Lexploria - Legal research enhanced by smart algorithms
Lexploria beta Legal research enhanced by smart algorithms
Menu
Browsing history:

Judgment of the General Court (Sixth Chamber) of 13 February 2012.

Budapesti Erőmű Zrt v European Commission.

T-80/06 • 62006TJ0080 • ECLI:EU:T:2012:65

  • Inbound citations: 19
  • Cited paragraphs: 0
  • Outbound citations: 3

Judgment of the General Court (Sixth Chamber) of 13 February 2012.

Budapesti Erőmű Zrt v European Commission.

T-80/06 • 62006TJ0080 • ECLI:EU:T:2012:65

Cited paragraphs only

Judgment of the General Court (Sixth Chamber) of 13 February 2012 — Budapesti Erőmű v Commission (Joined Cases T‑80/06 and T‑182/09)

State aid — Wholesale electricity market — Favourable terms granted by a Hungarian public undertaking to certain power generators under power purchase agreements — Decision to initiate the procedure laid down in Article 88(2) EC — Decision declaring the aid incompatible with the common market and ordering its recovery — New aid — Private investor test

1. Actions for annulment — Actionable measures — Measures producing legal effects — Commission decision to open a formal investigation procedure into a State measure in the course of implementation and to classify it provisionally as new aid — Admissibility (Arts 87(1) EC, 88(2) and (3) EC and 230 EC) (see paras 37‑39, 41)

2. State aid — Existing aid and new aid — Accession of a new Member State to the European Union — Distinction by reference to the specific rules established in Annex IV of the Act of Accession — Possibility of classifying as new aid a measure not initially constituting State aid — Advantageous conditions granted to certain Hungarian electricity producers — Classification as new aid (Arts 87(1) EC and 88(1) and (3) EC; Act of Accession of 2003, Annex IV; Council Regulation No 659/1999, Art. 1) (see paras 50, 51, 54‑56, 59)

3. State aid — Concept — Assessment according to the private investor test — Purchasing agreements for electricity guaranteeing to electricity producers a minimum purchase quantity and the remuneration of fixed costs and capital — Included (Art. 87(1) EC) (see paras 65, 66, 69, 71, 77‑79, 82)

4. State aid — Effect on trade between Member States — Adverse effect on competition — Criteria for assessment — Liberalised sector (Art. 87(1) EC) (see paras 95‑97)

5. State aid — Commission decision finding aid incompatible with the common market and ordering its recovery — Possible for the Commission to leave to national authorities the task of calculating the exact amount to be recovered — Indication of a repayment methodology in the final decision — State aid in the electricity market (Art. 88 EC; Council Regulation No 659/1999, Art. 14(1)) (see paras 106‑110, 113‑115)

6. State aid — Examination by the Commission — Purchasing agreements for electricity guaranteeing to electricity producers a minimum purchase quantity and the remuneration of fixed costs and capital — Adoption of a single decision for all the purchasing agreements after examining the similarities of all the agreements and their specific elements — Lawfulness (Art. 87(1) EC) (see paras 129‑131)

7. Actions for annulment — Grounds — Misuse of powers — Meaning (Art. 230 EC) (see para. 140)

8. State aid — Commission decision to open a formal investigation procedure in respect of aid — Duty to state reasons — Scope (Arts 88(2) and (3) EC and 253 EC; Council Regulation No 659/1999, Art. 6) (see para. 143)

Re:

Operative part

The Court:

1.Dismisses the actions;

2.Orders Budapesti Erőmű Zrt to pay the costs.

© European Union, https://eur-lex.europa.eu, 1998 - 2024
Active Products: EUCJ + ECHR Data Package + Citation Analytics • Documents in DB: 393980 • Paragraphs parsed: 42814632 • Citations processed 3216094