

1962 Act, as amended by Act no. 498/82, and subsection 4, as amended

by Act no. 521/75). Others who have been allowed to use a road for

economic purposes as well as possessors of rights of usufruct may

express their opinions during the proceedings (section 39,

subsection 2).

68.   The proceedings are conducted by an Expert assisted by two

Trustees (section 43, subsection 1 of the 1951 Act, as amended by Act

no. 321/72). The Expert is normally an official of the District

Surveying Office, either the Head of the Office or another land

surveyor appointed by him.

69.   The Trustees are appointed by the Expert from a list of at least

six persons adopted by the relevant Municipal Council (kunnanvaltuusto,

kommunfullmäktige) for a period of four years (section 43, subsection

1 of the 1951 Act, as amended by Act no. 321/72, and section 44, as

partly amended by Act no. 321/72). Instead of appointing the Trustees

the Expert may choose to be assisted by two members of the Road Board

(section 40, subsection 1 of the 1962 Act, as amended by 322/72). The

Trustees shall be acquainted with property matters and fulfil the

conditions of lay judges sitting on District Courts (kihlakunnanoikeus,

häradsrätt; section 45, subsection 1 of the 1951 Act, as in force at

the relevant time). There is no requirement that the Expert or any of

the Trustees should be a lawyer.

70.   The request for proceedings to be instituted before the Expert

and Trustees shall, as far as possible, contain a list of all those

affected by the proceedings as well as a sufficiently detailed map

showing the location of the road. The request shall further contain the

addresses of those applying for proceedings to be instituted and, as

far as possible, the addresses of all those affected by the proceedings

(section 41, subsection 2 of the 1962 Act, as amended by Act

no. 521/75).

71.   If the Expert is of one opinion and the Trustees jointly of

another, the Trustees' opinion shall prevail. If all three disagree,

the Expert's opinion shall prevail (section 49 of the 1951 Act).

72.   If the proceedings concern a forestry road, the Expert shall

inform the Central Forestry Board which shall, if necessary, appoint

an expert to represent the Board in the proceedings (section 42,

subsection 1 of the 1962 Act, as amended by Act no. 521/75).

73.   Section 43, subsections 1, 2, 6 and 7 of the 1962 Act, as amended

by Act no. 521/75, read, as far as relevant, as follows:

      (Finnish)

      "Toimitusinsinöörin on kutsuttava asianosaiset

      tietoimitukseen tiedottamalla kokouksen ajasta ja paikasta

      kuulutuksella kunnan ilmoitustaululla vähintään neljätoista

      päivää ennen kokousta.

      Tietoimituksesta on lisäksi kuulutettava yhdessä tai

      kahdessa paikkakunnalla leviävässä sanomalehdessä vähintään

      neljätoista päivää ennen kokousta sekä ilmoitettava

      kutsukirjeellä ... sellaiselle toisesta kunnasta olevalle

      asianosaiselle, jonka osoite on asiakirjoissa mainittu tai

      muutoin toimitusinsinöörin tiedossa. ...

      ...

      Tässä pykälässä tarkoitettu kutsukirje on vähintään

      neljätoista päivää ennen kokousta kirjattuna annettava

      postin kuljetettavaksi. ...

      Jos kaikki asianosaiset ovat saapuneet toimitukseen tai

      saaneet vähintään neljätoista päivää ennen sen alkamista

      toimitusinsinööriltä todistettavasti kehotuksen saapua

      siihen, voidaan toimitus suorittaa vaikka kokouksesta ei

      ole tässä pykälässä säädetyllä tavalla kuulutettu ja

      ilmoitettu."

      (Swedish)

      "Förrättningsingenjören skall kalla sakägarna till

      vägförrättning genom att tillkännagiva tiden och platsen

      för sammanträdet medels kungörelse på kommunens

      anslagstavla minst fjorton dagar före sammanträdets början.

      Vägförrättning skall dessutom kungöras i en eller två på

      orten spridda tidningar minst fjorton dagar före

      sammanträdets början samt genom kallelsebrev meddelas ...

      sådan sakägare från annan kommun, vars address är nämnd i

      handlingarna eller eljest är av förrättningsingenjören

      känd. ...

      ...

      I denna paragraf avsett kallelsebrev skall minst fjorton

      dagar före sammanträdet såsom rekommenderat inlämnas till

      posten för befordran. ...

      Ha alla de som äro sakägare vid förrättning kommit

      tillstädes eller minst fjorton dagar före förrättningens

      början bevisligen av förrättningsingenjören erhållit

      uppmaning att infinna sig, kan förrättningen verkställas

      även om sammanträdet icke blivit kungjort och delgivet på

      sätt i denna paragraf är stadgat."

      (English)

      "The parties to the proceedings shall be summoned by the

      Expert at least fourteen days in advance by means of a

      public notice on the municipal notice board indicating the

      hour and venue of the hearing.

      Notification of the proceedings shall further be given in

      one or two local newspapers. ... [A] party [to the

      proceedings] resident in another municipality and whose

      address is indicated in the documents or otherwise known to

      the Expert shall be summoned by mail. ...

      ...

      [Such a] summons shall be handed over to the postal service

      at least fourteen days prior to the day of the hearing with

      a view to being sent as a registered letter. ...

      The hearing before the Expert may be held despite a failure

      to comply with the requirements concerning the public

      notification and summoning, on the condition that all

      parties attend the hearing or, if a party does not attend

      the hearing, provided there is evidence that he has

      received an invitation to the hearing from the Expert at

      least fourteen days in advance."

74.   Section 45, subsection 2 of the 1962 Act, as amended by Act

no. 521/75, reads, as far as relevant, as follows:

      (Finnish)

      "Jollei kaikille niille, joille tietoimituksesta on

      lähetettävä kursukirje sen mukaan kuin 43 §:ssä on

      säädetty, ole sitä toimitettu, eivätkä he ole saapuneet

      toimitukseen, on toimitus ... siirrettävä ja sellainen

      kutsu toimitettava. ..."

      (Swedish)

      "Har ej kallelsebrev om förrättning tillställts alla dem

      som enligt vad i 43 § är stadgat skall tillsändas sådant

      och ha dessa icke kommit tillstädes, skall förrättningen

      uppskjutas ... och sådan kallelse utgå. ..."

      (English)

      "If all parties indicated in section 43 have not been

      summoned to the hearing and provided these do not attend

      the hearing nevertheless, the proceedings shall be

      suspended ... and a summons be sent in accordance with

      section 43. ..."

75.   At the hearing the Expert and Trustees shall decide, among other

matters,

      -    whether a road serving a certain property may be

           constructed over another property and whether a right of

           way to an already existing road shall be granted;

      -    the location and width of the road;

      -    those financially responsible for the construction and

           maintenance of the road;

      -    how this responsibility is to be distributed between the

           participants; and

      -    whether compensation shall be granted, to whom, in what

           amount and whether the compensation shall be paid by all or

           only some of the participants (section 48, subsection 1 of

           the 1962 Act).

76.   If a decision has been made to construct a road, a map and a road

description and, if necessary, a cost estimation shall be drawn up. The

location of the road shall further be marked in the terrain (section

48, subsection 2, as amended by Act no. 521/75).

77.   If the parties have reached an agreement on questions regarding

the right of way as well as its maintenance, the Expert and Trustees

shall consider whether that agreement or part of it can be confirmed

(section 49, subsection 1). If the agreement is contrary to the

requirements in section 7, subsections 2 and 3, or would clearly

encumber a property significantly more than allowed by the Act, these

parts of the agreement shall not be confirmed (section 49, subsection

2, as amended by Act no. 521/75).

78.   Section 49, subsection 3 of the 1962 Act was repealed by Act

no. 217/95 which entered into force on 1 March 1995. As amended by Act

no. 521/75 it read, as far as relevant, as follows:

      (Finnish)

      "Milloin tietoimitus koskee ... metsätietä, jota varten on

      asianmukaisessa järjestyksessä hyväksytty valtion varoilla

      laadittu suunnitelma, älköön suunnitelman mukaista tien

      asemaa muutettako, jollei siihen ole painavia syitä. ..."

      (Swedish)

      "Avser förrättning ... skogsväg, för vilken med statsmedel

      utarbetad plan i vederbörlig ordning godkänts, får vägens

      planenliga läge ej ändras, såframt icke vägande skäl

      därtill föreligga. ..."

      (English)

      "If the administrative proceedings concern a forestry ...

      road planned with State funds and provided the road

      construction plan has been properly approved, the location

      of the road shall not be altered unless there are weighty

      reasons therefor. ..."

79.   The notice of appeal against decisions made by the Expert and

Trustees shall be read out to the parties attending the proceedings,

handed over to a representative of theirs as well as to any party on

request (section 51, subsection 3 of the 1962 Act and section 316 of

the 1951 Act). The appeal shall be lodged within thirty days from the

date when the proceedings were announced to be terminated or the

decision was given. The notice of appeal or a copy thereof shall be

appended to the appeal (sections 313 and 314 of the 1951 Act, the last-

mentioned as amended by Act no. 509/84).

      4.   The proceedings before the Land Court

80.   Up to the entry into force of Act no. 506/91 on 1 September 1991

amending the 1951 Act the Land Court was presided by a judge and

further consisted of the Head of the County Surveying Office ex

officio, a Land Court Surveyor and two lay judges appointed by the

President of the Land Court (section 293, subsection 1, as amended by

Act no. 263/79 and section 294, subsection 3, as amended by 267/78).

81.   The President of the Land Court and the Land Court Surveyor are

both permanently appointed (subsection 294, subsection 1 of the 1951

Act, as amended by Act no. 638/87, and sections 88 and 89 of the 1919

Constitution Act (Suomen hallitusmuoto 94/19, Regeringsform för Finland

94/19), as amended by Act no. 637/87). The two lay judges are appointed

by the President of the Land Court for a particular case from a list

of at least four persons drawn up by the relevant Municipal Council for

a period of four years (section 294, subsection 3 of the 1951 Act, as

amended by Act no. 267/78).

82.   If the Head of the County Surveying Office was prevented from

performing the tasks incumbent on him as a member of the Land Court,

he was to be replaced by a substitute in the Office assigned to take

over such duties. If an urgent duty in office or other particular

grounds so required, the Head of the County Surveying Office or his

substitute on the Land Court could appoint another land surveyor of the

County or District Surveying Office to take over the duties as a member

of the Land Court (section 295, as amended by Act no. 321/72).

83.   All members of the Land Court shall have sworn a judicial oath

before taking up their duties (section 298, as amended by Act no.

321/72). The rules governing disqualification of a member of a Land

Court in a particular case are the same as those applicable to other

professional and lay judges (section 299, subsection 1, as amended by

Act no. 321/72, and chapter 13, section 1 of the Code on Judicial

Procedure (Oikeudenkäymiskaari, Rättegångsbalk)). However, as long as

the Head of the County Surveying Office sat on the Land Court he was

not considered biased for having performed tasks incumbent on the

Office in relation to the administrative proceedings in a particular

case (section 299, subsection 2 of the 1951 Act, repealed by Act

no. 506/91).

84.   As from 1 September 1991, when an overall restructuring of the

county surveying administration entered into force, the Land Court

consists of only four members, the Head of the County Surveying Office

no longer sitting on the Court (section 293, subsection 1, as amended

by Act no. 506/91).

85.    In the Government Bill to Parliament proposing the above-

mentioned 1991 amendments to the 1951 Act it was stated that the Land

Court should be an impartial and independent tribunal and that the

participation of the Head of the County Surveying Office on that court

"constituted an exception from the general practice" (Bill No. 199/90,

p. 3). Following the amendments the members of the Land Court would be

"totally independent from the county surveying authority responsible

for the administrative proceedings" (ibid., p. 9).

86.   The notification of a hearing before the Land Court shall be

placed on the municipal notice board and appear in one or two local

newspapers at least fourteen days before the hearing. Appellants whose

addresses are known to the Court should further be summoned in writing

at least fourteen days beforehand (section 320 of the 1951 Act, as

amended by Act no. 321/72).

87.   The Expert shall attend the Land Court's hearing in order to

reply to its questions regarding the administrative proceedings

conducted by him. He shall further be heard in regard to the

submissions made by the parties. The Expert's absence shall, however,

not prevent the Land Court from examining and deciding the case

(section 324, as amended by Act 321/72). If considered necessary, the

Land Court may invite other experts to submit information at its

hearing (section 300, as amended by Act no. 321/72).

88.   If a matter has been brought before the Land Court by way of an

appeal, a party who is not an appellant shall nevertheless be allowed

to present claims before the court on the ground that the matter also

affects his rights (section 322, subsection 1, as amended by Act

no. 321/72).

89.   Subject to its territorial competence the County Surveying Office

keeps a register of the private roads for which an association of joint

road owners has been established. The register contains, for instance,

the name and address of the Executor. Part of the information shall be

sent to, among other authorities, the Road Board for information

(section 51a of the 1962 Act, as amended by Act no. 521/75).

      5.   Supreme Court practice

90.   In a case decided by the Supreme Court (No. 1986 II 127) a party

to proceedings under the 1962 Act had been absent from the hearing

before the Expert and Trustees, where none of the attending parties had

requested compensation for the interference with their property rights

to be caused by the planned road and where no right to compensation had

therefore been granted. An absent party's appeal to the Land Court in

which he requested compensation was dismissed without an examination

of its merits, since no compensation claim had been made by him in the

proceedings before the Expert and Trustees. The Supreme Court observed

that pursuant to section 48, subsection 1 of the 1962 Act the

compensation matter was to be examined by the Expert and Trustees ex

officio. As the absent party had therefore not lost his right to

request compensation before the Land Court, the court should not have

dismissed his appeal. The matter was therefore returned to the Expert

and Trustees.

91.   The above-mentioned judgment confirmed the principle adopted in

a previous judgment of 1981, no. II 139.

III.  OPINION OF THE COMMISSION

A.    Complaints declared admissible

92.   The Commission has declared admissible:

      - the applicant's complaint concerning the presence of the Head

of the County Surveying Office on the Land Court, the applicant's

access to the Land Court as well as the fairness of the proceedings;

and

      - his complaint concerning the allegedly unjustified interference

with his property rights caused by the construction of the road,

excluding the logging on his property as carried out by the Forestry

Board in 1988, and the lack of an effective remedy.

B.    Points at issue

93.   The issues to be determined are:

      - whether there has been a violation of Article 6 para. 1

(Art. 6-1) of the Convention and/or Article 13 (Art. 13); and

      - whether there has been a violation of Article 1 of Protocol

No. 1 (P1-1) to the Convention and/or Article 13 (Art. 13) of the

Convention.

C.    As regards Article 6 para. 1 (Art. 6-1) of the Convention

94.   In so far as it is relevant Article 6 para. 1 (Art. 6-1) of the

Convention reads as follows:

      "In the determination of his civil rights ..., everyone is

      entitled to a fair ... hearing ... by an ... impartial

      tribunal established by law. ..."

95.   The applicant complains that the Land Court was not objectively

impartial, one of its members being the Head of the County Surveying

Office and thereby a superior of the Expert. This official was to some

extent the Expert's superior and to some extent responsible for the

proceedings conducted before the Expert and Trustees.

96.   The applicant furthermore complains that the proceedings as a

whole were unfair in several respects and makes the following

allegations. He was not summoned to any of the meetings or hearings

before the Forestry Board, the Expert and Trustees or the Land Court,

although his address was known to the authorities. Although he attended

the hearing before the Expert and Trustees, he had been informed about

it at a very short notice and was thus not sufficiently prepared for

it. Those attending were never asked whether they considered the

meeting to have been lawfully called, although such a statement appears

in the minutes. Those who had instituted the proceedings remained

unknown. Contrary to domestic law no estimation of the total road costs

was presented prior to or at the hearing. Nor was the relative

distribution of the road costs properly examined. At this hearing the

Forestry Board's plan was presented to the applicant for the first time

and he was not afforded sufficient time to study it. No general

discussion concerning the plan was allowed. The parties could only

submit their opinions one by one, other parties being unable to

overhear them. They were not allowed to propose a change of the

location of the road. The Forestry Board, however, was allowed to

submit its opinion in public. The applicant's compensation claim was

rejected without a fair consideration.  No notice of appeal was read

out or given to him at the close of the meeting.

97.   The applicant, moreover, alleges that the proceedings before the

Land Court were also unfair in that it wrongly declined to examine his

compensation claim on its merits. Nor did it properly hear any of

opponents of the Forestry Board's plan, but merely its proponents,

including the Executors of the plan and the Forestry Board itself. In

so far as his appeals were examined on their merits he maintains that

not all parties were treated equally. Although the alternative plan

supported by him had been presented at the Land Court's first hearing,

it was no longer considered at the second one, where the Land Court

considered itself limited either to confirming or quashing the Forestry

Board's plan. Accordingly, although a majority of all those affected

by the road had objected to the Forestry Board's plan, the Forestry

Board was de facto the only party heard at the Land Court's second

hearing. Had the proceedings been fair, the road costs could, pursuant

to section 22, subsection 2 of the 1962 Act, have been imposed solely

on its proponents.

98.   The applicant finally submits that the proceedings were also

unfair in that he was unable to obtain knowledge of the number and

respective identities of the proponents of the Forestry Board's plan.

The proponents were de facto represented by the Forestry Board itself,

although its role, in particular in the proceedings before the Land

Court, should have been limited to that of an independent expert.

Consequently, the opponents of the Forestry Board's plan, allegedly

constituting a clear majority of those to be affected by the road, were

not placed on an equal footing with its proponents.

99.   The Government maintain that there has been no violation of

Article 6 para. 1 (Art. 6-1). They emphasise that under domestic law

at the relevant time the Head of the County Surveying Office was not

biased as a member of the Land Court even if he had performed tasks

incumbent on his Office in relation to the administrative proceedings

in the applicant's case. This was so because his Office was merely

responsible for registering the proceedings and keeping their records.

He did not appoint the officials of the District Surveying Office,

notably the Expert in the present case, and had no right to influence

the outcome of the proceedings before the Expert and Trustees.

Moreover, the Expert was not a party to the case before the Land Court.

Finally, although he was lower in rank than the Head of the County

Surveying Office, the Expert was not subordinated to that official but

acted completely independently.

100.  As regards the fairness of the proceedings, the Government admit

that the applicant was not summoned to the meetings arranged by the

Forestry Board, although his address was known. In those proceedings,

however, he had no right under domestic law to be heard. In any case,

those proceedings fall outside the Commission's competence ratione

temporis and materiae, given that they took place prior to the entry

into force of the Convention with regard to the respondent State and

since they did not determine any civil rights or obligations of the

applicant.

101.  Whilst further admitting that the applicant was not summoned to

the proceedings before the Expert and Trustees either, the Government

underline that he nevertheless attended the hearing which was,

moreover, fair. They refer to the minutes from the hearing which, for

instance, do not support the applicant's contention that he requested

compensation. In any event, the question of compensation was considered

ex officio by the Expert and Trustees. Although admittedly the Forestry

Board's plan was introduced only at the hearing, the hearing was

suspended for a sufficiently lengthy period so as to enable it to be

studied. The Government finally refer to the Land Court's finding that

the applicant had attended the hearing, where a notice of appeal had

been read out and a copy handed over to one of the Executors.

102.  As for the fairness of the proceedings before the Land Court, the

Government explain that part of the applicant's separate appeal was

dismissed without examination because his compensation request had not

been made before the Expert and Trustees. The Government concede that,

according to case-law of the Supreme Court, a compensation claim under

the 1962 Act shall be examined ex officio by the Land Courts. The

practice of the Land Courts when dealing with fresh compensation claims

appears, however, to be varying.

103.  As far as the applicant's appeals were examined on their merits

and rejected, the Government refer to the Land Court's judgment which

shows that it also gave opponents of the Forestry Board's plan a

possibility to express their opinion. The role of the Forestry Board

in the proceedings before the Land Court was merely to put its

expertise at the disposal of, in principle, both the proponents and the

opponents of its plan and the road construction project as a whole.

104.  In their submissions at the hearing before the Commission the

Government conceded that, whilst the Forestry Board's plan was not

binding under the 1962 Act, it had a significant bearing on the final

outcome of the proceedings, given that section 49, subsection 3 of the

1962 Act presupposes weighty reasons for its amendment. The Expert and

Trustees were therefore to a great extent bound by it. Nor could the

Land Court immediately have approved a plan significantly different

from that of the Forestry Board.

105.  In their subsequent further observations on the merits, however,

the Government emphasise that the Land Court had the appropriate

jurisdiction as regards both points of facts and points of law raised

in the appeal proceedings. It could thus have rejected the Forestry

Board's plan as a whole or have amended it, having regard to sections

7 to 9 in the 1962 Act.

106.  Summing up, the Government consider that the applicant was not

placed at a substantial disadvantage in the proceedings as a whole.

107.  The Commission observes that except for the compensation claim

made in his separate appeal the applicant's appeals to the Land Court

were examined on their merits and rejected. To this extent there was

a determination by a "tribunal" of his property rights, these being

"civil rights" within the meaning of Article 6 para. 1 (Art. 6-1) (cf.,

e.g., Eur. Court H.R., Zander v. Sweden judgment of 25 November 1993,

Series A no. 279-B, p. 40, para. 27). It is undisputed that the Land

Court was "established by law".

108.  As regards the question whether the Land Court was an "impartial

tribunal", the Commission recalls that the existence of impartiality

for the purposes of Article 6 para. 1 (Art. 6-1) must be determined

according to a subjective test, that is on the basis of the personal

conviction of a particular judge in a given case, and also according

to an objective test, that is ascertaining whether the judge offered

guarantees sufficient to exclude any legitimate doubt in his respect

(e.g., Eur. Court H.R., Fey v. Austria judgment of 24 February 1993,

Series A no. 255-A, p. 12, para. 28). In the administration of justice

even appearances are of importance, although the standpoint of the

persons concerned is not in itself decisive. The misgivings of the

individuals before the courts must in addition be capable of being held

to be objectively justified (cf., e.g., Eur. Court H.R., Kraska v.

Switzerland judgment of 19 April 1993, Series A no. 254-B, p. 50,

para. 32). A tribunal found to be partial can, in principle, not

guarantee a fair hearing to the individuals involved in proceedings

before it (cf. Nos. 15530/89 and 15531/89, Mitap and Müftüoglu v.

Turkey, Comm. Report 8.12.94, para. 109).

109.  The Commission observes that the impartiality of the President

of the Land Court and the Land Court Surveyor is not in issue. The

Commission has, moreover, declared inadmissible the applicant's

complaint concerning the impartiality of the lay judges appointed by

the President of the Land Court from the list drawn up by the

municipality. Finally, as regards the Head of the County Surveying

Office only his objective impartiality has been questioned by the

applicant.

110.  The Commission further observes that the Head of the County

Surveying Office was, albeit also a State land surveyor, not attached

to the same Office as the Expert. It is undisputed, however, that once

an association of joint road owners has been founded for the

administration of a private road certain administrative tasks were

incumbent on the County Surveying Office pursuant to section 51a of the

1962 Act. The objectively close relationship between the District and

County Surveying Office was further borne out by section 295 of the

1951 Act, according to which the Head of the County Surveying Office

or his substitute at that Office could, in certain situations, if

prevented from carrying out his duties as a member of the Land Court,

appoint another land surveyor of the County or District Surveying

Office to sit on the Land Court.

111.  It is true that the Head of the County Surveying Office had to

swear a judicial oath before taking up his duties as a member of the

Land Court. Moreover, the rules governing his disqualification as a

member of that Court in a particular case were, in principle, the same

as those generally applicable to professional and lay judges. Domestic

law at the time, however, expressly exempted him from disqualification

for having performed tasks related to the administrative proceedings

in a particular case such as that involving the applicant. Certain

doubts about the compatibility of the position of the Head of the

County Surveying Office as a member of the Land Court with the notion

of an independent and impartial tribunal were raised in the

Government's Bill proposing a legislative change in this regard (see

para. 85). Thus the applicant's case was heard by a tribunal whose

impartiality seems to have been recognised by national law to be open

to doubt (cf. Eur. Court H.R., Oberschlick judgment of 23 May 1991,

Series A no. 204, p. 23, para. 50).

112.  It is furthermore true that under domestic law the Expert was,

strictly speaking, not a party to the proceedings before the Land

Court. This, however, is not of decisive importance, since the Land

Court was called upon to examine the applicant's appeal against the

outcome of the proceedings before that very Expert and the Trustees

assisting him.

113.  In these circumstances and regardless of whether the Head of the

County Surveying Office personally performed the tasks incumbent on his

Office the Commission finds that the impartiality of the Land Court was

capable of appearing open to doubt on account of his presence on the

bench. The applicant's fears in this respect were thus objectively

justified. Accordingly, Article 6 para. 1 (Art. 6-1) has been violated

in this respect.

114.   In the light of its above conclusion the Commission considers

that the Land Court could not have guaranteed the applicant a fair

hearing in any respect of his appeals. The Commission need not

therefore examine the further issues raised by the applicant in this

complaint.

      CONCLUSION

115.  The Commission concludes, unanimously, that in the present case

there has been a violation of Article 6 para. 1 (Art. 6-1) of the

Convention in that the applicant did not receive a fair hearing before

an impartial tribunal.

D.    As regards Article 1 of Protocol No. 1 (P1-1) to the Convention

116.  Article 1 of Protocol No. 1 (P1-1) reads as follows:

      "Every natural or legal person is entitled to the peaceful

      enjoyment of his possessions.  No one shall be deprived of

      his possessions except in the public interest and subject

      to the conditions provided for by law and by the general

      principles of international law.

      The preceding provisions shall not, however, in any way

      impair the right of a State to enforce such laws as it

      deems necessary to control the use of property in

      accordance with the general interest or to secure the

      payment of taxes or other contributions or penalties."

117.  The Commission recalls that in its decision on the admissibility

of the application it found that in so far as the present complaint

concerned the logging on the applicant's property carried out by the

Forestry Board in 1988 it was incompatible ratione temporis with the

provisions of the Convention within the meaning of Article 27 para. 2

(Art. 27-2) and therefore inadmissible.

118.  The applicant has also complained that the construction of the

road interfered in an unjustified manner with his property rights. It

did not pursue any general interest, as it was an exclusively private

road. Moreover, the alternative road plan supported by him would have

been a considerably cheaper solution and would not have affected his

property in as serious a way. He finally claims that his responsibility

for the road costs is excessive and disproportional to the benefits

from the road, in particular since his property was already served by

another road and since his share of the costs for the construction of

the new road allegedly equal the total value of the potential timber

from the forest on his property.

119.  The applicant contends that the Government have not shown any

document indicating the relative distribution of the road costs

between the road participants. He asserts that not all identities of

the participants have been made known and that the Forestry Board has

not properly dealt with his request for an exemption from participating

in the road and its costs.

120.  The applicant finally repeats that he was unaware of the

proceedings before the Forestry Board, as he had not been summoned to

any of its hearings. In his further observations on the merits,

however, he states having been informed about the planned location of

the road prior to the logging which took place in 1988.

121.  The Government submit that the road construction constituted an

interference with the applicant's rights under Article 1 of

Protocol No. 1 (P1-1) amounting to a control of the use of his

property. The interference was justified, however, since the costs for

which he became responsible were not excessive and given the States'

wide margin of appreciation in the field of property rights. Reference

is made, in particular, to the importance of forestry both for the

economy of individual owners of forest and the country as a whole.

122.  The Government further consider that by authorising the signing

of the road agreement the applicant must be considered to have waived,

at the latest on 12 January 1992, his right to compensation for the

damage caused to his property. Having accepted the road agreement, the

applicant also received a state subsidy and was granted a low-interest

loan, both intended to facilitate his participation in the road costs.

123.  The Government submit that the proceedings as a whole were fair

and afforded the applicant a reasonable opportunity of putting his case

to the relevant authorities. In particular, he had received knowledge

of the Forestry Board's plan before the proceedings before the Expert

and Trustees commenced. Whilst conceding that the Expert and Trustees

were to a great extent bound by the plan, the Government underline that

opponents of a plan approved by that body may later be exempted from

its maintenance costs pursuant to section 22, subsection 3 of the 1962

Act. Moreover, whilst the applicant was admittedly not summoned to the

hearing before the Expert and Trustees, he nevertheless attended it,

as he attended the subsequent hearings before the Land Court.

124.  The Government finally refer to a general recommendation

according to which the Forestry Board can begin planning a road if and

when 70 per cent of the property owners support a proposal to that

effect. This was, however, not a requirement by law to be followed in,

for instance, the applicant's case.

125.  The Commission will limit its examination to whether the facts

occurring after 10 May 1990, the date when the Convention entered into

force with regard to Finland, disclosed a breach of Article 1 of

Protocol No. 1 (P1-1). Events prior to 10 May 1990 will be taken into

account merely as a background to the issues before the Commission (cf.

Eur. Court H.R., Hokkanen v. Finland judgment of 23 September 1994,

para. 53, to be published in Series A no. 299-A).

      1.   The deprivation of the applicant's property

126.  The Commission recalls that Article 1 of Protocol No. 1 (P1-1)

comprises three distinct rules. The first rule, set out in the first

sentence of the first paragraph, is of a general nature and enunciates

the principle of peaceful enjoyment of property. The second rule,

contained in the second sentence of the same paragraph, covers

deprivation of possessions and makes it subject to certain conditions.

The third rule, stated in the second paragraph, recognises that

Contracting States are entitled, amongst other things, to control the

use of property in accordance with the general interest. The three

rules are not "distinct" in the sense of being unconnected: the second

and third rules are concerned with particular instances of interference

with the right to peaceful enjoyment of property and should therefore

be construed in the light of the general principle enunciated in the

first rule (e.g., Eur. Court H.R., Fredin judgment of 18 February 1991,

Series A no. 192, p. 14, para. 41).

127.  The Commission furthermore recalls that although Article 1

(Art. 1) contains no explicit procedural requirements, the proceedings

at issue must afford the individual with a reasonable opportunity of

putting his or her case to the responsible authorities for the purpose

of effectively challenging the measures interfering with his rights

under Article 1 of Protocol No. 1 (P1-1). In ascertaining whether this

condition has been satisfied a comprehensive view must be taken of the

applicable procedures (cf., e.g., Eur. Court H.R., Agosi judgment of

24 October 1986, Series A no. 108, p. 19, para. 55; Eur. Court H.R.,

Hentrich v. France judgment of 22 September 1994, para. 49, to be

published in Series A no. 296-A).

128.  The Commission observes that a road was constructed over the

applicant's property by virtue of a right of way encumbering his

property and favouring certain other properties. For this purpose the

applicant had to give up land on a permanent basis. Although this did

not take place by way of expropriation proceedings leading to the

transfer of a formal title of ownership, in the circumstances of the

case the creation of the right of way constituted a deprivation of the

applicant's property to the extent that this property was encumbered

by the right of way (cf. e.g., the above-mentioned Agosi judgment, pp.

17-18, para. 51). Whilst this deprivation did not transfer property

from the applicant to the State, it resulted from a plan adopted by the

Forestry Board. The Commission therefore considers that, regardless of

the fact that a private road was at issue, the deprivation incurred

State responsibility (cf., mutatis mutandis, No. 12570/86, Dec.

18.1.89, D.R. 59 p. 127; a contrario, No. 9781/82, Dec. 14.5.84,

D.R. 37 p. 42).

129.  The Commission recalls that a deprivation of possessions

constitutes an interference with property rights which is to be

examined under the second sentence of the first paragraph of Article 1

(Art. 1) (cf., Eur. Court H.R., Papamichalopoulos and Others v. Greece

judgment of 24 June 1993, Series A no. 260-B, pp. 69-70, paras. 41-46).

Such a deprivation must, firstly, pursue a legitimate aim in the public

interest. This requirement may be fulfilled even if the community at

large has no direct use or enjoyment of the property deprived from the

applicant (cf., mutatis mutandis, Eur. Court H.R. James and Others

judgment of 21 February 1986, Series A no. 98, pp. 30-32,

paras. 39-45). Secondly, there must also be a reasonable relationship

of proportionality between the means employed and the aim sought to be

realised (ibid., p. 34, para. 50).

130.  The Commission furthermore reiterates that the requirement that

a deprivation be "subject to the conditions provided for by law"

presupposes the existence of and compliance with adequately accessible

and sufficiently precise domestic legal provisions (Eur. Court H.R.,

Lithgow and Others judgment of 8 July 1986, Series A no. 102, p. 47,

para. 110). Deprivation of property belonging to a non-national is,

moreover, subject to the conditions provided for "by the general

principles of international law" (ibid., p. 47, para. 112).

131.  The Commission considers that the deprivation of part of the

applicant's property had the legitimate aim of facilitating and

stimulating forestry in the area served by the road. It is true that

the road was private and could therefore only be used by a limited

number of property owners and others. The Commission observes, however,

that under section 22 of the 1962 Act also others than the property

owners in the area may be allowed to use the road, provided they

participate in its maintenance costs. In these circumstances and having

regard to State's margin of appreciation the Commission accepts that

the deprivation took place in the public interest.

132.  As for the requirement that a deprivation be "subject to the

conditions provided for by law", the Commission recalls that its power

to review compliance with domestic law is limited (cf. the

above-mentioned Fredin judgment, pp. 16-17, para. 50). In interpreting

and applying this phrase the Commission must take into account the

principles concerning the interpretation of other references to the

"law" in the Convention, but it must also take account of the

differences in the wording of the different provisions (the above-

mentioned James and Others judgment, pp. 40-41, para. 67; James and

Others v. the United Kingdom, Comm. Report 11.5.84, para. 141,

Eur. Court H.R., Series A no. 98, pp. 68-69).

133.  The Commission considers that the phrase "conditions provided for

by law" refers primarily to such matters as the power to expropriate

(or otherwise take property) and compensation terms which, accordingly,

must be defined by the law with reasonable precision. Although the

second sentence of the first paragraph or any other provision of

Article 1 of Protocol No. 1 (P1-1), unlike Article 5 para. 1 (Art. 5-1)

of the Convention which refers to "a procedure prescribed by law", does

not contain any explicit procedural requirement, the prohibition of

arbitrariness is inherent in the provision in question. A manifest

violation of the national procedural rules governing the taking of

property can therefore, either alone or in combination with other

circumstances, amount to a violation of the requirement that a

deprivation of property be subject to the conditions provided for by

law.

134.  In the present case the national courts held that the deprivation

of the property had taken place in accordance with the relevant

provisions of the 1962 Act. Recalling its limited power to review

compliance with domestic law, the Commission considers that it has no

reason to dispute those findings in so far as the substantive

conditions of the deprivation of property are concerned. The Commission

also accepts that the relevant domestic legal provisions fulfil the

requirements of accessibility and foreseeability.

135.  In so far as the procedure is concerned the Commission, however,

notes the Government's concession that according to the Supreme Court's

interpretation of the 1962 Act, as shown by its judgments no. 1981 II

139 and 1986 II 127, claims for compensation were to be considered ex

officio by the Land Courts. The applicant's claim, as referred to in

its judgment, was nevertheless dismissed by the competent Land Court

without an examination of its merits on the ground that compensation

had not been claimed in the proceedings before the Expert and Trustees.

It thus appears that the procedural requirements of domestic law have

not been complied with.

136.  The Commission, however, cannot conclude on this basis that the

proceedings were arbitrary. In this respect it notes that the applicant

could explicitly have raised the above issue of non-compliance with

domestic law in his request for leave to appeal to the Supreme Court,

but failed to do so. It furthermore recalls its finding that there is

no indication that the deprivation of his property was otherwise

illegal under domestic law (see para. 134). Moreover, taking into

account the forestry improvement subsidy and the low-interest loan

granted to the applicant (para. 53), the Commission finds no indication

that the way in which he was compensated for the deprivation of his

property (see also para. 34 in fine) was not in reasonable relation to

its value or in violation of the general principles of international

law. Accordingly, Article 1 of Protocol No. 1 (P1-1) has not been

violated as regards the deprivation of property.

      CONCLUSION

137.  The Commission concludes, by 8 votes to 1, that in the present

case there has been no violation of Article 1 of Protocol No. 1 (P1-1)

to the Convention as regards the deprivation of part of the applicant's

property.

      2.   The applicant's obligation to participate in the road costs

138.  Recalling its finding as regards State responsibility for the

deprivation of part of the applicant's property (para. 128), the

Commission observes that, although the road costs were not levied by

the State, these equally resulted from the plan adopted by the Forestry

Board. The obligation imposed on the applicant, as an owner of property

through which the road was constructed, to participate in these costs

thus also incurred State responsibility.

139.  The Commission considers that the applicant's obligation to

participate in these costs constituted an interference with his

property rights which falls to be examined under the second paragraph

of Article 1 of Protocol No. 1 (P1-1) as to its lawfulness, purpose and

proportionality. As regards the proportionality, a fair balance must

be struck between the demands of the general interest of the community

and the requirements of the protection of the individual's fundamental

rights (e.g., the above-mentioned Fredin judgment, pp. 16 et seq.,

paras. 48 et seq.).

140.  The Commission considers that this interference had the same

legitimate aim as the deprivation of his property, namely to facilitate

and stimulate forestry in the area affected by the road. This purpose

was, moreover, in the general interest.

141.  As for the question of proportionality, the Commission finds it

established that the applicant's share of the road construction costs

was more significant than the size of his property would have called

for. It observes, however, that he was granted a State forestry

improvement subsidy and a low-interest forestry improvement loan by the

State in amounts equalling his share of those costs. Moreover, it is

still open to him to request an exemption from the maintenance costs

for the road, since his requests of November 1991 were not addressed

to the association of road owners, as prescribed in section 28,

subsection 2 of the 1962 Act. Finally, the Commission would not exclude

that the value of the remaining part of the applicant's property

actually increased as a result of the new road connection.

142.  The Commission observes, however, that the applicant has

complained not only that his responsibility for the road costs was

excessive but also, albeit under Article 6 para. 1 (Art. 6-1) of the

Convention, that the proceedings were unfair, since he was not

sufficiently involved in the proceedings up to and including the Land

Court.

143.  The Commission has recalled above (para. 127) that in assessing

whether a fair balance was struck in accordance with Article 1 of

Protocol No. 1 (P1-1) between the conflicting interests at stake, it

must also satisfy itself that the applicant was afforded a reasonable

opportunity of putting his objections to the Forestry Board's road

construction plan to the responsible authorities. These authorities

need not be "impartial tribunals" within the meaning of Article 6

para. 1 (Art. 6-1) of the Convention. To this end the Commission must

therefore take into account the whole of the proceedings in the course

of which the Forestry Board's plan was drawn up and approved as well

as the subsequent appeal proceedings, bearing in mind its competence

ratione temporis (para. 125).

144.  The Commission thus considers that the aspect of the applicant's

complaint under Article 6 para. 1 (Art. 6-1) of the Convention

concerning his inability to influence the proceedings in substance

falls to be examined under Article 1 of Protocol No. 1 (P1-1). A

preliminary question arising is whether the applicant had, on

10 May 1990, been afforded an opportunity of effectively opposing the

plan drawn up by the Forestry Board and adopted at the meeting on

3 June 1988. A further  question is whether, after 10 May 1990, he had

the opportunity of presenting to the Expert and Trustees and the Land

Court any weighty reason which could have led to the rejection or

amendment of the Forestry Board's plan and possibly to the approval of

the alternative plan supported by him.

145.  It is undisputed that the applicant had not been summoned to the

Forestry Board's meeting on 3 June 1988, where the road construction

plan had been adopted in so far as affecting, inter alia, his property.

The Commission cannot find it established that he had nevertheless

received prior information about the meeting and therefore could have

ensured his attendance or representation at it. Before the Commission

he has nevertheless conceded having received knowledge of the plan soon

after the meeting and prior to the logging on his property. At the

latest in November 1988 he had been informed by the National Forestry

Board of his possibility to challenge the plan in the proceedings

before the Expert and Trustees. The Commission therefore finds that,

although, on 10 May 1990, he had not yet had an opportunity of

effectively opposing the Forestry Board's plan, he had become fully

aware of the proceedings pending before the Expert and Trustees and of

the plan which was to be reviewed in those proceedings. He had thus

been afforded an ample opportunity to prepare himself for the hearing

before that body.

146.   As for the period starting on 10 May 1990, it is undisputed that

the applicant had not been summoned to the hearing before the Expert

and Trustees but that he nevertheless attended it. The minutes from the

hearing do not support the applicant's contention that he was prevented

from challenging the Forestry Board's plan in so far as it was to

affect his property.

147.  The Commission, moreover, observes that irrespective of whether

or not he received a notice of appeal at the close of the hearing

before the Expert and Trustees he nevertheless appealed to the Land

Court which accepted him as an appellant both in respect of his

separate appeal and in respect of the joint appeal of 23 July 1990.

148.  The Commission further finds it established that the Land Court

duly summoned the applicant to its hearing on 16 October 1990, where

he was represented by two different persons due to his two appeals.

Both of his representatives availed themselves of the opportunity to

argue his respective appeals. Also at the second hearing both of them

were heard.

149.  The Commission finds that the requirement in section 49,

subsection 3 of the 1962 Act according to which the Forestry Board's

plan could only be amended for weighty reasons did not as such prevent

the applicant from putting his case to the authorities reviewing it.

In these circumstances it can be left open whether the Land Court

could, in principle, have adopted the alternative plan supported by

him.

150.  The Commission furthermore observes that under section 22,

subsection 2 of the 1962 a private road shall not be constructed if a

significant number of those obliged to participate in its costs oppose

its construction. The Commission cannot find it established that the

applicant would have been prevented from verifying the identities and

respective number of proponents and opponents of the Forestry Board's

plan in order to challenge the plan on the grounds of insufficient

support.

151.  Nor can the Commission find that the applicant was prevented due

to insufficient information about the other road participants from

challenging, under section 23, subsection 1 of the 1962 Act, the

assessment of his share of the road costs. The Commission notes the

Forestry Board's list of 19 June 1990 setting out the size of each

property and each owner's share of the costs. It further notes that,

according to the minutes from the hearing before the Expert and

Trustees, a proposal by the Forestry Board for the relative

distribution of road costs was read out and not opposed by the

applicant.

152.  In the above circumstances the Commission concludes that the

proceedings viewed as a whole afforded the applicant a reasonable

opportunity of putting his case to the responsible authorities with a

view to establishing a fair balance between the conflicting interests

at stake. Having regard to its considerations above (paras. 140-141),

the Commission is further satisfied that such a balance was struck in

his case. Accordingly, the interference with his property rights by

virtue of his obligation to participate in the road costs was

proportionate to the aim pursued. Article 1 of Protocol No. 1 (P1-1)

has therefore not been violated in this respect either.

      CONCLUSION

153.  The Commission concludes, by 8 votes to 1, that in the present

case there has been no violation of Article 1 of Protocol No. 1 (P1-1)

to the Convention as regards the applicant's obligation to participate

in the road costs.

E.    As regards Article 13 (Art. 13) of the Convention

154.  Article 13 (Art. 13) of the Convention reads as follows:

      "Everyone whose rights and freedoms as set forth in this

      Convention are violated shall have an effective remedy

      before a national authority notwithstanding that the

      violation has been committed by persons acting in an

      official capacity."

155.  Having regard to its findings in regard to the complaints under

Article 6 para. 1 (Art. 6-1) of the Convention and Article 1 of

Protocol No. 1 (P1-1), the Commission finds that no further issue

arises under Article 13 (Art. 13).

      CONCLUSION

156.  The Commission concludes, unanimously, that no further issue

arises under Article 13 (Art. 13) of the Convention.

F.    Recapitulation

157.  The Commission concludes, unanimously, that in the present case

there has been a violation of Article 6 para. 1 (Art. 6-1) of the

Convention in that the applicant did not receive a fair hearing before

an impartial tribunal (para. 115).

158.  The Commission concludes, by 8 votes to 1, that in the present

case there has been no violation of Article 1 of Protocol No. 1 (P1-1)

to the Convention as regards the deprivation of part of the applicant's

property (para. 137).

159.  The Commission concludes, by 8 votes to 1, that in the present

case there has been no violation of Article 1 of Protocol No. 1 (P1-1)

as regards the applicant's obligation to participate in the road costs

(para. 153).

160.  The Commission concludes, unanimously, that no further issue

arises under Article 13 (Art. 13) of the Convention (para. 156).

Secretary to the First Chamber         President of the First Chamber

     (M.F. BUQUICCHIO)                          (C.L. ROZAKIS)

                                                        (Or. English)

             PARTIALLY DISSENTING OPINION OF MRS. J. LIDDY

As regards Article 6 para. 1 of the Convention

1.     I agree that there has been a violation of the Convention in

that the applicant did not receive a fair hearing before an impartial

tribunal.

As regards Article 1 of Protocol No. 1 to the Convention

2.     The applicant had a road built on his property against his will

but for the benefit of neighbouring private individuals, who were given

a right of way over his property. He did not receive any financial

compensation, it being considered that he also would benefit from the

road (para. 34 of the Report). On the contrary he was obliged to

contribute to the costs of the road. When all avenues of appeal were

exhausted he signed, under protest, the relevant road agreement in

order to reduce the extent of his financial contribution because

signature of the agreement qualified him for a small subsidy and

low-interest loan.

3.     A first preliminary question is whether the construction of the

road and creation of the right of way can be categorised as a

deprivation of possessions under paragraph 1 of Article 1 of

Protocol No. 1 or whether it was a control of the use of property

within the meaning of paragraph 2 of that Article. On balance, I agree

with the majority that the measure more closely resembles a

deprivation. This was not a measure enabling a public authority to have

occasional access to a structure built on the land (such as an

electricity pylon) in the public interest. It was, rather, the

deprivation of an essential attribute of private ownership, the right

to refuse entry to private individuals. At the same time it was a

transfer to those private individuals of the right to use the land for

the purpose of passage subject to the applicant's right to use the land

for that purpose and no other purpose.

3.     A second preliminary question is whether the Commission's

case-law to the effect that an obligation to contribute to road costs

is a "contribution" within the meaning of paragraph 2 of Article 1

(Application No. 7489/76, D.R. 9 p. 114) is still valid. The Court has

recently, in the case of Gasus Dosier- und Fördertechnik GmbH v. the

Netherlands (Eur. Court H.R., judgment of 23 February 1995, to be

published in Series A no. 306-B), left open a particular question. That

question is whether the right of States to enact such laws as they deem

necessary for the purpose of "securing the payment of taxes" is, as the

wording may suggest, limited to procedural tax laws (that is to say:

laws which regulate the formalities of taxation, including the

enforcement of tax debts) or whether it also covers substantive tax

laws (that is to say: laws which lay down the circumstances under which

tax is due and the amounts payable) (para. 60 of the judgment). The

same question would appear to arise in relation to the State's right

to "secure" the payment of "other contributions". In my opinion the

word "secure" covers not only technical devices to make certain

("assurer" in the French text) that payment is made. It also carries

the broader meaning of obtaining, or satisfying oneself that one has

not only the means but the legal right to have the payment made.

Accordingly, the applicant's obligation to participate in the road

costs falls to be examined under paragraph 2 of Article 1.

4.     It is then necessary to examine in relation to both measures

(the deprivation of a property right and the obligation to make

contributions) whether a fair balance has been struck between the

demands of the general interest of stimulating forestry in the area and

the interest of the individual. In particular it is necessary to

examine whether the procedures in question afforded the applicant a

reasonable opportunity of putting his case to the responsible

authorities (Eur. Court H.R., Hentrich v. France judgment of 22

September 1994, paras. 44 and 49, to be published in Series A

no. 296-A; Agosi v. the United Kingdom judgment of 24 October

1986,-Series A no. 108, paras. 52 and 55; the above-mentioned Gasus

Dosier- und Fördertechnik GmbH judgment, paras. 62 and 73).

5.     The following features of the procedures occurring after

10 May 1990 seem relevant to this assessment:-

(i)    The proceedings before the Expert and Trustees and before the

       Land Court took place against the background that the applicant

       had not been summonsed to the meetings arranged by the Forestry

       Board, although his address was known.

(ii)   The Forestry Board's plan had a significant bearing on the

       final outcome of the proceedings before the Expert and Trustees

       and the Land Court, because, as conceded by the Government

       (para. 104 of the Report), only "weighty" reasons could lead to

       its amendment.

(iii)  The applicant did not have an identifiable opponent at any

       stage. Before the Land Court his de facto opponents were the

       Forestry Board and the Expert, who had drawn up or upheld the

       plan and list of contributions. However, they were not seen as

       opposing parties. The Expert was heard as an independent expert

       rather than as an interested party.

(iv)   The applicant had no minutes of the proceedings that had been

       arranged by the Forestry Board, notwithstanding that he needed

       "weighty" reasons to upset the Board's plan.

(v)    The applicant was given no written notice of the list of

       contributions.

(vi)   The Land Court did not satisfy the requirement of impartiality

       contained in Article 6 para. 1 of the Convention.

6.     Taking "a comprehensive view of the applicable procedures" (the

above-mentioned Agosi judgment, para. 55), it appears to me that the

applicant's original disadvantage in not being summonsed to the

meetings arranged by the Forestry Board was exacerbated by numerous

features of the proceedings that followed. I cannot conclude that he

had a reasonable opportunity of putting his case to the competent

authorities.

7.     Accordingly, the procedural requirements of Article 1 of

Protocol No. 1 were not observed, with the consequence that no fair

balance was struck between the demands of the general interest and the

interest of the individual. For these reasons I voted for violations

of the Convention on both aspects of the issue under that provision.

© European Union, https://eur-lex.europa.eu, 1998 - 2024
Active Products: EUCJ + ECHR Data Package + Citation Analytics • Documents in DB: 398107 • Paragraphs parsed: 43931842 • Citations processed 3409255