Order of the Court (Grand Chamber) of 9 June 2010.
European Commission v Schneider Electric SA.
C-440/07 P • 62007CO0440 • ECLI:EU:C:2010:324
- 87 Inbound citations:
- •
- 0 Cited paragraphs:
- •
- 0 Outbound citations:
Order of the Court (Grand Chamber) of 9 June 2010 – Commission v Schneider Electric
(Case C‑440/07 P)
Appeal – Partial annulment of the judgment under appeal – Final judgment where the state of the proceedings so permits – Non-contractual liability of the Community – Evaluation of the loss
1. Non-contractual liability – Damage – Evaluation – Criteria – Making good of various expenses borne by an undertaking as a result of the annulment of a decision declaring a merger operation incompatible with the common market and of a decision ordering the separation of the entities merged (Art. 288, second para., EC) (see paras 41-50)
2. Procedure – Costs – Rules applicable (see paras 51-53)
Re:
Operative part:
1.Fixes the amount of the loss to be made good in point 3 of the operative part of the judgment of the Court of Justice of the European Communities of 16 July 2009 in Case C-440/07 P Commission v Schneider Electric [2009] ECR I-6413 at EUR 50 000.